PMP Certification Exam Prep Course Practice Test – 177 Free Exam Questions with Answers

PMP Certification Exam Prep Course

177 questions · instant answer feedback · concise explanations · free

  1. Question 1 of 177What is the main difference between the product scope and the project scope?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The product scope describes the features and functionality of a product, whereas the project scope describes how to get the features and functionality from the product.

    Product scope is the 'what' (features and functionality). Project scope is the 'how' (work to deliver them). This is a fundamental distinction.

  2. Question 2 of 177The project team has been brought together for the first time to work on a network upgrade project. They were able to learn about the functions they will doing on the project and what their roles will be. What will the team do next, according to Tuckman's ladder?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Storming

    Tuckman's stages progress from forming to storming. Initial role orientation defines the forming stage.

  3. Question 3 of 177The project manager is currently analyzing the requirements for the project. He has been informed that the stakeholders will be very disappointed if there are defects in the deliverables. He decides to ensure that the project team receives the right training and the best equipment available to build the deliverables correctly. This will in turn increase the overall cost of the project, but stakeholders do not mind the increase in cost. What best describes this increase in cost?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Cost of quality

    Cost of quality covers expenses to meet requirements, like better equipment. This is a standard project management concept.

  4. Question 4 of 177The project manager is currently assigning costs to each individual activity on the project. A team member has informed the project manager that he should include additional cost just in case the software needs more testing. What best describes this additional cost?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Contingency reserve

    The correct answer proves contingency reserves are for project-specific risks. Management reserve is for unknowns at the portfolio level, while project and testing reserve are not PMI terms.

  5. Question 5 of 177The project team has completed the scope baseline and has started to break down each of the work packages into individual activities. What process should the team do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Sequence Activity

    The correct answer proves the project sequence process. The trap is confusing the work breakdown structure step with the sequencing step.

  6. Question 6 of 177While working on a project, the project manager has been inspiring the team members to do the best they can, while also regularly communicating the project's vision to the team. What skill does this best describe?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Leadership

    The correct answer proves leadership as a core interpersonal skill. The trap is confusing it with facilitation or active listening.

  7. Question 7 of 177A project manager wants to ensure that the new cell phone the project is creating will beat or match the performance of new cell projects by other companies. What tool would be the best for the project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Benchmark

    The correct answer proves benchmarking for quality standards. The trap is confusing process names with the specific tool.

  8. Question 8 of 177While working on a large multinational project, you identify some of the positive and negative stakeholders. What process group are you currently engaged in?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Initiating

    The correct answer proves identifying stakeholders is in the initiating group. The trap is misplacing it in planning or stakeholder management.

  9. Question 9 of 177The project manager and team have decided to hire a contractor to complete building out the remaining section of the datacenter. They have the requirements listed in detail and would like to use a contract that would present the smallest amount of risk to the project. The project team members would like to purchase the materials themselves since there are very familiar with the work. What contract is best for this project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Cost plus fixed fee

    The correct answer proves cost-plus-fixed-fee limits buyer risk. The trap is not recognizing time-and-materials as higher risk.

  10. Question 10 of 177While developing complex software for an organization, the project team creates a computer-generated model of what it will look like when it is done. This model is given to the customers for their feedback. What best describes this model?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Prototypes

    The correct answer proves prototypes for early user feedback. The trap is confusing it with a simple screenshot.

  11. Question 11 of 177The project team has completed the server deployment project. They have tested the server to ensure that it works according to the requirements given to them, and it seems to be functioning correctly. What process group has the team just completed?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Executing

    The correct answer proves executing is about completing deliverables. The trap is confusing it with monitoring and closing phases.

  12. Question 12 of 177While planning the risk responses for a construction project, the project manager and project team have decided they will have to choose a new electrical contractor due to the fact that the recommended contractor has legal issues with the local building department. The legal issues could cause the project to be delayed. What risk response does this represent?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Avoid

    The correct answer proves avoidance by eliminating the risk source. The trap is confusing avoidance with acceptance or mitigation.

  13. Question 13 of 177While managing a small construction project, the project manager informs the project team members that they are using more materials than necessary to complete the project work. What process describes this scenario?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Control resources

    The correct answer proves controlling physical resource usage. The trap is confusing it with team management processes.

  14. Question 14 of 177While working on a project, the project manager asks the team to incorporate more of the user feedback into the deliverables. In an agile project, where do the customers give the team feedback on the product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Sprint review

    The correct answer proves the sprint review for stakeholder feedback. The trap is confusing it with retrospective or planning meetings.

  15. Question 15 of 177During the datacenter development project, the project manager has noticed that some of the work being done on the project is not in the baseline scope. The project manager has analyzed the work completed by the project team and then compared that to the project management plan to see where the differences are. What process best describes the work of the project manager?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Control scope

    The correct answer proves the Control Scope process, which compares actual work against the project plan. The elimination cue is that 'Monitor' and 'Manage' are not formal PMI process names.

  16. Question 16 of 177A project has completed 60% of all the work. The team has spent 55% of the project budget. The budget is currently set at $180,000. The sponsor has requested the project's CPI. What CPI figure should the project manager provide?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. 1.1

    The correct answer proves the formula CPI = EV / AC. The elimination cue is that CPI is a ratio, not a monetary value, ruling out the distractors.

  17. Question 17 of 177While working on a project, you realize that you will not be able to install the server and the workstations at the same time. In fact, the team has alerted you that after the server installation is done, you should wait an additional 4 days before installing the workstations. This is due to the updates the server will need, which is an automated process. What do you need to add to the schedule in order to account for this delay?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Lag

    The correct answer proves Lag, a required delay between tasks. The trap is confusing this with float, which is schedule flexibility, not a mandatory delay.

  18. Question 18 of 177While working with the project team and conducting a brainstorming session, the project manager noticed that a lot of the ideas the team was coming up with were not organized. What tool can be used by the team to best visually organize their ideas?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Mind mapping

    The correct answer proves Mind Mapping, a visual tool for structuring unstructured ideas. The other options are eliminated by their use for process flow or analysis, not brainstorming organization.

  19. Question 19 of 177The project team has identified a number of risks that could affect the project. One risk in particular is that the permit to build the foundation has shown up late. They have ranked this risk as the most important in the project since it will cause the largest delay. What process best describes this ranking?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Qualitative risk analysis

    The correct answer proves Qualitative Risk Analysis, which prioritizes risks by impact. The trap is confusing this with Quantitative Analysis, which assigns numerical values, not just ranking.

  20. Question 20 of 177A large development company has just initiated a project to build a 60-story building. The project will take approximately 3 years to complete with a cost of $550 million. The development company has started to facilitate funding for the project by asking private equity firms and banks. What tools does this best represent?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Financing

    The correct answer proves Financing, the process of securing external funds. The distractors are eliminated by their focus on cost estimating or fund limitations, not acquisition.

  21. Question 21 of 177When selecting a project, the company looks at different factors that could impact their selection. What document best identifies the need for a project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Business Case

    The correct answer identifies the document that justifies a project's existence. Options A, B, and C are distractors that describe project authorization or planning documents.

  22. Question 22 of 177While working on a large project, the project manager originally counted 12 stakeholders. A new requirement and six more stakeholders were added to the project. How many communication channels are on this project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. 153

    The correct answer applies the communication channels formula. Options B, C, and D are distractors that result from miscalculating the formula or the number of stakeholders.

