Question 1 of 168A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact project implementation. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Meet with the team member to understand their concerns and/or issues
Meeting privately with the team member is correct because it reflects servant leadership and uses emotional intelligence to uncover hidden root causes. Reassigning work or immediately escalating bypasses the necessary coaching and interpersonal dialogue.
Question 2 of 168An agile project has a documented list of requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority. What should the project manager recommend?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Ensure the product owner determines the priority based on a product roadmap, release plan, and iteration plan.
Ensuring the product owner determines the priority based on roadmap and release plans is correct because managing and prioritizing the backlog is strictly the product owner's responsibility. The team should not drive business priority sequencing without them.
Question 3 of 168A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed. In which project document should the project manager record the concern?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Risk register
Because the concern is a potential future problem, it is classified as a risk and belongs in the risk register. An issue log is incorrect because the event has not yet materialized into an active problem that requires immediate resolution.
Question 4 of 168A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project. What should the project manager have done to prevent this?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Developed a detailed, phased procurement management plan including all activities required and had the client approve it.
Developing a detailed phased procurement management plan and obtaining client approval is the correct answer. This plan defines how procurement processes align with the schedule, ensuring contract durations cover the entire project. Negotiating a second contract later is reactive and violates proactive planning principles.
Question 5 of 168In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Start the organization's change control process via a change request.
Starting the change control process via a change request is the correct action. The new environmental reinforcement work represents an unscoped change. PMI standards require evaluating scope impacts through formal change control before implementation.
Question 6 of 168A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders. What should the internal project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Host an alignment session with stakeholders to formalize the project requirements.
Hosting an alignment session to formalize project requirements is the correct action. The project manager needs to ensure a shared understanding of supplier responsibilities and customer roles. This promotes clarity and helps define acceptance criteria.
Question 7 of 168A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Review organizational process assets (OPAs) and perform analogous estimating.
Reviewing organizational process assets and performing analogous estimating is the correct action. Leveraging historical data and lessons learned from a similar prior project provides a sound basis for early planning under strict time constraints, saving crucial estimation time.
Question 8 of 168A pharmacy needs to launch a medication delivery service. An interdisciplinary team was created in order to have the service ready in one-month when it usually takes five months to complete. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Assist the team in proposing a minimum viable product (MVP).
Assisting the team in proposing a minimum viable product is the correct action. In an extremely time-constrained project, the project manager should help the team deliver the most valuable features first. This ensures business value within the tight deadline.
Question 9 of 168A project manager has recently been asked to take over an existing project. The project manager would like to determine how the project has been progressing by tracking features that are in progress, completed, or scheduled to be worked on. Which of the following can help the project manager assess the state of the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Cumulative flow diagram
The Cumulative Flow Diagram is the correct answer. It visually displays work in progress, completed work, and work yet to start across time. This makes it the ideal tool for assessing the current state of an ongoing agile or hybrid project.
Question 10 of 168A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary. What should the project manager have done before the beginning of the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.
Preparing an inception deck and clearly explaining the purpose and benefits of agile ceremonies before starting is the correct action. An inception session ensures team alignment on agile principles and practices, fostering buy-in and collaboration rather than forced compliance.
Question 11 of 168An organization is transitioning from a predictive to an agile approach. What should the project manager do to ensure that the agile approaches will bring about significant change?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Obtain full management support
Obtaining full management support is critical because transitioning to agile requires leadership buy-in and sponsorship. For the exam, remember that management provides the vision, removes organizational barriers, and empowers teams. Training the team is helpful but fails without foundational executive support.
Question 12 of 168A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they feel it is a waste of time. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Welcome and involve the contractors as part of the project team.
Welcoming and involving contractors as part of the team is correct because project managers must foster collaboration and inclusivity. A strong exam cue is to favor servant leadership and team integration over punishing or isolating external members, which ensures everyone shares ownership of project success.
Question 13 of 168A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all. How should the project manager proceed?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Calculate the costs for each option in each location and compare the net present value (NPV) for each.
Calculating the costs and comparing the net present value for each option is the correct choice. Net present value is the most reliable financial metric because it accounts for the time value of money across all cash flows. Avoid payback period as it ignores overall profitability.
Question 14 of 168Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information should the project manager provide so that senior management can get a broader view of the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Milestones status report
Sharing a milestone status report is correct because it summarizes major accomplishments and progress toward objectives. On the exam, remember that executives need a concise, high-level view for strategic decision-making. Providing a resource breakdown structure would overwhelm them with unnecessary operational details.
Question 15 of 168A project schedule risk has turned into an issue. The project manager foresees delays in project execution. What should the project manager do to resolve the issue?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Work with relevant stakeholders to determine possible solutions
Working with relevant stakeholders to determine possible solutions is correct because project managers must take ownership of issue resolution through collaboration. For the exam, always try to solve problems at the project level first. Escalating immediately fails because you must analyze the impact beforehand.
Question 16 of 168A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Ensure the team receives continuous feedback from customers/users.
Ensuring the team receives continuous feedback from customers is correct because iterative validation keeps deliverables aligned with expectations. On the exam, watch for prevention questions in agile environments. Updating plans or submitting change requests are reactive steps taken after the misalignment occurs.
Question 17 of 168A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management competencies. The project manager explains that the exiting team members were lazy. What should the project manager do to prevent this high turnover rate from continuing?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Develop relationship skills as a leader and also develop the teams' emotional intelligence skills.
Developing relationship skills and team emotional intelligence is correct because leadership competencies foster trust and retention. A practical exam cue is to choose proactive personal development over punishing rules. Blaming the team ignores the systemic feedback from exit interviews and worsens morale.
Question 18 of 168A project manager is performing the role of scrum master for a team of developers. There is a conflict among the developers generated by differences in how a feature can be delivered. The project manager organized a few spikes to resolve this conflict. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Allow the team to decide on their own which option should be implemented.
Allowing the self-organizing team to decide is correct because agile teams own their technical delivery decisions. Avoid forcing consensus or escalating; the servant leader facilitates the process but trusts the team to choose after gathering spike data.
Question 19 of 168A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Net present value (NPV)
Net present value is correct because it evaluates the long-term financial return of building versus buying by discounting future cash flows to today's value. Remember that earned value measures project performance, not initial financial decisions.
Question 20 of 168During the closing process, the project manager learns that one deliverable is not meeting customer expectations. How should the project manager proceed?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Review the deliverable requirements, check the customer approval criteria, and proceed accordingly
Reviewing the requirements and checking the documented acceptance criteria is correct because closure relies on objective evidence rather than subjective expectations. Meeting to negotiate scope is a strong distractor but bypasses the formal verification step.
Question 21 of 168A company is transitioning from a predictive approach to an agile approach. The team members work remotely, and some have personal conflicts that make them unavailable for some project ceremonies. The product owner has made it clear that the agenda is very tight and the team should make every effort to participate in all ceremonies. What should the project manager, as a servant leader, do to address this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Ask the team members to decide collectively on how to support the team.
Asking the team to decide collectively is correct because agile teams self-organize and must own their working agreements to solve scheduling conflicts. Conducting separate ceremonies or excluding members fractures the collaborative team environment.