  23. Question 23 of 177The project manager and the project team are currently assessing various ways of responding to a particular risk. The project involves reconstructing part of their current office building, and they're worried about a hurricane hitting and damaging the materials or parts of the unfinished building. The best response they came up with was to purchase insurance in case a hurricane does hit. What kind of strategy is this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Transfer

    Transferring risk involves shifting the financial impact to a third party. Purchasing insurance is the classic example, where the risk of loss is transferred to the insurance company.

  24. Question 24 of 177While managing the project team the agile project manager is having a very difficult time understanding why team members are always frustrated when communicating with him. What critical soft skills does this project manager lack?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Emotional intelligence

    Emotional intelligence is the core competency for managing team relationships and reactions. Other skills are components of it.

  25. Question 25 of 177While constructing a new office space, the sponsor has requested the project manager complete the project sooner. While analyzing the work, the project manager has noticed that some of the work can start before the predecessor work is done. What can the project manager do in this scenario to complete the project sooner?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Add lead times between project activities

    A lead allows an activity to start before its predecessor finishes. Lag adds delay, the opposite of what's needed.

  26. Question 26 of 177During a new smartphone development project, the customers are given a prototype of the product for them to demo. They inform you that the phone constantly reboots, and sometimes the touch screen does not work. What tool can the project team use to find the reasons for these defects?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Ishikawa diagram

    An Ishikawa diagram identifies potential root causes for a problem. The other tools analyze different aspects of the project.

  27. Question 27 of 177What is the main benefit for conducting the project using agile methodology versus traditional methodology?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Agile delivers value incrementally

    Agile delivers value incrementally throughout the project. Traditional methods often defer value delivery until the very end.

  28. Question 28 of 177The sponsor makes it clear that he does not want any of the team members to be overworked while working on a project. This means that no team member is allowed to work overtime. The sponsor is okay with the project being delayed due to this. What technique can the project manager best implement to ensure that no team member is overworked?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Resource leveling

    Resource leveling resolves resource overallocation by changing the schedule. Resource smoothing only works with existing slack.

  29. Question 29 of 177The project manager has noticed that a few team members are having a difficult time following the inspection process to check the quality of new software. What is the best tool to help them see the process, making it easier to follow?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Flowchart

    Flowcharts visually map processes for clarity. Distractors like histograms or control charts measure data, not guide step-by-step procedures.

  30. Question 30 of 177The datacenter redesign project is currently 30% complete. The project manager is not happy with the way processes are being followed by the team in ensuring that the network wiring will meet its quality requirements. What should the project manager do to improve the processes so as to meet the quality requirements with the network wiring?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Manage quality

    Manage quality improves processes through audits. Other options measure against baselines rather than enhance workflows.

  31. Question 31 of 177While developing a new smartphone, the project team has identified a specific set of performance measurements that the phone should meet when it is complete. The measurement looks at how fast the phone can boot up and how fast it can shut down. Where should the project team document these measurements?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Quality metrics

    Quality metrics define measurable performance criteria. Checklists guide inspections, but metrics quantify standards.

  32. Question 32 of 177While installing the new virtual server, the team discovers a new method that they can use on this project and future projects that can get the installation done in about half the time. This new method involves prepping the server image and cloning the machines. What is the best project document for the team to update?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Lessons learned register

    Lessons learned register captures new knowledge for reuse. Risk registers track threats, not improvements.

  33. Question 33 of 177The project manager and team are currently working to create a list of activities needed to complete the project. They have come to one particular work package that they cannot decompose because they do not know enough about the work yet. They have decided that midway through the project, they will decompose this particular work package. What tool or technique are they using?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Rolling Wave Planning

    Rolling wave planning defers detailed planning for future work. Decomposition breaks down known work now, not later.

  34. Question 34 of 177A project manager is currently working with the team to complete the office redesign project when a sponsor tells him to finish it 2 weeks sooner than planned. The project manager will need 4 new people to join the team to complete the work by the new deadline. What technique is best described in this scenario?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Crashing

    Crashing adds resources to shorten the schedule. Fast tracking overlaps activities, but here resources are explicitly added.

  35. Question 35 of 177The project team has finished 60% of the deliverables when management informs the project manager that the project will be canceled immediately and the team will be reassigned to work on a new project that management feels is more important. What should the project manager do right away?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Inform the project team, conduct a lesson learned session, and formally release the team from the project

    Project closure requires formally releasing the team and conducting lessons learned. Ignoring the closure process violates standard project management procedures.

  36. Question 36 of 177The project manager and the project team are reviewing the completed deliverables to see if they meet the performance requirements outlined in the requirements documentation. This is done so that when the customers are invited to inspect the deliverable, there will be no issues. What is the best output of this process?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Verified deliverables

    Control quality produces verified deliverables, which are formally inspected before customer acceptance. Accepted deliverables result from a separate validate scope process.

  37. Question 37 of 177While monitoring and controlling a project, the project manager has been comparing the work performance data to the project management plan to see if there is any variance. What process did the project manager finish to get the work performance data?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Direct and manage project work

    Work performance data is the primary output of executing Direct and Manage Project Work, not from control or monitoring processes.

  38. Question 38 of 177The project team and the project manager held a meeting to discuss a few issues related to the project. The meeting was very productive and led to most of the issues being resolved. A few weeks later, one team member brought up one of the issues that was resolved in the previous meeting as being unresolved. The project manager reviewed the meeting documentation and determined that the issue was resolved, but the team member may not have known about the resolution. What could the project manager have done differently to prevent this miscommunication?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Distributed detailed meeting minutes

    Meeting minutes are the official record of resolutions, preventing miscommunication. Other meeting best practices do not ensure everyone knows the outcome.

  39. Question 39 of 177You are having an issue with the software crashing consistently on the project. What should you use to identify the cause of this issue and the effect it may have on your project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Ishikawa Diagram

    An Ishikawa diagram identifies causes and effects. Flowcharts and histograms analyze data but do not find root causes.

  40. Question 40 of 177While working on a project, the project manager notices that most of their time is spent resolving conflicts between members of the project team. What is the best tool the project manager can use to resolve the problems amongst the team members?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Interpersonal and team skills

    Conflict management is an interpersonal skill. Training and colocation are team development techniques, not conflict resolution tools.

  41. Question 41 of 177While conducting a risk assessment on a project, the project manager has identified a new regulatory risk. If the project is not completed by July 31, the company will have to scrap the project. What best describes this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Project constraint

    This describes a time constraint. Project constraints include scope, cost, time, resources, risk, and quality.

  42. Question 42 of 177While monitoring a large construction project, the project manager has calculated the SPI of the project to be 1.2. A contractor has informed the project manager that a delivery will be 1 week late. The 1-week delay is 10% of the project schedule. What would mostly likely happen to this project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The project will finish ahead of schedule

    With an SPI of 1.2, the project is 20% ahead of schedule. A 10% delay would not change the final outcome of finishing ahead of schedule.

  43. Question 43 of 177A change request has been made by a senior stakeholder to add a new reporting function to the current financial software development project. The change was assessed by the project team and approved by the sponsor. What process should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Direct and manage project work

    The correct answer proves that execution follows approved changes. Direct and manage project work is for executing approved changes, while integrated change control is for the assessment process.

  44. Question 44 of 177The project has managed to build about half of the deliverables needed to complete the project. The project has spent $50,000 on materials and labor. This money that has already been spent is generally referred to as what?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Sunk cost

    The correct answer proves sunk costs are irrelevant to future decisions. Sunk costs are past expenditures that should not influence go/no-go decisions, unlike opportunity costs.