Question 22 of 168While working on a proposal for a national-level solution, a new project manager finds that the proposal is asking for compliance from various organizations and policies. The project manager understands that while several compliances are in place, some of the specific regulatory needs for this project are not in place. Senior management advised the project manager to overlook these compliance problems, because they will be ready when that stage of the project is reached, and to continue building the proposal. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Verify the regulatory requirements and establish a strategy for compliance.
Verifying the regulatory requirements and establishing a compliance strategy is correct because the project manager must ensure the proposal adheres to all legal and ethical standards before proceeding. Documenting the interaction or using alternatives happens later.
Question 23 of 168A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Study and determine the appropriate leadership style suitable for the team.
Studying and determining the appropriate leadership style is correct because project managers must tailor their approach to the current team dynamics and maturity before taking action. Immediately confronting the team or forcing an agile approach ignores situational context.
Question 24 of 168A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Refer to the risk register and follow the mitigation plan.
Reviewing the risk register and following the mitigation plan is correct because a previously identified risk requires executing its planned response. Documenting changes or requesting an extension is a secondary step after applying the predetermined strategy.
Question 25 of 168To prevent influential stakeholders from dominating product delivery decisions, the product owner decided to use planning poker. What is a key advantage of using this technique?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Ensures active project team participation
Ensuring active team participation is correct because planning poker requires all team members to reveal estimates simultaneously, preventing dominant personalities from anchoring the discussion. More accurate estimates are a beneficial result, not the core mechanism.
Question 26 of 168Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval. What should the project manager have done to prevent this from happening?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Validated each stakeholder's understanding during the kick-off meeting
The project manager should have validated that all stakeholders had a common understanding of the project objectives during the kickoff meeting. Simply sending meeting minutes afterward is passive and fails to confirm real-time alignment.
Question 27 of 168An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Schedule a session with stakeholders to understand the impact.
The project manager should first schedule a session with stakeholders to collaboratively assess the impact of the operating system termination. Jumping straight into adding backlog items skips the necessary evaluation of the change.
Question 28 of 168A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Coordinate a meeting to understand the situation and resolve any conflicts.
The project manager should coordinate a meeting to understand the situation and actively resolve any conflicts. Escalating to regional managers without first attempting to facilitate an agreement bypasses direct servant leadership.
Question 29 of 168A company has started developing a new product. During execution the project team notices that another competitor has launched a product with very similar functionalities and a cheaper market price. What should have been done differently to avoid this scenario?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. A minimum viable product (MVP) should have been released to get feedback from the market.
Releasing a minimum viable product early would have allowed the team to test the market and gather actionable customer feedback. Adopting an iterative approach without actually delivering value to users does not solve the issue.
Question 30 of 168A project team with members from many different countries is struggling to cooperate. The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase. The project is beginning to fall behind schedule. What can the project manager do to move the team to the norming phase?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Plan social activities to help foster stronger interpersonal relationships and identify shared goals.
Planning social activities helps foster interpersonal trust and allows the team to identify shared goals, moving them toward norming. Highlighting the schedule impact only increases pressure and fails to resolve underlying conflicts.
Question 31 of 168A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Negotiate a common agreement with the involved stakeholders regarding the requirements.
The project manager should act as a negotiator to help the involved stakeholders reach a mutual agreement on requirements. Allowing the project team to decide inappropriately shifts stakeholder conflict resolution downward.
Question 32 of 168A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach. Recently, the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large, complex project with the same group of stakeholders. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project.
Discussing the pros and cons of agile with the stakeholders to choose the approach is correct because tailoring requires collaborative alignment. Simply mandating agile training ignores the need for stakeholder buy-in before transitioning complex projects.
Question 33 of 168A team has individual daily start times for each team member. Sometimes the overlap between team member working hours is short. During those times, the interactions and work as a team are reduced and ineffective. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Ask the team to define a team charter and agree on core working hours.
Creating a team charter with agreed core hours empowers the team to self-organize and maximize collaboration. Mandating strict schedules fails because it ignores the servant leadership principle of letting the team establish its own working agreements.
Question 34 of 168A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Include a representative from the customer to work collaboratively with the team.
Including a customer representative to work collaboratively with the team ensures continuous feedback and alignment. Holding a workshop alone is weaker because it provides only temporary clarification rather than ongoing engagement throughout delivery.
Question 35 of 168A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in meetings with end users. The meetings have been slowing down project progress. What should the project manager do to keep the deployment on track while obtaining stakeholder approval?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Put all of the requirements, priorities, and progress on a visible board, share it with all entities, and decrease the number of meetings.
Using a visible information radiator decreases unnecessary meetings while maintaining transparency and obtaining stakeholder approval. Mandating a daily meeting or stopping attendance entirely fails to solve the underlying communication bottleneck and damages valuable stakeholder engagement.
Question 36 of 168A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile. What should the project manager recommend?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Negotiate special arrangements for an agile pilot project.
A pilot project builds trust through demonstrated results without forcing a risky, large-scale organizational transition. Detailed work instructions contradict agile principles, and hiring contractors ignores the fundamental need to build internal capability and secure business buy-in.
Question 37 of 168During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Meet with the stakeholder prior to the meeting to obtain their opinion
Meeting the stakeholder beforehand ensures their critical perspective is included in the scope change discussion. Proceeding directly with the change control board without their input risks alienating a key partner and making poorly informed decisions.
Question 38 of 168A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client. What should the project manager do before sending the information to the client?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Work with the team to understand their views and add the appropriate dependencies and risks.
Agile estimation requires collaborative team input to identify dependencies and risks accurately before sending details to the client. Working independently violates this core principle and leads to unrealistic estimates, despite the temptation to directly deliver a prototype.
Question 39 of 168A project has been successfully completed. The project was ahead of schedule, under budget, and delivered the expected benefits. The project sponsor was satisfied and distributed recognition certificates to key project team members. However, the project sponsor accidentally forgot to issue a certificate to a key team member. How should the project manager treat the missed key team member to avoid disappointment and demotivation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Explain the situation to the team member and follow up with a reward and recognition for them.
Explaining the oversight transparently and securing proper recognition maintains fairness and trust. Simply requesting another certificate later ignores the immediate disappointment, while offering a public lunch feels like an inadequate excuse rather than formal recognition.
Question 40 of 168While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Analyze the impact of the change request on the project.
Analyzing the impact on scope, schedule, and cost is the mandatory first step before any change decision is made. Immediately seeking formal approval or rejecting it outright bypasses the necessary evaluation required to make an informed choice.
Question 41 of 168A project manager is leading a program execution and has challenges, because a project team waits for every decision to be made by the project manager. The progress of the team is slow because the project manager is the bottleneck. Upon assessing the situation, the project manager realized that the team members can handle the work on their own. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Revise the roles and responsibilities and empower the team to make their own decisions.
Revising roles and empowering the team to make their own decisions eliminates the bottleneck and applies servant leadership principles. Creating a feedback process merely formalizes the dependency, whereas shifting decision-making authority directly accelerates delivery and builds team capability.
Question 42 of 168The project manager is reviewing the program risks and issues with key stakeholders. One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Risk register
The risk register is the correct artifact because it tracks identified risks alongside their specific triggers and potential timing. The risk management plan merely outlines the methodology for handling risks, whereas the register captures the actual project-specific data requested.
Question 43 of 168A lead project manager for an agile project needs to prioritize requirements, define the scope of the initial product, and deliver the approved scope in a series of multiple versions. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Work with the product owner to evaluate and prioritize the requirements.
Working with the product owner to evaluate and prioritize requirements is correct because the product owner holds final authority over backlog ordering. The project manager acts as a facilitator to ensure alignment, but should never unilaterally dictate priorities based on stakeholder hierarchy.
Question 44 of 168A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers' group was not consulted, and they use the site for a monthly market. What should the project manager do to move forward with the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Discuss the project objectives with all stakeholders. including the farmers' group, and review their requirements.
Discussing the project objectives with all stakeholders, including the farmers' group, and reviewing their requirements is the correct approach. This promotes inclusive stakeholder engagement and helps identify mutually acceptable solutions. Ignoring them or simply documenting a risk avoids necessary collaboration.
Question 45 of 168A project manager is managing a government project that targets the development of small businesses in remote towns. The project team is having difficulty conducting entrepreneurship training in some of the targeted towns because the local municipal governments will not authorize the training. As a result of the delay, project implementation is at risk. What is a probable reason for this?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. The project did not identify and engage the correct stakeholders.
The most probable reason is that the correct stakeholders, meaning the local municipal authorities, were not identified and engaged early. In government projects, failing to recognize local decision-makers inevitably leads to delays and resistance. Building centers without authorization is an unrealistic distractor.
Question 46 of 168A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue.
Holding a meeting with the project team and stakeholders to determine the best response is the correct approach. This promotes collaboration and enables the development of an effective issue resolution plan. Avoiding the issue or halting the project are passive and incorrect actions.
Question 47 of 168A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who used to be a high performer was not able to complete their work on time. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Talk to the team member to determine why their performance changed.
The project manager should talk directly with the team member to uncover the root cause of the sudden performance drop. Involving human resources or functional managers immediately is a premature escalation before attempting personal coaching and collaborative problem-solving.
Question 48 of 168A project sponsor asked the product owner to deliver the functionality that provides the highest return on investment (ROI) as soon as possible. Which artifact should the project lead use to track benefits?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Product backlog
The product backlog is the primary artifact used to prioritize and track the delivery of features based on their value and return on investment. Requirements backlog is a distractor because agile teams officially prioritize work through the product backlog.
Question 49 of 168A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Perform a detailed assessment to analyze the impact.
Performing a detailed impact assessment is required before deciding how to handle any requested change, regardless of the project phase. Rejecting the change outright bypasses formal change control procedures, while instantly applying schedule compression acts without proper analysis.
Question 50 of 168During a project's third iteration, two of the existing team members were replaced. As the project entered the next iteration, the team velocity dropped and the performance started to slip. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Guide the team to revert back to the forming and storming stages.
According to Tuckman Ladder, adding new members resets the team dynamic, requiring the project manager to coach them back through the forming and storming stages. Escalating performance issues to human resources happens only if coaching fails to restore productivity.
Question 51 of 168During the planning stage of a project, the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during meetings. How should the project manager handle this moving forward?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Allocate time to gain buy-in from the stakeholder prior to key decision meetings.
Gaining buy-in from the stakeholder before key meetings is the best approach. This proactive engagement strategy minimizes disruptions. Updating the risk register alone is too passive, as it does not actively solve the interpersonal issue.
Question 52 of 168A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches. What does the project manager need to do first in order to have good project performance?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Assess the required training per team member.
Assessing the required training per team member is the correct first step to identify specific skill gaps. Providing uniform training to everyone wastes resources, while changing the team entirely avoids necessary professional development.
Question 53 of 168One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Understand the reason for the team member's absence and encourage them to attend future meetings.
Understanding the reason for the absence and encouraging attendance is the correct approach. Using emotional intelligence builds rapport. Mandating attendance through ground rules might cause resentment without fixing the underlying conflict.
Question 54 of 168Toward the end of a project, the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Review the requirements traceability matrix.
Reviewing the requirements traceability matrix verifies if the deliverables meet the approved business needs. This tool links requirements to product functions. The quality management plan is too broad for identifying specific missed requirements.
Question 55 of 168A project manager has recently joined a small company. The company's chief operating officer (COO) asked the team to skip some steps in the process in order to work more quickly. The project manager wants to ensure that these steps are not skipped in the future. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Schedule a review of the process steps with the team and the COO.
Scheduling a review with the team and the COO builds transparency and shared understanding. This approach explains the value of each step. Unilaterally notifying the team ignores the executive input and creates future conflict.
Question 56 of 168An agile project team discovers that they are unable to implement a feature completely in the first iteration. The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized. What should the team do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Split the feature into smaller subfeatures, implement them, and then deliver them incrementally in multiple iterations.
Splitting the feature into smaller subfeatures allows the team to deliver value incrementally across multiple iterations. This aligns perfectly with agile principles. Asking the customer to simplify the feature compromises critical business needs.
Question 57 of 168A project manager is working on a large project with a very difficult client. During the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early. How should the project manager approach this?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Develop a business case and submit it to the client.
Developing a business case allows the project manager to objectively justify the additional time and funding. This gives the client the data needed for decision-making. Updating the plan without approval violates change control procedures.
Question 58 of 168A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member's deliverables do not meet the requirements. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.
Discussing the creation process first helps uncover if a simple requirements misunderstanding caused the noncompliant deliverables. Jumping straight to disciplinary threats or demanding immediate rework skips root cause analysis, which is essential for fixing global team communication gaps.
Question 59 of 168A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Assess the schedule impact and evaluate the most feasible solution to keep the project on track.
Assessing the schedule impact and evaluating feasible solutions ensures the project manager makes an informed, data-driven decision during a critical path crisis. Unilaterally holding the shipment or shipping as is without impact analysis risks causing massive schedule delays.
Question 60 of 168A project manager is managing an agile project for the first time. Early on, the project manager discovers the team is struggling to agree on the scope of a feature during a sprint. How should the project manager help the team resolve the issue?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Encourage the team to collaborate to resolve their understanding of the feature.
Encouraging the team to collaborate directly applies agile values of self-organization and shared understanding to resolve the scope confusion. Having a senior member dictate the scope violates team empowerment, while simply moving on fails to deliver business value.
Question 61 of 168A project team has recently finished a sprint for developing two features for a fleet management system. Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to what has occurred. What can the project manager do to help increase the team's motivation and engagement with the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Perform a sprint retrospective with the project team members.
Facilitating a sprint retrospective provides a safe space for the team to openly discuss conflicts and processes, which rebuilds trust and motivation. Reviewing sprint planning or progress focuses on mechanics rather than resolving the underlying team dynamics.
Question 62 of 168A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule. What should the project manager do next to minimize the impact on the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Review and update the issue log and determine if any alternative components can be offered
Capturing the issue in the issue log and exploring alternative components directly addresses the delay while maintaining project momentum. Avoid immediately replacing the vendor or extending deadlines; focus on proactive problem-solving and impact analysis before escalating.
Question 63 of 168As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail. What should the project manager do first to decide how to manage this project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Determine the most appropriate life cycle approach for the project
Evaluating the clarity of requirements allows the project manager to select the most suitable development approach. A hybrid approach might seem viable later, but you must first assess the overall project context and uncertainty before deciding on the life cycle.
Question 64 of 168A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Review the quality management plan with the senior manager
Reviewing the quality management plan transparently demonstrates that quality processes are established and being followed. Dismissing the concern by stating standards are already approved fails to engage the manager constructively or validate their specific worries.