  45. Question 45 of 177The project has just been initiated, and the project sponsor calls the project manager to ask approximately when he thinks the project will be completed. The project manager replies that they have been unable to thoroughly analyze the work needed to complete the project and that he is not very knowledgeable about this kind of work. The sponsor insists on receiving a high-level estimate. The project manager responds that it will take approximately 3 months to complete the work based on his experience working on a project very similar to this one. What technique best represents this estimate?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Analogous estimates

    The correct answer proves analogous estimates use historical data. Analogous estimation is top-down and fast, relying on past similar projects rather than detailed analysis.

  46. Question 46 of 177While working on a project with a budget of $5,000, the project manager determines that the earned value on the project so far is $1,750. So far, the project team has spent $2,900. What should the project manager report as the status of the budget?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The project is over budget by 40%.

    The correct answer proves CPI measures cost efficiency. With a CPI of 0.6, the project is 40% over budget, as CPI below 1 indicates cost overrun.

  47. Question 47 of 177The risk management plan generally outlines the steps the project will take to conduct risk management processes on the project. Which of the following will the risk management plan not include?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Positive risks that could affect the project

    The correct answer proves that positive risks are documented in the risk register, not the risk management plan. The other options are standard components of the risk management plan.

  48. Question 48 of 177You are currently managing a business process reengineering project and have identified all the risks that can affect the project. You would like to put the risks in order from most impact to least impact on the project. What is the best process for doing so?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Perform qualitative risk analysis

    The correct answer proves that qualitative risk analysis ranks risks by impact and probability. The distractors are either invalid processes or describe later stages like quantification or response planning.

  49. Question 49 of 177While managing a datacenter project, a few customers requested a feature be added to the project that will enhance the security system in the datacenter. The change was submitted to the change control board and was denied due to the high cost of the security system. A few months later another customer submitted the same change back to the project manager. What is the best step the project manager can take in this scenario?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Inform the customers the change cannot be done

    The correct answer proves that a denied change should not be re-submitted. The elimination cue is the prior denial, which makes re-evaluation or re-adding the change inappropriate.

  50. Question 50 of 177The project manager is currently reviewing all of the meetings that took place over the past few weeks to ensure that it was done according to the communication management plan. What process is the project manager currently conducting?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Monitor Communications

    The correct answer proves the Monitor Communications process, which compares actual work performance data against the plan. The elimination cue is that 'Conduct Communications' is not a defined PMI process.

  51. Question 51 of 177Which of the following statements is true about projects:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Projects are temporary endeavors to create a unique product, service, or results

    The correct answer proves the PMBOK definition of a project as temporary. The elimination cue is that projects are finite endeavors, not ongoing operations.

  52. Question 52 of 177The agile project team has determined that many of its processes have a lot of waiting and would like to remove all of the waste in the processes. What would be the best tool the agile team can use to improve their processes?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Value stream map

    The correct answer proves the Value Stream Mapping technique for identifying waste. The elimination cue is that the distractors describe unrelated quality tools.

  53. Question 53 of 177Which of the following is not a principle of agile planning?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Conduct most of the planning at the beginning

    The correct answer identifies the anti-pattern of upfront planning. The elimination cue is that agile planning is iterative and continuous, contrary to traditional methods.

  54. Question 54 of 177When deciding which user stories can be done in the next iteration, what should the project team consider?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. How many points the team completed in the past iterations

    This question tests Agile velocity for iteration planning. Velocity measures past completed points, making 'past iterations' a concrete planning cue, while distractors focus on individual story characteristics.

  55. Question 55 of 177While measuring quality on a project, the project team decided to just measure the quality as pass/fail. The team has determined that this is the best method because the deliverables are mostly functions that will need to produce a correct result. What best describes this measurement?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Attribute sampling

    This question tests 'Attribute sampling'. A pass/fail measurement is the defining characteristic of attribute sampling, as opposed to the variable scales used in statistical sampling.

  56. Question 56 of 177There have been many disputes on the project with the current contractor. The contractor claims the project team is always asking that work not be listed in the contract, and the team claims that the contractor has not been doing the work listed in the contract. What should the project manager do first?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Review the contract

    This question tests contract management fundamentals. The first step in any contractual dispute is always to review the contract itself to clarify the original agreement, as it's the source of truth.

  57. Question 57 of 177The project manager has brought the project team together to explain what the project will be about and what their roles will be. The team members introduce themselves and learn about the different skill sets each of them brings to the project. What stage on Tuckman's ladder best represents this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Forming

    This question tests the 'Forming' stage of team development. The initial meeting where members get acquainted and understand their roles is the classic description of the forming stage.

  58. Question 58 of 177After the project manager has collected the requirements and received approval for the scope statement, what process should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Create WBS

    The correct answer shows the standard sequence of scope management processes. The Work Breakdown Structure is built directly from the approved scope statement.

  59. Question 59 of 177The project manager has been informed that the cost of building a new room in the office will be $15,000, +/- 65%. The project manager wants to know why there is such a large variance in the estimate. The builder said they have not seen the space and it's just a high-level estimate. What kind of estimate does this best represent?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Rough order of magnitude estimate

    The correct answer identifies the specific type of cost estimate based on its variance range. A Rough Order of Magnitude is characterized by its wide -25% to +75% accuracy.

  60. Question 60 of 177In what process does a project manager determine the approach they will use to involve the stakeholders to meet their expectations?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Plan stakeholders engagement

    The correct answer proves Plan Stakeholder Engagement, where strategies to meet stakeholder needs are defined. The trap is confusing this with Plan Communications, which focuses only on information distribution.

  61. Question 61 of 177While conducting procurement on a project, the project manager has received many different bids with a wide variance of estimated cost for the work. What can the project manager use to best determine which vendor has given a realistic price?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Independent estimate

    The correct answer proves Independent Estimate, an external benchmark for pricing. The trap is distractors used for vendor selection, not price validation.

  62. Question 62 of 177You have just been appointed the new project manager on a product upgrade project. One person in particular at the company feels like the project may cause them to lose their job. This person has expert knowledge of the current product and does not feel that it needs an upgrade. What would you consider this person on your project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Stakeholder

    The correct answer proves Stakeholder, anyone impacted by the project. The trap is distractors that assume the person is part of the team.

  63. Question 63 of 177Your company has just started a project to allow remote workers to join the network using a virtual private network (VPN). During the execution of the project, one of the VPN servers completely fails, and the team will need to replace it as soon as possible. Fortunately, the project team anticipated that this might happen and has a plan for replacing the server. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Implement risk response

    The correct answer proves the executing process of enacting pre-planned responses. Options A, B, and C are distractors that describe planning activities or non-existent processes.

  64. Question 64 of 177Which of the following is an XP practice that helps to create a shared vision between the developers and the customers?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Metaphors

    The correct answer identifies the XP practice for aligning vision. Options B, C, and D are distractors that describe other common agile ceremonies.

  65. Question 65 of 177Which technique should the agile team use to list the reasons for why a particular process was failing during iteration?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Fishbone analysis

    The correct answer identifies the retrospective technique for root cause analysis. Options B, C, and D are distractors that describe other agile practices or goal-setting methods.

  66. Question 66 of 177The sponsor would like a report about the resources that are being used on the project. He would like to see them broken down by different categories to make them easier to understand. What process will the project manager use to create this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Estimate activity resources

    Estimate activity resources creates the resource breakdown structure, a categorized resource list. Other process options don't produce this hierarchical document.

  67. Question 67 of 177The project manager, Peter, has been informed by the sponsor that the project needs to be completed 2 weeks earlier than the scheduled time. Peter goes to the team and informs them that they will need to work overtime to complete the project sooner. What is Peter doing to shorten the schedule?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Crashing

    Crashing shortens a schedule by adding resources, such as overtime, which increases cost. Fast tracking is about parallelism, not adding resources.

  68. Question 68 of 177The project team is currently having disagreements about the program and methods they would use to implement a few of the features in the product backlog. What role should the agile project manager take during this scenario?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Coach them to a resolution

    The agile coach guides the team to resolve disagreements during storming. Directing or delegating undermines self-organization.

  69. Question 69 of 177The project manager is currently estimating how many programmers will be needed to complete the financial software upgrade project. What document can the project manager use to determine who is available to work on the project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Resource calendar

    Resource calendar shows resource availability for estimating team needs. Lessons learned register captures project knowledge.

  70. Question 70 of 177While working on a project schedule, the project manager notices that activities A, B, and C all have a duration of 4 days. The project manager also notices that activities F and G have a duration of 7 days. Activities A, C, F, and G have a slack of 1 day. Activity B is the only one on the critical path. What is the slack on activity B?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. 0 days

    The correct answer proves that any activity on the critical path has zero slack. The rule is that critical path activities have no float, which eliminates all other options.

  71. Question 71 of 177While monitoring the status of an agile project, what numerical analysis can the project team use to help determine if the project is on schedule?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Earned value management

    The correct answer identifies earned value management as the tool for schedule variance analysis. The trap is distractors related to financial metrics or generic scheduling terms.

  72. Question 72 of 177The project manager is having a very difficult time collecting the requirements from the customers. The customers are having a difficult time putting the requirements into logical groupings. What tool can best help them group the requirements?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Affinity Diagram

    The correct answer identifies the affinity diagram as the tool for grouping ideas or requirements. The trap is distractors that are outputs or other techniques, not specifically for grouping.

  73. Question 73 of 177The product owner would like to see how much work remains to be done on a project. What would be the best agile tool to display this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Burndown chart

    The correct answer identifies the burndown chart as the visual for tracking remaining work. The trap is distractors that show other project metrics, not remaining work.

  74. Question 74 of 177You're currently working on a large new building development project. The project team is currently breaking down the deliverables listed in the project scope statement into work that is more manageable. What process best describes this scenario?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Create WBS

    Create WBS is the process of decomposing deliverables into work packages. Define activities is the next step, breaking work packages down further into individual tasks.

  75. Question 75 of 177Project manager Mary was informed by the team that the constant conflicts in the project have slowed down the team so that they are now behind in the work. Mary is not sure what she did wrong while planning the project. She used a RACI chart to assign roles to each team member. She has assigned each activity to at least two people who will be held accountable for the work. What best explains the conflicts in the project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Only one person should be held accountable for an activity when using a RACI chart.

    The core principle of a RACI chart is that a single person is accountable for each activity to prevent ambiguity and confusion. Assigning multiple 'Accountable' roles directly creates conflict.

  76. Question 76 of 177While planning a project, the project manager is given many requirements that the customers would like to add to the project. Upon further investigation, the project manager decides that a few of the requirements will not be feasible within the limited time and cost allocated to the project. What document would best list the requirements that will not be added to this project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Project scope statement

    The project scope statement explicitly lists the deliverables and, just as importantly, defines what is excluded from the project. This provides a baseline to prevent scope creep.

  77. Question 77 of 177The project sponsors have informed the project manager that they would like to be included in the weekly meetings along with the team members. What should the project manager update to include the sponsors in the weekly meetings?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Communication management plan

    The communication management plan defines communication requirements, including who receives information, their format, and the frequency. This is the correct document to update for meeting attendance.

  78. Question 78 of 177A project manager is having a very difficult time negotiating with a functional manager. The project manager would like to have Peter, the system administrator, work on the project full time, but the functional manager needs Peter full time to work on the servers throughout the day in case one goes down. After a few days of negotiating, the project manager has determined that he will have Peter from Monday to Wednesday, and the functional manager can have Peter on Thursday and Friday. Although this solution is not the most ideal scenario for the project manager and functional manager, it will have to work for now. What conflict resolution technique was used?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Compromising

    Compromising is a lose-lose approach where both parties give up something to reach a temporary solution. This is different from problem-solving, which aims for a win-win outcome.

  79. Question 79 of 177The project team has just assigned costs to all activities on a project. They will now use these costs to find the overall budget of the project. What tool can the project team use to complete this task?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Cost aggregation

    Cost aggregation is the process of rolling up individual activity costs to establish a total project budget. It is the final step in the Determine Budget process.

  80. Question 80 of 177The project manager is informed that a manager in the finance department has requested to be included in the weekly status updates on the project. What document should the project manager update immediately?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Stakeholder register

    The stakeholder register must be updated with the new stakeholder and their communication requirements. Other documents are updated later in the process.

  81. Question 81 of 177Over the last three weeks the project team has finally been able to establish a shared vision of what the product would look like when it is complete. This is an example of?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Progressive elaboration

    Progressive elaboration is the process of iteratively adding detail to a project plan. A shared vision is an outcome of this process, not a project management method.

  82. Question 82 of 177After the iteration has completed, where will the team inspect the methods they used to build that increment?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Retrospective

    The retrospective is the event where a team reflects on their process and plans improvements. It is distinct from review or planning meetings.

  83. Question 83 of 177While constructing a roof for a large building, the project team has identified the risk of a snowstorm. Due to the region in the country and the time of the year, the team has decided to take no action or preparations for the snowstorm. What risk response strategy is the team using?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Acceptance

    Acceptance is a risk response strategy where no action is taken. All other options involve active mitigation, avoidance, or enhancement.

  84. Question 84 of 177The project manager is working on a new electrical wiring upgrade project for the entire office. Due to safety issues, the project manager cannot move forward with many parts of the project without inspections and permits from the local Buildings Department. Most permits take approximately 6 weeks to get. Where would the project manager document the opportunity the project should take if a permit comes within 2 weeks instead of the 6 weeks?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Risk register

    Opportunities are documented in the risk register. An assumption log tracks assumptions, and a change request is for approved changes.

  85. Question 85 of 177The project manager and the team have worked many hours to calculate the amount of time it will take to conduct each activity. They would like to document some of the assumptions they made and the constraints they may face when the project is executed. What document will they use for this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Basis of estimates

    Correct answer proves the basis of estimates document details calculation rationale. Distrators trap candidates by naming related but incomplete documents.

  86. Question 86 of 177The agile project team has completed the Sprint planning meeting. What would be the output of this meeting?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Sprint backlog

    Correct answer proves the sprint backlog is the key output. Distrators trap candidates with similar but incorrect artifacts like product backlog.

  87. Question 87 of 177While managing a product development project, the project manager met with the team to determine some of the key tasks that will ensure they produce a high-quality product. What should they consider the most important concept in quality?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Quality is about prevention

    Correct answer proves prevention is more important than inspection in quality management. Distrators trap candidates with cost of quality misunderstandings.

  88. Question 88 of 177While attempting to determine the schedule for the project, the project manager has been informed from the team that each line of code will take about 15-45 minutes to write and debug. There will be about 1 million lines of code in the application. What schedule-estimating technique best describes this estimate?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Parametric

    Parametric estimates use statistical relationships to calculate duration. Analogous and bottom-up are not driven by a unit metric like this.