Question 65 of 168An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached. Which approach should be used in this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. An iterative approach starting with the highest value epic.
Starting with the highest value epic using an iterative approach ensures maximum business value is delivered early before the volatile budget depletes. An incremental approach focuses on completing functional subsets rather than refining the most valuable features first.
Question 66 of 168An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay. How should this situation be handled?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product.
Adding an experienced professional to the team fosters internal mentoring and skill growth while maintaining project ownership. Outsourcing the work completely or using external consultants prevents the team from developing the necessary expertise themselves.
Question 67 of 168A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity. What should the team member do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity
Informing the scrum master about the request and its productivity impact allows leadership to shield the team and enforce proper communication channels. In a hybrid environment, routing requests directly to a change control board bypasses necessary initial project manager triage.
Question 68 of 168A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Perform trend analysis.
Trend analysis uses historical performance data to predict future performance, allowing the project manager to anticipate potential schedule or cost deviations and take proactive action.
Question 69 of 168A client has requested that a product be implemented in 4 months and is ready to increase their budget to do this quickly. The project manager cannot comply with the request with the current resources or even additional resources. The project manager estimates that 8 to 12 months are needed for the product to go live. What should the project manager do to address this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Discuss with the client alternative approaches to deliver the minimal viable product (MVP) in 4 months and the rest later
Discussing with the client to redefine scope and deliver a minimum viable product within the requested timeframe aligns with value delivery principles. This approach balances stakeholder expectations, feasibility, and value realization.
Question 70 of 168A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Acknowledge the impediments and facilitate their resolutions.
Acting as a servant leader, the scrum master must acknowledge team impediments and actively facilitate their resolution. Escalating to the product owner or delaying action inappropriately shifts these operational blockers.
Question 71 of 168A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business. What should the project manager do to ensure business value is delivered early?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Break down the deliverables into sprints and deliver value incrementally
Breaking down deliverables into sprints delivers business value incrementally and early. Creating a detailed plan or fast-tracking ignores agile principles for innovation projects. Focus on iterative delivery to ensure continuous value realization.
Question 72 of 168A senior project manager is assigned to lead a team of project managers to run a large initiative. One of the key stakeholders often bypasses the senior project manager and gives instructions to the other project managers directly. What should the senior project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Evaluate the stakeholder analysis to identify the stakeholder's influence.
Evaluating the stakeholder analysis helps you understand the stakeholder's influence and communication preferences. Escalating immediately to sponsors is too confrontational without first analyzing their engagement level and adjusting the communication plan.
Question 73 of 168A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables. What should the project manager do to ease the situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Talk to the customer and project team member separately to assess the issue and decide on the next steps.
Talking to the customer and team member separately is the best approach. It allows you to understand both perspectives, identify the root cause, and decide on appropriate next steps. Apologizing or removing the member without facts violates emotional intelligence and servant leadership principles.
Question 74 of 168A project manager has been keeping track of impediments that have been discussed with the team in daily meetings. The risk register continues to grow, and only a few impediments have been mitigated. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Identify any critical impediments that may affect the project.
Identifying critical impediments that affect the project is the correct approach. You must analyze and prioritize blockers to focus on those with the most impact on value delivery. Simply asking the team to resolve everything or halting development ignores effective servant leadership and risk prioritization.
Question 75 of 168A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy
Immediately discussing the issue with the project sponsor and requesting to revisit the budget is the correct action. The charter defines high-level objectives, and significant missing costs must be escalated to ensure alignment with business goals. Starting the project or reducing quality violates stewardship principles.
Question 76 of 168A project manager is about to kick off a new project with the team. Due to an unprecedented event, all team members are currently working remotely. How should the project manager ensure the continuity of information sharing for the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Setup clear communication channels with increased team interactions online.
Setting up clear communication channels with increased online interactions is the correct answer. Structured tools like video calls and shared dashboards ensure visibility and collaboration in a remote environment. Sending excessive emails or reports creates information silos and lacks real-time collaborative engagement.
Question 77 of 168A project manager has been approached by the project sponsor about adding to the project scope. How should the project manager accommodate this request?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Create a change request for the change control board (CCB) to review.
Creating a change request for the Change Control Board to review is the correct answer. According to PMI standards, all scope changes must be formally documented, analyzed for impact, and approved through integrated change control. Adjusting the schedule directly bypasses this mandatory formal process.
Question 78 of 168During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Update the issue log and act to minimize the impact
Updating the issue log and acting to minimize the impact is the correct approach. A supplier bankruptcy is an immediate issue requiring documentation and mitigation. Escalating delays or updating the schedule first bypasses the essential problem-solving step.
Question 79 of 168A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing. Which action should the project manager take next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Meet with the development team to review and assess the requirements specifications.
Meeting with the development team to review and assess the requirements is the correct approach. The project manager should first analyze the gap to determine the impact on scope and quality. Submitting a change request prematurely skips this necessary analysis.
Question 80 of 168An organization is transitioning to agile and a project has been chosen as a pilot. The assigned project manager only has experience using predictive approaches, but the project manager is now required to use agile approaches with the help of an agile coach. During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework. What should the project manager do in this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Promote collaboration to help remove the obstacles for the team
Promoting collaboration to help remove obstacles for the team is correct because servant leaders must clear systemic barriers. A practical exam cue is that agile project managers act as facilitators. Creating a dedicated sprint fails because it wrongly halts value delivery to fix organizational process issues.
Question 81 of 168Midway through the execution of an agile project there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Schedule a meeting with the team to assess the impact of the change
Scheduling a meeting with the team to assess the impact of the change is correct because project managers must act as integrators when strategy shifts. A helpful exam tip is to always evaluate how changes affect objectives before taking action. Updating the backlog independently skips this required team analysis.
Question 82 of 168In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing. The software update will be accomplished using an agile approach in order to minimize risk. The machine procurement, installation, and integration will be accomplished using predictive approaches. What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Weekly colocated meetings with the relevant stakeholders
Weekly colocated meetings with relevant stakeholders is correct because regular coordination between agile and predictive workstreams is essential. A great exam cue is that frequent, high-bandwidth communication promotes integration and timely decision-making. Written status reports lack the interactive collaboration needed here.
Question 83 of 168A project manager is using a hybrid approach for a project. The project team created and reviewed the risk log with the stakeholders at the beginning of the project. However, midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies. When should the risks be reviewed to ensure alignment between the project team and the stakeholders?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. During each iteration and review
In a hybrid environment, risks are continuously reviewed during each iteration and review meeting to maintain alignment. Retrospectives focus strictly on internal team process improvements rather than formal stakeholder risk alignment.
Question 84 of 168A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Explain the third-party supplier situation to the client and request payment.
The project manager should transparently communicate the supplier's situation to the client and request early payment. Reassigning resources or securing loans violates project boundaries and financial stewardship.
Question 85 of 168A project manager is assigned to lead a hybrid innovation project. During a meeting with the sponsor and major stakeholders, the project manager realizes that the requirements are unclear. What should the project manager do in this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Help the sponsor and major stakeholders to craft the product vision.
The project manager should act as a facilitator by helping the sponsor and stakeholders craft a clear product vision. Logging unclear requirements as a risk delays necessary proactive alignment and does not resolve the ambiguity.