  89. Question 89 of 177While working on a complex software development project, the team is having a difficult time understanding a process used to code a particular report. They find the process to have many different paths and if/then scenarios. They have asked the project manager for a tool that can help them see the process on a large white board or on paper. What's the best tool the project manager can recommend for the team to help visualize the process?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Flowchart

    A flowchart visually maps steps, decisions, and paths in a process. The other diagrams are for different purposes.

  90. Question 90 of 177Senior management has requested an update to the current product upgrade project. The project manager knows she has to keep the information high-level, and as short as possible. Which resource would be the best to show senior management?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Milestone chart

    A milestone chart provides a high-level view of major deliverables and dates, ideal for executive updates.

  91. Question 91 of 177A major portion of a large construction development project was completed by a contractor. The contractor has completed all the work listed in the agreement but also completed other work the contractor felt had to be done. The contractor is asking for more money that was not listed in the agreement, and the project manager feels that what they're asking for is too much for the additional work that was completed. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Contact claims administration

    Claims administration is the formal process to resolve contract disputes and change order disagreements.

  92. Question 92 of 177While planning a major network upgrade project, one stakeholder has given a requirement to upgrade the switches. The project manager has determined that this would be too costly to be included in the project and has decided to exclude it. What process will the project manager use to document this exclusion?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Define Scope

    Define scope captures exclusions in the scope statement. Other processes do not formally document excluded items.

  93. Question 93 of 177A company has completed building a new datacenter. The project has many changes that were submitted to the change control board. Most changes were approved, and some were not. Which of the following is not a purpose of the change control board?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Deny changes whenever possible

    The change control board evaluates changes fairly, not denies them unnecessarily. Its goal is to manage, not obstruct, valid changes.

  94. Question 94 of 177A project manager on an agile project conducts planning at multiple points in time as the scope is refined and changed over the project lifecycle. This is known as?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Rolling wave planning

    Rolling wave planning handles iterative planning. Progressive planning is vague, while agile planning is not a formal PMP technique.

  95. Question 95 of 177The project manager has been informed that the company's senior management would like a meeting about the status of the project. What should the project manager take to display the current schedule of the project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Milestone chart

    A milestone chart provides a high-level view of major accomplishments, ideal for executive presentations. Gantt charts and network diagrams offer too much detail for a quick status update.

  96. Question 96 of 177The project manager has to present a risk assessment to senior management and has decided to take the most graphical representation of the probability and impact assessment. What tool should the project manager use?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Bubble chart

    A bubble chart is the best graphical tool for showing probability and impact visually. Risk registers are tabular, and Pareto charts are for quality analysis, not risk.

  97. Question 97 of 177The project manager and the project team were able to identify a number of risks that could affect the website upgrade project. They listed all of the risks on the risk register. They will now conduct a qualitative risk analysis to prioritize the risks. What will the team look at when prioritizing the risks?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Probability and impact

    Qualitative risk analysis prioritizes risks based on probability and impact. Ranking by only one factor or source does not fully assess risk exposure.

  98. Question 98 of 177While managing a datacenter development project, the project manager has noticed there are many conflicts between the team members on the project. When managing a conflict in a project, what would be the best role for the project manager?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Facilitator

    A facilitator guides parties toward a mutual resolution, which is standard conflict management. Dictatorial or advisory approaches ignore process best practices.

  99. Question 99 of 177The project manager has calculated the SPI of the project to be .7 and the CPI to be .9. When reporting the progress of the project to the company stakeholders, what should the project manager say about the project to the stakeholders?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The project is delayed and over budget

    Performance indices like SPI and CPI determine project health. An SPI under 1 indicates delays; a CPI under 1 shows over budget.

  100. Question 100 of 177While working on a web design project, the change control board approved a change to the layout of the menu. What process should the project manager conduct next to ensure the change is implemented?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Direct and manage project work

    Approved changes are implemented through direct and manage project work. Verify scope comes after work is complete.

  101. Question 101 of 177The project manager is working on a top-secret company project and would like to ensure all the correct security measures are in place for communications regarding the project. What tool should the project manager use?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Communication technology

    Communication technology tools address security needs. Encryption is a feature, not a standalone tool.

  102. Question 102 of 177The project manager has acquired the project team members and is starting to work with them to complete the project work. During this process, the project manager has utilized a variety of rewards and recognition theories to keep the team motivated. What is the output of this process?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Team performance assessments

    The Develop Team process produces team performance assessments. Other options are tools used within the process, not its output.

  103. Question 103 of 177The deliverables for the office relocation project were accepted by the company stakeholders, and all office staff were very happy with the work of the movers. The office manager requested the project be closed immediately due to year-end budgetary closeouts. The movers filed a claim for an additional $300 for moving a copier that was not part of the plan. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Keep the project open and inform claims administration.

    Claims must be settled before project closure. The correct step is to forward the claim to claims administration for negotiation and resolution.

  104. Question 104 of 177While working on a project, the project team has encountered a problem that has halted the project work. The team is unable to come up with a solution and would like to have an outside company come in and finish the rest of the project. What should the project team do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Create a request for proposal

    A request for proposal is appropriate when an external solution is needed for a complex problem and the approach is not predefined.

  105. Question 105 of 177While analyzing the budget of a project, the project manager notices that the current CPI of the project is .93 and the SPI is 1.1. What best describes what is taking place on this project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Crashing

    Crashing adds resources to decrease schedule, often increasing cost. A low CPI and high SPI suggest this method is being used.

  106. Question 106 of 177Project manager Mark is working to create the project scope statement for a sales management software. Many stakeholders have requested that a feature be added to enable automated call-backs to leads that come through the website. Mark realizes that adding this feature will not be possible due to the fact that the company's current network lacks the required hardware. What is the best approach for Mark to take?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Add the feature as an exclusion to the scope statement

    The correct answer proves scope exclusions prevent false expectations. The scope statement explicitly defines what is not in scope to avoid future change requests.

  107. Question 107 of 177The team is concerned with the quality of the product about to be created by the project. What statement about quality management is true?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Low-grade, high quality is okay

    The correct answer proves grade is separate from quality. Grade is the tier of features, while quality is conformance to requirements. Low quality is never acceptable.

  108. Question 108 of 177When using different prioritization techniques what is the most important aspect that the agile project manager should communicate to the customers?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Don't worry too much about the specifics it's more important to get the relative prioritization correct

    The correct answer proves relative value matters more than process specifics. The technique is a tool; the business value of prioritization is what drives decisions.

  109. Question 109 of 177While working on a tablet redesign project for large technology company, the project manager received a change request from a key stakeholder. The change request would change the position of the power button from the top to the side of the tablet. After an assessment of the change, the change control board declined the change due to concerns about redesigning the motherboard. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Update the change log

    The correct answer proves the change log tracks all change statuses. After a change is approved or denied, the change log must be updated to reflect the decision.

  110. Question 110 of 177When managing risks on a project, the project manager should be aware of the individual project risks and which other project risks?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Overall project risks

    The correct answer proves that project risks are categorized as individual and overall. The other options describe risk attributes, not distinct risk categories.

  111. Question 111 of 177When an organization is considering a project, what are some of the factors that can influence why a project should get done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Meeting regulatory, legal, or social requirements

    The correct answer proves that meeting regulatory requirements is a valid justification for a project. The other choices represent operational activities, not project justifications.

  112. Question 112 of 177The agile project team has decided to do one of the features from the product backlog. The single feature will take six weeks to complete and will be reviewed by the customer. What actions should the agile project manager take next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Informed the team six weeks is too long and they will need to decomposed that feature into smaller increments

    The correct answer proves that agile iterations must be decomposed into smaller increments. The trap is the duration, which signals the need to break down the work into sprints.