Question 86 of 168A company is set to execute a project across different localities and countries. Right before execution, a press release from one of the impacted communities expresses disapproval of the project. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Engage all critical stakeholders and align project objectives with expectations from the community.
The first step is to engage the critical stakeholders and align project objectives with the community's expectations. Updating the risk register or communications plan is premature before fully understanding their concerns.
Question 87 of 168A project manager is using a subcontractor for mobile application development. When the project team tests the application, they realize it does not comply with the new company user-interface standards. Even though these new standards were not included in the statement of work (SOW), the subcontractor agrees to the additional scope as long as payment for this additional work is paid immediately. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Initiate a change request and review the contract to evaluate the payment options before responding.
Initiating a change request and reviewing the contract is correct because any new scope requires formal integrated change control. Negotiating pricing or approving payments before evaluating the contract terms bypasses procurement governance.
Question 88 of 168The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders. This issue is putting the project schedule at risk. What should the project manager do first to facilitate the approval of project requirements?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Identify the source of the disagreement
Identifying the source of the disagreement is correct because you must find the root cause of a conflict before attempting to resolve it. Performing a stakeholder analysis is a strong distractor, but it is too broad when a specific disagreement is actively causing schedule delays.
Question 89 of 168As a project is reaching completion, the project sponsor tells the project manager to immediately close the project and to move on to another project. Which critical task should the project manager complete before closing the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Archive all the project documents following the organization's accepted practices so the documents can be used in other future projects.
Archiving project documents is correct because formal closure requires updating organizational process assets. While updating the risk register seems plausible, archiving historical data and lessons learned is the definitive administrative closure step.
Question 90 of 168A project manager is assigned to a project. The project schedule and costs are tight, and the project manager determined that there is a lack of resources to deliver this project. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Identify the resource requirements and communicate them to the stakeholders seeking resources.
Identifying the specific resource requirements and communicating them to stakeholders is correct because you must first quantify the gap before asking for help. Updating the risk register is a logical next step, but communication must happen first.
Question 91 of 168A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Define the project scope with the stakeholders and determine how formal acceptance will be obtained
Defining the project scope and determining how formal acceptance will be obtained is correct because vague expectations require measurable scope and clear acceptance criteria. Reviewing the competitor's app is a tempting distractor, but it does not establish project boundaries.
Question 92 of 168A project manager is leading a project which shows a trend to exceed the cost baseline. What should the project manager do first to manage the budget?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Meet with the project team to analyze the actual cost to determine deviations
Meeting with the project team to analyze actual cost deviations is correct because you must diagnose the root cause of variances before taking action. Issuing a change request is a common trap; you should only request more budget after analyzing the data.
Question 93 of 168A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Facilitate a problem-solving session with the team to analyze the problem
Facilitating a problem-solving session empowers the team to collaborate on finding a solution. Organizing an early retrospective is a distractor because retrospectives focus on process improvements, not resolving immediate technical impediments during a sprint.
Question 94 of 168A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Analyze both projects to determine the most effective use of common resources
Analyzing both projects to determine the most effective use of shared resources applies systems thinking to resolve constraints. Applying fast-tracking is a clear trap because the scenario explicitly states there are no activities that can be overlapped.
Question 95 of 168A project sponsor has requested a trend analysis of all risks that the project has monitored over the past 12 months. What should the agile project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Extract this from the project risk register tracking tool and issues log
Extracting historical risk data from the tracking tool and issue log is correct because trend analysis relies on documented project artifacts. Brainstorming in a stakeholder meeting is a distractor, as it produces subjective opinions rather than actual monitored data.
Question 96 of 168In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery. What should the project manager do to help this team member?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Mentor the team member on a regular basis.
Mentoring the team member regularly is the best approach because it builds confidence and independence. Watch for coaching traps like delegating to another senior member, which ignores the servant leadership duty to develop the team directly.
Question 97 of 168A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support at project completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology. What should the project manager do to resolve the conflict?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Acknowledge the lack of approval and focus on a resolution that will benefit the customer.
Acknowledging the lack of approval and focusing on a customer-benefiting resolution balances innovation with compliance. Avoid blindly promoting the technology or strictly adhering to plans without addressing the underlying operational governance risk.
Question 98 of 168A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project timelines have slipped, and the staff is overwhelmed. What should the project manager do to help the company meet their financial objectives?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Prioritize the projects, giving higher priority to projects that will increase profit
Prioritizing projects that increase profit aligns team efforts with strategic value delivery. Hiring more staff or simply fast-tracking everything fails because it ignores the need to focus limited resources on the highest business value initiatives.
Question 99 of 168A project manager noticed that a team member has been struggling with some tasks, which may ultimately impact the completion date. Team morale is low because they will not get the expected bonus if they do not finish on time. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Acknowledge the team for their accomplishments, encourage them, and offer assistance to avoid future delays.
Acknowledging accomplishments, encouraging the team, and offering assistance demonstrates servant leadership and addresses low morale. Replacing the team member or immediately asking for schedule delays skips the necessary step of identifying obstacles.
Question 100 of 168A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Have a confidential discussion with the team member to identify the root cause
Having a confidential discussion identifies the root cause while maintaining trust and respect. Starting a group discussion fails because it might embarrass the team member and violate psychological safety by airing individual struggles publicly.
Question 101 of 168A software company office will be shut down for repairs, and a project team will be required to work remotely. A few team members have never worked this way and are apprehensive of how they will be able to consistently deliver their work products. What should the project manager do to ensure that the team continues to perform while working remotely?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Identify areas of training for the team to be able to use remote tools for team collaboration.
Identifying training for remote collaboration tools builds confidence and ensures continuity. Reducing scope is incorrect because it artificially punishes the schedule instead of proactively enabling the team to succeed in a new environment.
Question 102 of 168A company is working on a project to develop an integration of their existing systems. There are known issues in production. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Review the quality control processes and procedures.
Known production issues indicate a breakdown in quality control processes, making a review the best first step. While updating the definition of done seems tempting for future prevention, it does not address why existing defects escaped detection in the first place.
Question 103 of 168During the last sprint review, the main stakeholder complained that the product was missing many features they had been expecting. The project team argued that every increment met the acceptance criteria and was approved by the main stakeholder. The cost performance index (CPI) of the project is 1.15 and the schedule performance index (SPI) is 1.43. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Analyze the reason for the gap in understanding with both sides and negotiate a solution.
The project manager must analyze the root cause of the expectations gap and negotiate a collaborative solution. Relying solely on favorable performance indices or strict acceptance criteria ignores the relationship breakdown and misses the opportunity for continuous improvement.
Question 104 of 168A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Organize a team meeting to discuss the next course of action.
Engaging the team promotes collaboration and helps identify the root cause before taking further action on the delayed deadline. Jumping straight to schedule compression or escalating immediately bypasses this necessary problem-solving step and damages team trust.
Question 105 of 168During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings. How should the project manager handle this?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Review the stakeholder engagement plan and put in place any existing actions accordingly
Reviewing the stakeholder engagement plan and implementing appropriate actions directly addresses unauthorized communication. While updating the communications management plan seems viable, you must assess and engage stakeholders first to resolve behavioral gaps before altering documented project strategies.
Question 106 of 168A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing. What should the project lead do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Invite the board member to the next sprint review.
Inviting the board member to the next sprint review is the correct action because this event showcases the completed increment to stakeholders. A retrospective is strictly an internal team meeting focused on process improvement, making it inappropriate for external stakeholders to attend.
Question 107 of 168A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the project is overbudget. What should the project manager have done at the start of the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Adapted a direct management style according to the project team's needs
Adapting a direct management style according to the team's needs provides the necessary structure for inexperienced members to succeed. While establishing goals is helpful, newly hired teams typically lack the baseline cohesion required to thrive under hands-off or fully autonomous approaches immediately.
Question 108 of 168A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Ensure that relevant stakeholders and expectations are identified and assess the component delay
Ensuring relevant stakeholders are identified and assessing the component delay follows the standard procedure for handling unexpected vendor issues. Requesting expedited delivery is a reactive workaround that should only be considered after fully analyzing the actual schedule impact.
Question 109 of 168For some time now, doubts have been raised about who is responsible for delivering a key benefit of a project. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Meet with the stakeholders involved to clearly define their roles and responsibilities with regard to the benefit.
Meeting with stakeholders to clarify roles and responsibilities regarding benefit delivery is the correct action. This ensures accountability, alignment, and ownership of project outcomes. Distractors involving immediate escalation or risk documentation skip the foundational step of clarifying ownership.
Question 110 of 168A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards. In order to ensure this, what should the project manager define and document?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Quality
Defining and documenting quality standards is the correct action. Because the client is known for high-quality products, the subcontractor must establish quality metrics and acceptance criteria. While requirements define what to build, quality standards specifically ensure those requirements meet the expected standards.
Question 111 of 168A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Organize a team meeting to resolve the communication challenges.
Organizing a team meeting to openly discuss the communication issues is the correct action. It allows the team to identify specific problems and agree on preferred communication methods. Simply adding collaboration tools or letting things smooth out naturally does not solve the root problem.
Question 112 of 168A project team has run into an issue with a vendor who is known for a lack of quality. The project manager must ensure that the quality problem is addressed appropriately. What should the project manager do to start the issue resolution process?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Meet with the vendor and request corrective actions.
Meeting with the vendor and requesting corrective actions is the correct first step. Because the problem has already occurred, it is an issue rather than a risk, meaning risk register responses do not apply yet. The project manager must address the vendor directly to resolve it.
Question 113 of 168A project manager is working with an agile team to enhance a product. Due to a tight deadline, the team is trying to crash the schedule by engaging multiple resources to work on the project simultaneously. However, the technical environment is configured to allow only one resource to work on a feature at a time. The team plans to upgrade the technical environment but is unable to agree on a way forward. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Conduct a consensus-building session to decide how to approach the next set of work.
Conducting a consensus-building session is the correct action. The project manager should facilitate collaboration to help the team agree on a path forward, ensuring all perspectives are considered. A standard planning session skips the necessary conflict resolution and alignment.
Question 114 of 168A company has always acquired very specialized services from local companies for its projects. During the planning stage for a regulatory project, the project manager is informed that local vendors would not be able to operate due to an unexpected major event. There is an option to hire the same services from companies in other countries. What should the project manager do in this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Plan to execute the procurement tasks in a virtual environment.
Executing the procurement tasks in a virtual environment is the proactive choice that keeps the project moving forward despite the sudden unavailability of local vendors. Asking for a project extension or holding the project pauses work unnecessarily before trying alternative solutions.
Question 115 of 168A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects, and there is no capacity for any developer to take on additional work. What should the project manager do next to fulfill this resource need?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Determine resource allocation options based on project priority.
The project manager should collaborate with the development manager to evaluate resource allocation options based on overall project priority. Immediately asking the sponsor to rebaseline the schedule is a drastic step taken only after exploring internal negotiation and resource leveling.
Question 116 of 168A project manager sent the first communication about the project management plan to the team. The next day, two field engineers were asking about their roles and the project schedule. What should the project manager have done?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Confirmed that the communication was understood and solicited feedback from the team
Effective communication requires confirming that the message was understood and actively soliciting feedback from the recipients. Simply sending documents assumes perfect transmission, whereas interactive communication ensures clarity regarding roles and schedule expectations.
Question 117 of 168A company's CEO has just returned from a conference on the use of artificial intelligence (AI) and would like the project manager to implement this technology in the organization. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Start developing a business case
Developing a business case is the necessary first step to evaluate the feasibility, expected benefits, and strategic alignment of the new technology before formal project initiation. Gathering requirements happens much later, only after the business case justifies the project.
Question 118 of 168A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses. The country's economy is struggling, and some stakeholders cannot agree on this transformation need. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Review the project business case and update it periodically.
Reviewing and updating the business case ensures the project remains viable and strategically aligned amid changing economic conditions and stakeholder disagreements. A communication management plan addresses information flow but fails to resolve fundamental disagreements over business value.
Question 119 of 168A project has completed the first phase. During the lessons learned meeting, the project manager reported that the project was successful because it was on time, on budget, and on scope. The sponsor objected and said that other project benefits, such as cost reduction of the product and system response time, were not achieved. What may have caused this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. The acceptance criteria were not accurately defined.
Defining acceptance criteria inaccurately caused this issue by focusing solely on the triple constraint. The project lacked measurable targets for business value. Managing benefits at the organizational level does not fix planning flaws.
Question 120 of 168A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Set up a steering committee session to review the project delay.
Setting up a steering committee session to review the delay is the correct first action. Significant impacts require escalation to the governance board. Logging a risk is reactive, and asking for immediate approval skips impact analysis.
Question 121 of 168A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.
Holding virtual daily standups maintains agile collaboration while complying with the directive against in-person meetings. Using online tools ensures communication continues smoothly. Switching to weekly reports breaks the daily feedback loop.
Question 122 of 168In a weekly status meeting with the client, the project manager asks each team member to present how their deliverables are impacting the customer's final product requirements. Which leadership skill is the project manager applying?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Having a holistic and systemic view
The project manager is using systems thinking by connecting individual deliverables to broader customer outcomes. Expecting clear expectations is a strong distractor, but it misses the larger focus on understanding cross-functional impacts.
Question 123 of 168A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders. The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts, which are listed on the project risk matrix. What should the project manager do with regard to community engagement in this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Build channels to extend communication efforts to the local community.
Building direct communication channels is correct because proactively engaging external stakeholders mitigates risks fueled by rumors. Delegating communication to city administration fails because the project manager must own stakeholder engagement.
Question 124 of 168A project manager is managing the transition to operations. The project sponsor wants to ensure that good support is provided to the end users. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Ensure that knowledge is transferred to the operations team.
Transferring knowledge directly to the operations team ensures they can independently support end users. Simply handing over comprehensive documentation is a trap because passive documents do not guarantee true operational readiness.
Question 125 of 168During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays. On which area should the project manager focus?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders
Revisiting the stakeholder engagement plan is correct because approval delays signal misaligned expectations and conflict. Increasing update meetings is a weak distractor that provides status without resolving underlying engagement gaps.
Question 126 of 168In a complex project with several subcontractors, one subcontractor reports a likely delay in the schedule. This could affect the other subcontractors and impact their ability to deliver on time. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Assess the schedule and update the risk register.
Assessing schedule impact and updating the risk register is correct because you must analyze threats before acting. Escalating immediately is a common trap; you should evaluate the data first to avoid unnecessary alarm.
Question 127 of 168An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external dependencies?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Assess consolidated project plans for dependencies, gaps, and continued business value
Reviewing consolidated plans allows the manager to proactively identify dependencies and gaps across the portfolio. Delegating this review to the sponsor improperly offloads a core project management responsibility.
Question 128 of 168A research and development team is finishing up a two-year initiative. The project manager is focused on the closing activities for the project. Which activity should be considered as a priority?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Ensure that knowledge transfer activities are executed as planned.
Prioritizing knowledge transfer ensures the organization retains critical technical insights and operational capabilities. Releasing resources is a tempting distractor, but doing so before transferring knowledge jeopardizes continuity.
Question 129 of 168A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Evaluate the impact and submit a change request.
Evaluating the impact and submitting a formal change request is correct because integrated change control requires analysis before approval. Discussing the change directly with the sponsor skips the required documented evaluation step.
Question 130 of 168The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down. A new project sponsor has recently started with the company but has not had time to meet the project manager. The project is at the point where the issues are significantly impacting delivery of the project. How should the project manager alert the new project sponsor about these concerns?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them
Sending a concise status summary and immediately requesting a focused meeting is the most proactive and respectful way to engage a busy new sponsor. Simply copying them on standard reports or dumping raw data fails to highlight the urgency and drive decision making.
Question 131 of 168A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Issue log
The issue log is the proper project document for tracking and communicating problems that have actively occurred and require immediate resolution. A risk register is incorrect here because the supplier delivery failure is a current reality, not a potential future possibility.
Question 132 of 168A project team consisting of various professionals of different nationalities is struggling to achieve their project deliverables. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Provide the team with support to solve their own problems.
Supporting the team to solve their own problems empowers them, fosters collaboration, and promotes ownership in a diverse environment. Escalating issues to sponsors or human resources abandons the servant leadership role expected of modern project managers.
Question 133 of 168A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours. How will the project manager be able to complete this task?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Tell the owner that a rough order of magnitude will be provided
Providing a rough order of magnitude estimate is the best response when time and detailed information are severely limited. Refusing the request or calling meetings wastes time, whereas a rough estimate fulfills the immediate business need using available data.
Question 134 of 168A member of the board of directors is the sponsor of a project that is important to the organization. This stakeholder has many other priorities and is not currently engaged in the project activities. How should the stakeholder be engaged in the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Involve the stakeholder in governance and decision making
Engaging the sponsor in governance and decision making leverages their authority effectively despite their limited availability. Simply keeping them informed or consulted fails to utilize their primary role as a project champion and strategic escalation point.
Question 135 of 168A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Analyze the interests and influence of stakeholders and evaluate their requirements.
Analyzing the interests and influence of stakeholders ensures that diverse and competing requirements are systematically evaluated and prioritized. Including only common requirements or solely team opinions risks alienating key community groups and missing critical project constraints.
Question 136 of 168At the end of a meeting, a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project. What should the project manager do in this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Advise the functional manager and the project team member to review the resource management plan
The resource management plan identifies roles and responsibilities, making it the ideal reference for resolving role ambiguity. Directing the team member and functional manager there ensures alignment based on approved project documents.
Question 137 of 168A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact on the project outcomes. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Assess the impact of the risk with an expert and prioritize further outcomes with the client.
Assessing the risk's impact with a subject matter expert ensures accurate understanding of the regulatory change. Collaborating with the client to reprioritize outcomes then aligns the project scope with the updated requirements.
Question 138 of 168The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements. How should the project manager address this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Collaborate with the compliance team member to review and prioritize the requirement's delivery.
Collaborating with the compliance team to review and prioritize the new requirement ensures that mandatory obligations are addressed promptly and appropriately. This aligns with hybrid governance, which balances flexibility with adherence to regulatory constraints.
Question 139 of 168A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and delay new feature development. Which action should the project manager take to resolve the quality issues?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Plan for continuous validation of the product.
Planning for continuous validation of the product ensures that quality is embedded throughout the development process. This involves iterative testing, feedback loops, and early defect detection, aligning with both agile and PMI quality principles.
Question 140 of 168How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. By focusing on the delivery of incremental working products to the customer
Agile measurements focus on delivering incremental working products rather than tracking percent complete. Predictive approaches often stall during final integration, whereas agile techniques validate progress continuously through tangible value.
Question 141 of 168A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Discuss the suggestions with the staff responsible for the compliance issues.
The project manager should discuss the stakeholder suggestions directly with the compliance staff to determine feasibility and corrective actions. Logging lessons learned only applies after the issue is resolved, not during active execution.
Question 142 of 168During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team. How should the project manager handle this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Review the risk management plan to evaluate the probability and impact of these delays
Reviewing the risk management plan helps the project manager assess and address these international delays. Schedule compression techniques like crashing or fast-tracking are premature because you must evaluate the identified risks before taking action.
Question 143 of 168On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project manager realized that some of the key activities were scheduled over the holiday periods in the overseas offices. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage.
The project manager should update the schedule and balance the workload among available offices to mitigate the delays. Requesting overtime or hiring temporary personnel wastes money before optimizing the current resources across global teams.
Question 144 of 168A new agile team is forming and the project manager notices that the team is struggling in many areas. The team is experiencing both the inability to meet iteration commitments and team member conflicts. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Coach the team both as a whole and individually
Coaching the team addresses both the conflicts and the missed commitments by building agile maturity and collaboration. Raising issues in the retrospective is helpful, but active servant leadership coaching resolves behavioral and performance issues faster.
Question 145 of 168A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Perform integrated change control.
Integrated change control is required because adding new audit resources and resolving corrective actions directly impacts the project baselines. Look for the option that evaluates the broader impact across knowledge areas rather than just updating a single subsidiary plan.
Question 146 of 168In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Work with the team to develop a risk response plan.
Working with the team to develop a risk response plan is the best action. It aligns with optimizing risk responses and engaging the team to mitigate or provide contingency strategies for delays. Informing the sponsor or HR is an escalation that should only happen after attempting to resolve the issue internally.
Question 147 of 168The project manager has learned that the project sponsor is unhappy with the development of the project requirements. In order to realign the project with the sponsor's expectations, what should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Perform a stakeholder evaluation
Performing a stakeholder evaluation is the most appropriate action because sponsor dissatisfaction indicates a gap in expectations. Reevaluating the sponsor's needs and engagement level allows you to realign the project requirements. Reviewing templates or risks fails to address the root cause of the misalignment.
Question 148 of 168As part of a company's planning effort for team capacity building, the project manager was asked to provide management with a list of required trainings for the project team. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Review the project pipeline, identify gaps in competencies for execution, and decide on the needed trainings.
Reviewing the project pipeline and identifying competency gaps for execution is the correct approach. This ensures proactive skill development aligned with upcoming organizational goals and value delivery. Looking only at past performance misses future project demands, making the pipeline review essential.
Question 149 of 168A project manager is attending a progress meeting with a client. The client requests a design change which might potentially add value to the project. What action should the project manager take?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Make transactional decisions focusing on the project goals.
Making transactional decisions focusing on project goals is the correct action. This means following the integrated change control process by evaluating the potential value and impacts, then submitting it for approval. Accommodating changes without analysis violates scope controls.
Question 150 of 168Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations. What should the project manager do next to address this issue?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Ask the team members to proceed independently while examining needs and alternatives.