  113. Question 113 of 177While building an agile space, the project manager would like to implement a tool that will allow the team to keep track of the flow of work while limiting the work in progress. What tool best meets these requirements?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Kanban development

    The correct answer proves that Kanban is designed to visualize workflow and limit work in progress. The other tools serve different purposes, like tracking progress or managing time.

  114. Question 114 of 177Your company has decided to roll out a new Wi-Fi network for the staff. The sponsor has informed you that encryption on the network is mandatory. Where will the project manager document that the encryption was mandated by the sponsor?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Requirements traceability Matrix

    The correct answer proves that the requirements traceability matrix links requirements to their sources. The other options contain requirements but not their origins.

  115. Question 115 of 177The product owner has informed the project manager that all items in the product backlog are valuable and they should all get done. How should the agile project manager respond?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Educate the product owner on the benefits of prioritizing the product backlog

    The correct answer proves that the agile project manager must educate stakeholders on prioritization. The distractors misrepresent agile roles, as the product owner owns prioritization.

  116. Question 116 of 177The project team is currently working on an advertising project. They have completed a few of the activities, which includes writing the script for the commercial. Once the team completes an activity, what should they do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Update work performance data

    The correct answer proves the immediate step after work completion is to document progress in work performance data. The trap distractor suggests premature project closure before all work is done.

  117. Question 117 of 177The project team is working with the customers to write the user stories. The customers have refused as they claim this would add no value to the project. What would be the best step to resolve this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Educate the users why the user stories are valuable

    The correct answer proves the agile principle of educating stakeholders on value. The trap distractor suggests deferring to a role or discontinuing a core agile practice.

  118. Question 118 of 177While working on an agile project, the team receives a request from the customer to deploy the software as soon as the iteration is done. The customer has already checked the completed part of the software and has accepted it. The team has refused to deploy the software. What best explains the team's refusal?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The iteration is part of a release

    The correct answer proves the distinction between iterations and releases in agile. The elimination cue is that the customer's acceptance implies no errors, invalidating the distractors.

  119. Question 119 of 177Team members Mark and Bill are currently experiencing conflict in the office move project. Mark believes that it would be best if they moved the furniture first and then the computers, whereas Bill believes it's best to move the computers and then the furniture. This conflict is causing a serious delay to the project, and both Mark and Bill have decided they will make a decision on what to move first at a later date. What conflict resolution technique best describes this scenario?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Withdrawal

    This question tests the 'Withdrawal' conflict resolution technique. The act of postponing the decision to a later date is a direct match for withdrawal, whereas 'compromise' would require immediate agreement.

  120. Question 120 of 177The project manager has met with the project team and has informed them that his team performance assessments are done, and he would like to speak with each of them individually about the results. What process group is this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Executing

    This question tests the 'Executing' process group. Performance assessments and one-on-one coaching are direct activities associated with managing the team during the execution phase.

  121. Question 121 of 177While working on the network upgrade project, the project manager receives many ideas about what to include in the project. The ideas seem to be very scattered and not logically grouped. What tool can best help the project manager group these ideas?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Affinity diagrams

    This question tests the 'Affinity diagrams' tool. The specific purpose of an affinity diagram is to organize a large number of unstructured ideas into logical groupings for analysis.

  122. Question 122 of 177A project manager has just taken over an agile project that is about 50% complete. The project manager is currently reviewing the product backlog and notices the requirements are not in an order he understands. How is the product backlog prioritized?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. By value

    This question tests Agile product backlog prioritization. The fundamental principle is prioritization based on value to the customer or business, not secondary factors like cost or schedule.

  123. Question 123 of 177Senior management would like your project to have as few risks as possible. Which of the following contracts best meets their criteria?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Fixed price

    The correct answer, fixed price, demonstrates the lowest risk for the buyer. A contract's risk distribution is a key consideration for stakeholders prioritizing budget certainty.

  124. Question 124 of 177During a new workstation rollout project, a stakeholder asked for a change to some of the software being installed. The change was submitted to the Change Control Board but was rejected due to the high increase in cost of the software being requested. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Update the change log

    The correct answer confirms documentation is required for all change decisions. Updating the change log provides a formal record of the rejection, which is a core project management task.

  125. Question 125 of 177After a project manager is assigned to the project with the project charter, he continues to identify the stakeholders on the project. In this process, he creates the stakeholder register. Which of the following statements about the stakeholder register is false?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. It's only updated in the initiating phase of the project

    The correct answer identifies a key project management principle. The stakeholder register is a living document, updated continuously as new stakeholders are identified.

  126. Question 126 of 177The project manager decided to assign each team member on a project to no more than one activity at a time. This way, the team doesn't get burned out and can work at a steady pace. The schedule may increase due to this policy, which is okay with the sponsor. What technique best describes this action?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Resource leveling

    The correct answer defines the purpose of a common scheduling technique. Resource leveling smooths resource allocation to eliminate over-allocation, at the cost of extending the schedule.

  127. Question 127 of 177As an agile project manager, you have encountered many issues with the product owner. The product owner has refused to prioritize the product backlog, stating that all items are equally important. After educating the product owner about the value of prioritization, he still refuses. What should the agile project manager do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Continue to educate the product owner

    The correct answer shows coaching as a primary responsibility of an agile leader. The project manager's role is to guide and educate stakeholders on agile principles until they are adopted.

  128. Question 128 of 177Project manager Mark is currently working on a new office automation project and is consistently being asked for updates and meetings with the project sponsor. Mark informs the sponsor that the constant meetings disrupt his work, and his project is starting to fall behind schedule. The sponsor responds by saying that that is his management style. What best describes the sponsor's management style?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Theory X

    The correct answer proves Theory X, a micromanagement style based on distrust. The distractors are eliminated by recognizing Theory Y's trust-based approach and the other concepts' unrelated focus.

  129. Question 129 of 177While building the agile space for new agile team, which of the following tools should the project manager ensure is available to all of them?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. A whiteboard

    The correct answer proves Whiteboard, a key low-tech tool for collaboration. The trap is distractors with high-tech solutions that hinder face-to-face engagement.

  130. Question 130 of 177The project manager is conducting a presentation with a few of the senior stakeholders, and they are not happy with the progress of the project. The project manager has informed them that the delay is due to a contractor that was affected by a major flood a few weeks ago. What process does this best describe?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Manage communication

    The correct answer proves that this is about actively engaging stakeholders with project updates. Options C and D are distractors that name non-existent processes.

  131. Question 131 of 177After many years of following the agile principles the project team has implemented a few new methods in addition to the agile methods in order to increase the efficiency of the project. This will be known as?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Process tailoring

    The correct answer defines the process of customizing a methodology. Option B is a distractor that labels the new methods incorrectly.

  132. Question 132 of 177The project manager has just identified a new regulation that can possibly delay the project significantly. The project manager has added this new regulation to the risk register. What should the project manager do next with this risk?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Conduct a qualitative and quantitative assessment

    The correct answer proves the process of analyzing risks before developing a response. Option A is a distractor that jumps to a response without analysis.

  133. Question 133 of 177While working on the workstation upgrade project, the project sponsor informs the team that they have to stop the project immediately and start working on a router upgrade project. The sponsor wants the router upgrade project to start in as little as 2 days. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Conduct the close project or phase process for the current project and write the final report.

    The correct answer proves the required procedure for project termination. Option C is a distractor that addresses the new project instead of closing the old one.