Asking the team to proceed independently while examining needs and alternatives keeps work moving and demonstrates adaptive leadership. Options that halt activities are incorrect because agile and hybrid approaches favor continuous progress over waiting.
Question 151 of 168A project manager is replacing the knowledge-sharing platform of a project with a new web-based solution, ensuring that the system is aligned with a significant change in the organization's structure. The project charter was approved and the team is working on the detailed planning. The project management office (PMO) has provided detailed templates for all new projects to follow. Which strategy should the project manager adopt for the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Develop a training and communications schedule with sufficient lead time in collaboration with the change agents.
Developing a training and communications schedule with sufficient lead time ensures stakeholders are prepared for the transition. Collaborating with change agents is crucial because major technological and structural shifts require proactive user adoption.
Question 152 of 168Most of the work packages for a project are subcontracted. In the middle of execution, the project manager is informed that a new contract manager will take the position in one week. What should the project manager do next?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Analyze and document the interests of the new contract manager and select a strategy to manage the relationship.
Analyzing and documenting the interests of the new contract manager addresses the immediate need to manage this new stakeholder relationship. Updating the communications management plan is a subsequent step that happens only after assessing their influence and engagement requirements.
Question 153 of 168A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public. What is the appropriate flow for product development?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.
Completing the must-have functionalities first supports failing fast and securing early regulatory feedback for this innovative product. Option C is also highly defensible for agile methodologies since it explicitly includes demonstrating the product increment, though it omits early focus group testing.
Question 154 of 168A company starts implementing Scrum. About halfway through the first sprint, communication issues develop. Some project team members are not in sync with other team members. What is the cause for this communication gap?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Daily standup meetings were not held or enforced
The absence of daily standup meetings is a strong cause because synchronization is their primary purpose in Scrum. However, option A is highly defensible since a Scrum board provides continuous visual alignment, whereas standups are merely brief verbal checkpoints.
Question 155 of 168A large construction project is progressing well as per the project objectives. The project manager would like to report the project's value to the project sponsor and seek the next phase of funding closure. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Ensure a measurement system is in place like earned value analysis (EVA) to track project value for the project sponsor
Ensuring that a measurement system such as Earned Value Analysis is in place is the correct action. It integrates scope, schedule, and cost to provide a quantitative measure of progress for informed funding decisions. Standard reports or site visits alone lack this objective mathematical backing.
Question 156 of 168A project manager is tasked with developing a coaching model to support and recognize team members' growth. What should the project manager consider when defining their coaching strategy?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Individual and personal objectives
Considering individual and personal objectives is the correct approach when developing a coaching model. Effective coaching focuses on personal growth and skills development for each team member. While team goals matter for general leadership, coaching is inherently individualized.
Question 157 of 168A project manager is launching an agile project with team members located in multiple countries. In order to connect the team and improve the overall productivity, what should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Consider bringing the team members together periodically to work on critical tasks and bond together.
Periodic co-location builds trust and shared understanding, which are essential for distributed agile teams. Distractors involving rigid headquarters scheduling actually harm collaboration by ignoring local team contexts.
Question 158 of 168Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed. This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week. How should the project manager address this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Discuss project requirements with the new stakeholder, and update the communications management plan.
Meeting the new stakeholder to discuss specific requirements and updating the communications management plan ensures they receive relevant information going forward. Defensively showing proof of sent emails ignores that current communication methods are not working for this person.
Question 159 of 168During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: B. B. Update the issue log. identify the involved stakeholders, and assign resources to the corrective actions.
Logging the issue, identifying stakeholders, and assigning resources to corrective actions ensures proper accountability and tracking before the work begins. Changing quality requirements to match a flawed deliverable defeats the purpose of quality control.
Question 160 of 168A project manager is working with the product owner and customer stakeholders on prioritizing the product backlog and planning the product delivery dates. The customer stakeholders are asking to include several deliverables as high priority. The product manager also has technical tasks that should be added as high priority. What should the project manager do?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Lead the team to identity the product objectives at every delivery iteration and clarify priorities.
Facilitating team collaboration to clarify product objectives and priorities for each iteration ensures alignment between business value and technical needs. Letting stakeholders dictate priorities or just building a roadmap ignores the agile necessity of balancing technical debt.
Question 161 of 168A project manager is preparing the business case for a project in a not-for-profit organization. The project manager justifies the cost of the project to a group of sponsors. Which benefits realization metric should the project manager use?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Total value of ownership
Total value of ownership is appropriate here because it captures the intangible social and environmental benefits critical to not-for-profit organizations. However, traditional metrics like payback period or return on investment remain highly defensible for standard financial justification.
Question 162 of 168An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager. What should the project manager do to manage business concerns and expectations before starting the project?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: A. A. Request that the project team develop a release plan and roadmap for the project.
Developing a release plan and roadmap aligns business expectations with the delivery strategy by showing how value will be delivered over time. This helps stakeholders visualize progress, benefits realization, and alignment with business outcomes before execution starts.
Question 163 of 168A new resource has joined an iterative project team. The project manager notices that the resource is unable to complete the deliverables on time. How should the project manager address this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Address the lack of performance by coaching the new team member.
Addressing the performance issue directly through coaching aligns with servant leadership. It supports integration, clarifies expectations, and builds confidence for the new team member without demotivation or escalation.
Question 164 of 168A project manager has received an updated earned value analysis report. The following are the key findings from the report: Budget at completion = US$1 million; Earned value = US$0.7 million; Actual cost = US$0.75 million; Cost performance index = 0.933. Based on this information, what should the project manager conclude about project performance?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. The project will be difficult to complete as planned
A cost performance index less than one indicates the project is over budget and completing it as planned will be difficult. If the budget is overrun now, expect future financial trouble unless you implement immediate corrective actions.
Question 165 of 168In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted the import of this machine model. What should the project manager have done to prevent this from happening?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Ensured that regulatory compliance was considered in the quality management plan.
The project manager should have included regulatory compliance checks in the quality management plan before procurement. Defining the project scope does not automatically account for import restrictions. Always verify legal requirements for international deliveries.
Question 166 of 168The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them. What should the project manager do first in this situation?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: D. D. Meet with the project sponsor as soon as possible to discuss the matter further.
Meeting directly with the sponsor addresses the access request immediately while upholding professional integrity and respecting authorization limits. Updating logs or plans is a reactive step that avoids the necessary direct conversation to resolve the governance conflict.
Question 167 of 168A project manager has been newly assigned to an existing project. The project manager noted that the input from a business unit, which is critical to the success of the project, was not included in any project assets. Instead, there were many complaints about the project's operational results and the alignment with solutions affected by the business unit's operations. What action should the project manager take?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Optimize alignment among needs, expectations, and project objectives.
Optimizing alignment among needs, expectations, and project objectives addresses the root issue of missing stakeholder input. Engaging the excluded business unit ensures operational alignment and recovers support for project success.
Question 168 of 168A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed. Which technique should the project manager apply to verify the knowledge transfer?
Tap an answer — you get instant feedback and the reasoning.
Show answer & explanation
Correct answer: C. C. Expert judgment
Expert judgment is the correct tool to confirm operational readiness and validate knowledge transfer. Subject matter experts or operational leads assess the team's capability to support the product. Meetings alone do not validate true comprehension.