  134. Question 134 of 177While working on a network upgrade project, a team member installed the network connection and is now configuring the router in order to work with the network connection. The network connection must be done before the router can be configured. This is an example of what kind of dependency?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Mandatory dependency

    Mandatory dependency requires a specific sequence, proven here by the router needing the network connection first. Distractors like 'internal' miss the required nature of the sequence.

  135. Question 135 of 177The project was executed about 3 weeks ago, and the project team seems to be having a lot of difficulties getting along with each other. They are always having conflicts about how to proceed on certain activities, and the project manager has to step in in order to solve these conflicts. What process is the project manager performing?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Manage Team

    Manage Team is the process for resolving team conflicts using interpersonal skills. Control Resources and Control Scope are unrelated to team dynamics.

  136. Question 136 of 177The project manager is currently working on a large building renovation project. The project team is almost done with planning when the project sponsor informs the project manager that due to new regulations, the project will need to be completed within 6 months; if not, they will not be able to open the building to the public. What best represents this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Constraints

    A constraint is a limitation, such as the required project completion time. Deliverables and work packages are project outputs, not constraints.

  137. Question 137 of 177The project manager and sponsor are consulting with banks and other lending institutions in order to obtain funds for the project. What process describes these actions?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Determine budget

    Determine Budget uses financing to seek project funds. The charter authorizes the project, and cost management planning is separate.

  138. Question 138 of 177While working with the system administrator, the project manager identifies many different types of resources required for the project to be completed successfully. The project manager classifies them as HR, material, equipment, and consumable resources. Where can the project manager best document these resources?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Resource breakdown structure

    Resource breakdown structure categorizes resources by type, like HR or equipment. Other options describe different outputs.

  139. Question 139 of 177While working on a complex web design project, the manager has received a change request from a senior stakeholder to fix a problem with the current intranet server. The project manager has determined that this change is outside the scope of the project and is not covered by the work listed in the project charter. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Inform the stakeholder that this change request should be considered a new project

    The correct answer proves that a change outside the project scope should be treated as a new project. The trap is distractors that imply accepting or processing the change within the current project framework.

  140. Question 140 of 177You are currently working on a large building demolition project. There are many requirements for the potential vendors on the project, and you would like to ensure that they all receive the same information. What is the best tool or technique to ensure all vendors receive the same information about the project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Bidder Conference

    The correct answer identifies bidder conference as the tool to ensure consistent information for all potential vendors. The elimination cue is that other options are project documents, not communication techniques for vendors.

  141. Question 141 of 177The project team has been working very hard over the last 4 months to program the financial application and has completed it. The project manager has informed the team that the quality control team will be inspecting it next. What process group best describes what the team has done so far?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Executing

    The correct answer identifies the executing process group, where deliverables are produced. The elimination cue is that other process groups involve planning, control, or closure, not active work.

  142. Question 142 of 177While working on a new server upgrade project, the project manager calculates the SPI of the project to be 1.3. The project sponsor would like an explanation for why the SPI is that high. What would be the project manager's best response?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The project team were able to finish the work faster than anticipated and this is what led to the project being ahead of schedule

    The correct answer proves that an SPI greater than 1 indicates the project is ahead of schedule. The trap is distractors suggesting the project is on schedule or behind schedule.

  143. Question 143 of 177The project manager is having a difficult time keeping the project on plan. There are many changes regarding the project scope, which has led to an increase in the project budget. Management would like a reason why there have been so many scope changes on this project. What would most likely cause many scope changes on a project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Did not gather detailed requirements.

    The correct answer identifies poor requirements gathering as the primary cause of scope changes. The elimination cue is that other options are unsupported by the information given in the scenario.

  144. Question 144 of 177The project team is having a very difficult time deciding what method they should use when programming the new functions in the application. They can choose between four different methods, and the team is evenly split regarding which method to choose. The project manager has decided that he will choose the method for them and will take the responsibility in case it is not the best way to program functions. What best describes this technique?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Autocratic

    The autocratic decision-making technique allows a single individual to make decisions and take full responsibility. This contrasts with team-based approaches like voting, where the group collectively decides.

  145. Question 145 of 177The project sponsor has signed off on the project charter and has spoken to the project manager, who then has to keep the cost down on the project. The project manager agrees to try his best to keep cost down and to finish the project under budget. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Meet with the stakeholders to gather their requirements

    After the project charter, the immediate next step is to gather detailed stakeholder requirements. This information is essential before defining scope, creating the WBS, and developing a realistic cost baseline.

  146. Question 146 of 177One of the customers would like to add a new component to the project that would likely increase the functionality of the software. What steps should the customer take when adding this new component on an Agile project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Add it to the product backlog

    In Agile, new features or requirements are submitted as items in the product backlog. They are then prioritized and planned for a future sprint, allowing for flexibility and change.

  147. Question 147 of 177The project manager has decided that most of the stakeholders on the project would like to reference the status reports for the project on the company's internal website on their own time. This would make it easier for them, as it is very difficult to schedule a meeting with all of them at once. What type of communication best describes this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Pull communication

    Pull communication is when stakeholders access information on their own time. Push communication sends information to stakeholders, while interactive communication is real-time.

  148. Question 148 of 177A project manager working in a large multinational corporation has been assigned to upgrade the company's website. This project will require inputs for many functional managers across the organization from different countries. Each functional manager would like one of their representatives to be present on the project team. What would be the best tool or technique for handling this scenario in a cost-effective way?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Using virtual teams

    Virtual teams are a cost-effective way to collaborate across locations. Collocation is expensive and impractical for this multinational scenario.

  149. Question 149 of 177While working on a large utility project for a major metropolitan area, the project manager has noticed that there is no change control board to approve changes for the project. What would be the best step for the project manager to take in this scenario?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Establish a change control board for the project

    The project manager should establish a change control board for a large project. The sponsor's approval is typically reserved for smaller projects.

  150. Question 150 of 177While working on a project, the CEO of the company has informed you that he would like to terminate the project and have you work on a few other projects. What kind of influence does this best represent?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Upwards

    Correct answer demonstrates upward influence with senior management. Distractors trap candidates by misapplying directional influence types downwards, sideways, or outwards.

  151. Question 151 of 177While working on an agile project, the project manager met with the project team members to discuss what they did the day before and what they plan to do today. What is the name of this meeting?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Daily stand-up meeting

    Correct answer identifies the daily stand-up by its three-question purpose. The trap is distractors for other agile ceremonies like sprint planning or review.

  152. Question 152 of 177The project team has completed a major deliverable on the game development project. The deliverable was given to the project manager. What action should the project manager take next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Check the deliverable for quality requirements

    Correct answer shows the immediate next step is quality control verification. The trap is distractors jumping to later steps like acceptance or closure.

  153. Question 153 of 177The project manager is working on a project for which the scope, time, and cost are known during the early parts of the project planning. What life cycle will the project manager consider on this project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Predictive life cycle

    Correct answer identifies the predictive life cycle by its upfront planning nature. Distrators misrepresent other life cycle types like iterative.

  154. Question 154 of 177The project team has completed a bidder conference for the office renovation project. Over 15 different construction companies came to the conference. Directly after the conference, all the companies submitted their bids immediately. What is the next step the project team should take?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Select the seller

    Correct answer shows the immediate next step is seller selection. Distrators trap candidates by naming procurement inputs instead of outputs.

  155. Question 155 of 177The project team is currently working on a project to upgrade all the servers across the organization. Before they are able to get the financial server, the vendor calls and says the server delivery has been delayed 2 weeks. What documents should the project manager update immediately?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Issue log

    Issue logs record unresolved problems for tracking. Schedule updates or change requests come later after initial logging.

  156. Question 156 of 177While compiling all the work performance information into the work performance report, a project manager notices that the SPI of the project is .6 and the CPI is .7. What action should the project manager take next on this project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Create a change request to correct the project.

    An SPI of .6 and CPI of .7 indicate significant schedule and budget variances requiring corrective change requests. Simply reporting the problems is insufficient.

  157. Question 157 of 177The project planning has been completed for the office renovation project. The project management plan has been approved by the sponsor and senior management. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Hold a kickoff meeting

    After approval, a kickoff meeting aligns the team on the plan. Senior management is already aware, and deliverables acceptance comes later.

  158. Question 158 of 177The project manager has reviewed all the work performance information that has been created so far on the project. He has started to create the overall project status report to present to the project stakeholders. What process is the project manager conducting?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Monitor and control project work

    Monitoring and controlling project work involves using performance information to create reports on the project's status.

  159. Question 159 of 177A team member is working on upgrading the network server while another team member is painting the server room. The outcomes of these two events will not affect each other. What best describes the relationship between these two events?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. There are statistically independent

    Statistically independent events do not influence each other's outcomes, which is the case here.

  160. Question 160 of 177A project manager has completed the project status report. The report states the CPI is 1.1 and the SPI is 1.14. The report was given to the project sponsor, who has become very upset about the project's progress and has requested an immediate meeting with the project manager. What should the project manager report in the meeting?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The project is progressing on schedule and budget

    A CPI and SPI both greater than 1 indicate the project is under budget and ahead of schedule.

  161. Question 161 of 177Which of the following would be considered waste on a project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Waiting

    The correct answer proves waiting is non-value-added time. Value-added features and processes contribute to the product, while completed work is the desired outcome.

  162. Question 162 of 177Two team members were having a conflict over what programming method should be used on the new application. They have resolved the conflict. What would be their next step?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Implement the new method and verify that it solves the actual problem.

    The correct answer proves that resolving conflict requires implementing and verifying the solution. The trap is assuming resolution equals completion, ignoring the need to confirm effectiveness.

  163. Question 163 of 177Managing a project can be a very complex task that involves identifying and managing all the stakeholders on the project. The project manager spends 90% of their time doing what important task?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Communications

    The correct answer proves that communication dominates a project manager's time. The elimination cue is that estimating cost and duration is the responsibility of subject matter experts, not the project manager.

  164. Question 164 of 177While developing very complex software, the project manager met with some of the industry's top subject matter experts to understand their perspectives on solving some of the problems in the software. What tool best describes these meetings?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Focus groups

    This question tests the 'Focus groups' tool. Bringing together SMEs to discuss their perspectives is a primary function of a focus group, while 'brainstorming' typically involves generating new ideas from a group.

  165. Question 165 of 177While managing the stakeholders' engagement, the project manager notices that some of the team members are not respectful to other team members. This has led to a few conflicts between the members. What can the project manager best do about this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Implement ground rules

    This question tests 'Implementing ground rules'. The best immediate response to behavioral issues is to enforce established team rules, which are a standard tool for managing team interactions.

  166. Question 166 of 177The datacenter redesign project has been executed and is currently 50% complete. One of the project's key stakeholders has submitted a change request to change the building's wiring from copper cables to fiber cables. The project manager has contacted a wiring contractor, who said it will take about 2 months to install the fiber at a cost of $2 million. What should the project manager do next?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Submit the change to change control board

    The correct answer proves the change control board process. Formal approval, not individual manager decisions, is required before updating project plans.

  167. Question 167 of 177While working on an agile project, the sponsor would like to know how much work remains to be completed on the project. The project manager has scheduled a meeting with the sponsor for the next day. What tool would be best for the project manager to take to the meeting?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Burndown chart

    The correct answer demonstrates the use of a key agile reporting tool. The burndown chart visually communicates remaining work, which is a primary metric for sponsors.

  168. Question 168 of 177The project manager, Mark, overheard that the project team is not satisfied with the way the budget was created. They strongly believe the project will be over budget at the end. What is the next best step for Mark?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Bring the team together and attempt to understand why they feel this way.

    The correct answer demonstrates stakeholder communication best practices. The immediate step is to understand the root cause of team concerns before taking corrective or escalated action.

  169. Question 169 of 177What is the difference between the product backlog and the iteration backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The product backlog contains all work needed to be completed on the project, and the iteration backlog will contain all work that will get done in the next iteration

    The correct answer proves the Product Backlog is all project work, while the Iteration Backlog is just the next cycle's work. The distractor's mistake is reversing their scopes.

  170. Question 170 of 177The product owner has added three new changes to the product backlog. The agile project manager has met with the team and they have decided immediately how to implement these new changes, although these changes will be implemented until three iterations from now. The product owner informs the agile project manager that he is not happy about this. What should the agile project manager do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Tell the team they should not have committed to doing these changes until they were ready to implement them

    The correct answer demonstrates the agile principle of deferring decisions until necessary. Option A is a distractor that ignores the core principle of not committing to future work.

  171. Question 171 of 177A project manager is having difficulties communicating with the project team; there always seem to be misunderstandings and conflicts. What interpersonal and team skills should the project manager improve on?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Active listening

    Active listening reduces misunderstandings by ensuring full comprehension. Distractors like 'passive' are counterproductive skills.

  172. Question 172 of 177While monitoring and controlling the project, the project manager and the team have consistently received broken equipment from a particular vendor. They have spoken with the vendor and implemented a new process that will ensure the equipment does not show up broken. This seems to have solved the problem. What is the next step the project manager should take?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Check the solution

    The correct answer shows the final step in problem-solving is to verify the solution. The trap is distractors representing earlier problem-solving steps that have already been completed.

  173. Question 173 of 177The project manager and team have decided to hire a contractor to complete the installation of the servers for the system's upgrade project. The terms of agreement have the contractor being paid on a monthly basis until the work is done. During what process will the contractor payments be made?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Control procurement

    Contractor payments occur during the Control Procurement process. Plan Procurement determines what to buy, and Conduct Procurement selects the seller.

  174. Question 174 of 177Mark is currently working on the workstation upgrade project. He has noticed there are three activities on the critical path, which are activity A, C, and D. Activity B has a slack of 2 and a duration of 4 days. Activity C has a duration of 3 days, and activity D has a duration of 6 days. What is the slack on activity A?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. 0 days

    Correct answer proves critical path activities have zero slack. The trap is unnecessary calculation distractors since A is on the critical path.

  175. Question 175 of 177The project manager has released the project team, completed the final lesson learned, and then completed the final report. The PMO has informed the project manager that it is not happy with this approach. What has the project manager done wrong?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Releasing the team and then doing lessons learned

    Correct answer shows lessons learned should involve the team. The trap is distractors that focus on minor procedural order errors.

  176. Question 176 of 177What is considered the single most important skill a project manager should have?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Communication

    Communication is essential for stakeholder alignment and team coordination. Projects fail without it.

  177. Question 177 of 177The project manager has just spoken to one of the software developers, Bill, about the project and has asked for an estimate of how long it will take to code a specific function. Bill said that it would take a maximum of 10 days, but that most likely it will be 6 days. The project manager has calculated the PERT estimated duration of this activity to be 6 days. What is the least amount of days it will take to complete this activity?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. 2

    The least amount of days is the optimistic estimate. Using the PERT formula with the given duration reveals the optimistic estimate is 2 days.

This test also exists as narrated videos — every answer explained out loud: