Professional Scrum Master I (PSM I) Practice Test – 554 Free Exam Questions with Answers

Professional Scrum Master I (PSM I)

554 questions · instant answer feedback · concise explanations · free

  1. Question 1 of 554What are the three questions the Sprint Planning answers?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Why, What and How ?

    Sprint Planning answers why the Sprint is valuable, what can be completed, and how the chosen work will get done. Remember that the event focuses on value, scope, and actionable planning rather than strict scheduling.

  2. Question 2 of 554Who creates a Product Backlog item's estimate?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers after clarifying requirements with the Product Owner

    The people doing the work create the estimates. The Product Owner might influence them by clarifying details, but the Developers hold the final say to ensure commitment and accuracy.

  3. Question 3 of 554By the end of the Sprint Retrospective, the Scrum Team should have identified:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Improvements that it may implement in the next Sprint

    The outcome of the Sprint Retrospective is identifying actionable improvements for the next Sprint. It focuses on process adaptation rather than finalizing the exact work scope for the next Sprint.

  4. Question 4 of 554The Sprint Retrospective is an opportunity for the Scrum Team to:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. inspect itself and create a plan for improvements

    The Sprint Retrospective is dedicated to team introspection and creating actionable improvement plans. Choosing the next Sprint's scope happens during Sprint Planning, not the Retrospective.

  5. Question 5 of 554When does the second Sprint start?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Immediately after the first Sprint

    A new Sprint starts immediately after the conclusion of the previous Sprint. Sprints are continuous cycles with no gaps in between. Eliminate any options suggesting dependencies on external approvals or integration phases between Sprints.

  6. Question 6 of 554Which of these may a Scrum Team deliver at the end of a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. An increment of working product that is "done"

    The team delivers an increment of working product that is done. Remember that an increment must meet the definition of done and be usable. Options involving bugs or documents are incorrect because they violate this quality requirement.

  7. Question 7 of 554Which of the following points could be discussed by the Scrum Team during a Sprint Retrospective?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. All answers are correct

    A sprint retrospective examines interactions, processes, tools, and the definition of done. Option B is correct because all listed items are valid discussion topics. This event focuses on continuous improvement rather than the product itself.

  8. Question 8 of 554What is the source of the requirements for any changes to the product? (choose the BEST answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Backlog

    The Product Backlog is explicitly defined in the Scrum Guide as the single source of requirements for any changes made to the product. For the exam, remember that stakeholders or the CEO provide input, but the structured requirements live only in the Product Backlog.

  9. Question 9 of 554Who is responsible for conducting the Daily Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers

    The Developers are solely responsible for conducting the Daily Scrum to inspect progress toward the Sprint Goal. The Scrum Master ensures the event happens and stays within the time-box, but does not run the meeting.

  10. Question 10 of 554Who must attend the Daily Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Developers

    Only the Developers are required to attend the Daily Scrum to inspect progress and adapt their plan. The Product Owner or Scrum Master may attend if they are actively doing development work, but the event is specifically for the Developers.

  11. Question 11 of 554What is the main reason for the Scrum Master to be at the Daily Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. He or she does not have to be there; he or she only has to ensure the Developers have a Daily Scrum

    The Scrum Master does not need to attend the Daily Scrum; their primary accountability is simply ensuring that the Developers hold the event. The Daily Scrum is owned by the Developers, so the Scrum Master acts as a facilitator only if requested.

  12. Question 12 of 554When is the Sprint Backlog created?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. During the Sprint Planning meeting

    The Sprint Backlog is initially created during the Sprint Planning event as the team determines the Sprint Goal and the work required. It is highly visible and can then be updated throughout the Sprint as new work is discovered.

  13. Question 13 of 554A Scrum Team is only allowed to meet with stakeholders during the Sprint Review.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Scrum strongly encourages ongoing collaboration with stakeholders throughout the entire Sprint, not just during the Sprint Review. The Sprint Review is a formal checkpoint, but developers can clarify requirements with stakeholders anytime.

  14. Question 14 of 554What best describes the Sprint Backlog? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Product Backlog items selected for this Sprint plus the plan for delivering them.

    The Sprint Backlog consists of the selected Product Backlog items for the Sprint, the Sprint Goal, and an actionable plan for delivering them. Choosing an option without the delivery plan ignores the highly visible nature of this artifact.

  15. Question 15 of 554Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Developers

    The Sprint Backlog belongs solely to the Developers, giving them exclusive authority to update it during the Sprint. The Scrum Master and Product Owner do not direct these daily technical adjustments, ensuring the team remains self-managing.

  16. Question 16 of 554A Product Owner wants advice from the Scrum Master on estimating work in Scrum. Which of these is the guideline that the Scrum Master should give?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Estimates are made by the Developers

    The Developers performing the work are solely responsible for all sizing and estimation. The Product Owner might clarify details, but mandating specific units like story points goes against Scrum principles of team autonomy.

  17. Question 17 of 554Who is responsible for representing the stakeholders?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner

    The Product Owner represents the stakeholders to the Scrum Team, ensuring their needs are reflected in the Product Backlog. Traditional roles like Project Manager do not exist in Scrum, making this accountability exclusive to the Product Owner.

  18. Question 18 of 554When might a Sprint be abnormally terminated?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. When the Sprint Goal becomes obsolete

    A Sprint is abnormally terminated only when the Sprint Goal becomes completely obsolete. If work remains unfinished, the team simply continues the Sprint, as cancellation is rare and costly due to short timeboxes.

  19. Question 19 of 554A Developer on the Scrum Team takes the Scrum Master aside to express concerns about data security issues. What should the Scrum Master do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Ask the person to share the issue with the rest of the Scrum Team as soon as possible

    The Scrum Master should ask the Developer to share the issue with the entire Scrum Team to foster transparency and collective problem-solving. Unilaterally adding security to the Definition of Done bypasses the team's autonomy.

  20. Question 20 of 554When Developers have difficulty delivering a functional increment because they don't understand a functional requirement, what should they do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Collaborate with the Product Owner to determine what is possible and acceptable

    Developers should collaborate directly with the Product Owner to determine what is possible and acceptable. Deferring work or partially completing it without this clarification avoids the necessary clarification needed to satisfy stakeholder needs.

  21. Question 21 of 554During the Sprint, if new work is required, the Developers can add it to the current Sprint Backlog.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    The Sprint Backlog emerges throughout the Sprint as the Developers learn more about the work needed to achieve the Sprint Goal. The Developers own the Sprint Backlog and can add new items whenever necessary.

  22. Question 22 of 554A Scrum Team is required to deliver a done increment by the end of a Sprint. Select two statements that explain what "Done" means. (Choose 2)

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. No work left from the definition of "Done" · C. All work to create software that is ready to be released to end users

    Done means no work remains according to the Definition of Done, ensuring the Increment is potentially releasable to users. Remember that quality standards are set by the whole Scrum Team, not just the Product Owner.

  23. Question 23 of 554What are the three pillars of product ownership?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Value, Decision Making, Engagement

    Product ownership is built on value, decision making, and engagement. The Product Owner maximizes value, makes important product decisions, and actively engages with stakeholders and the Scrum Team.

  24. Question 24 of 554Which three phrases best describe the purpose of a Definition of Done? (Choose 3)

    Select 3 answers.

    Show answer & explanation

    Correct answer: B. It guides the Developers in creating a forecast at the Sprint Planning · C. It defines what it takes for an increment to be potentially ready for release · D. It creates transparency over the work inspected at the Sprint Review

    The Definition of Done guides the Sprint forecast, clarifies Increment release readiness, and ensures transparency during the Sprint Review. It is not a task checklist or a percentage tracker, but rather a quality gate.

  25. Question 25 of 554Which topics are covered during Sprint Planning?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Why is this Sprint valuable, What can be Done this Sprint and How will the chosen work get done?

    Sprint Planning covers why the Sprint is valuable, what can be done, and how the work will get done. Avoid options that assign tasks or dictate roles, as self-managing Developers determine their own plan.

  26. Question 26 of 554What happens if the Developers cannot complete their work by the end of the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Sprint length holds and the Developers continuously learn what is actually possible to do within a sprint of this length

    A Sprint is fixed in length and is never extended, serving as a predictability mechanism. Incomplete Product Backlog items are returned to the Product Backlog for future consideration.

  27. Question 27 of 554How should the Developers deal with non-functional requirements?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Ensure every Increment meets them

    Developers must ensure every Increment meets non-functional requirements. Often captured in the Definition of Done, these standards apply continuously, making hardening phases unnecessary.

  28. Question 28 of 554When does the next Sprint begin?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Immediately after the conclusion of the previous Sprint

    A new Sprint begins immediately after the previous Sprint concludes. This creates a consistent, predictable rhythm with no gaps. Avoid distractors that suggest waiting for a specific day or requiring prior approval to continue.

  29. Question 29 of 554Who determines how work is performed during the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers

    Developers determine exactly how to perform the work during the Sprint. They are self-managing and create their own plan. External managers or architects cannot dictate daily work to a self-managing Scrum Team.

  30. Question 30 of 554When is a Sprint over?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. When the time-box expires

    A Sprint ends precisely when its fixed time-box expires. Work completion does not alter the schedule. Maintaining strict time-boxes ensures predictable inspection cycles and stable planning.

  31. Question 31 of 554A Scrum Master is introducing Scrum to a new Scrum Team. The Developers have decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Begin facilitating productive and useful Scrum Retrospectives

    The Scrum Master must ensure all Scrum events take place and remain productive. If a new team wants to skip the Retrospective, the Scrum Master steps in to facilitate it, because self-management does not mean abandoning required Scrum events.

  32. Question 32 of 554Who is responsible for ensuring that the new increments meet the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Developers

    The Developers are responsible for ensuring that every Increment meets the Definition of Done. A practical exam cue is to always associate quality and meeting the Definition of Done directly with the Developers, never the Scrum Master or Product Owner.

  33. Question 33 of 554For the purpose of transparency, when does Scrum say a new increment must be available?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. At the end of every Sprint

    Scrum requires a new Increment to be available at the end of every Sprint. Ignore options suggesting specific phases or multiple Sprints; always tie Increment creation directly to the conclusion of each Sprint boundary.

  34. Question 34 of 554Who has the final say on the order of the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. The Product Owner

    The Product Owner has the final say on Product Backlog ordering to maximize value. While others may influence the Product Owner, the ultimate accountability for backlog ordering and content always rests solely with this role.

  35. Question 35 of 554A product increment must be released to production at the end of each Sprint.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    An increment must be in a usable condition and meet the definition of done, but the product owner decides if it makes sense to actually release it. Remember that releasable and released are completely different concepts.

  36. Question 36 of 554Who is allowed to change the Sprint Backlog during the Sprint? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Developers

    The sprint backlog belongs solely to the developers, so they are the only ones who change it during the sprint. While the product owner might negotiate scope, only the developers manage the actual work plan.

  37. Question 37 of 554What are the Product Owner's responsibilities during the interval between the conclusion of the current Sprint and the initiation of the next Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner has no specific interval responsibilities between Sprints, as the next Sprint begins immediately following the conclusion of the previous one.

    A new sprint starts immediately after the previous one concludes, meaning there is no gap or interval between them. Any backlog refinement or planning simply happens inside the sprint timebox itself.

  38. Question 38 of 554What does the word 'development' mean in the context of Scrum? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. Complex work that can include, but is not limited to, all of the suggested options above.

    In Scrum, development refers to any complex work, not just writing software. The framework applies to hardware, research, and product enhancement, so the option including all suggested examples is correct.

  39. Question 39 of 554Product Backlog Refinement… (choose the best two answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. Is the act of breaking down and further defining Product Backlog items into smaller more precise items · B. Is an ongoing activity to add details, such as a description, order, and size

    Refinement breaks down large items and adds details like description and size. It is an ongoing activity throughout the sprint, rather than a single timeboxed event or a session strictly for sprint planning.

  40. Question 40 of 554What does the word "increment" mean in the context of Scrum? (Choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. A potentially releasable piece of the product that adds value and meets the Definition of Done.

    An increment is a valuable, usable piece of the product that fully meets the definition of done. Work cannot be called an increment if it does not meet this quality standard, regardless of its potential.

  41. Question 41 of 554When can a Developer cancel a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Never. Only Product Owners can cancel Sprints

    Only the product owner has the authority to cancel a sprint, though developers or others might influence that decision. Remember that scrum masters and developers never hold cancellation authority.

  42. Question 42 of 554What does a self-managed Scrum Team choose?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. How to best accomplish its work

    A self-managing Scrum Team decides internally who does what, when, and how to best accomplish its work. The Product Owner orders the Product Backlog, and developers collaborate on technical execution rather than waiting for external management.

  43. Question 43 of 554Which commitment from the Sprint Planning provides the Developers with an overall goal and direction for the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Sprint Goal

    The Sprint Goal provides the overarching objective and direction for the Sprint, giving Developers flexibility in their work. It acts as the primary commitment created during Sprint Planning, keeping the team focused on delivering coherent value.

  44. Question 44 of 554Who is responsible for tracking the remaining work of the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Developers

    Developers are responsible for tracking the remaining work of the Sprint because they self-manage their daily work. The Product Owner tracks the overall Product Backlog, while a traditional Project Manager role does not exist in Scrum.

  45. Question 45 of 554When is it most appropriate for a Scrum Team to change the Definition of "Done"?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. During the Sprint Retrospective

    The Sprint Retrospective is the designated event for the Scrum Team to inspect itself and create an improvement plan. This is the most appropriate time to adapt the Definition of Done to improve quality, provided it does not conflict with organizational standards.

  46. Question 46 of 554Which of the following choices is the most effective way for a Scrum Master to maintain a Scrum Team at its highest level of productivity?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Coach the Scrum Team members and cause the removal of impediments to the team's progress

    The Scrum Master serves the team by coaching developers and removing impediments. Remember that forcing backlog constraints or acting as a meeting enforcer misses the larger focus of servant leadership and enabling flow.

  47. Question 47 of 554Which best describes the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. It is allowed to grow and change as more is learned about the product and its customers

    The Product Backlog is allowed to grow and change as more is learned. It is a living artifact that evolves with the product. Avoid options suggesting baselining or treating it as a fixed project plan.

  48. Question 48 of 554What are considered attributes of a Product Backlog? (choose the best three answers)

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. As long as a product exists, its Product Backlog also exists. · C. It is dynamic. · E. It is never complete.

    A Product Backlog is dynamic, never complete, and exists as long as the product does. It evolves continuously to maximize value. Eliminate options claiming a backlog is closed or unneeded after specific releases.

  49. Question 49 of 554The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.

    The Scrum Master serves the Product Owner by helping them maximize value through effective backlog management. The Scrum Master guides but never takes over the ordering process. Avoid options suggesting Sprints be extended.

  50. Question 50 of 554When Developers determine that they have over-committed themselves for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner and the Developers

    Developers renegotiate work with the Product Owner if they overcommit. The Product Owner must be present to clarify priorities and adjust scope. Stakeholders and managers are not required for this mid-Sprint adaptation.

  51. Question 51 of 554The Scrum Master participates in the Sprint Retrospective as a:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Peer team member

    The Scrum Master participates in the sprint retrospective as a peer team member. They share equal footing while inspecting processes. The Scrum Master is neither a silent observer nor a traditional team leader dictating decisions.

  52. Question 52 of 554The Sprint Review is no more than a demo of the Product Backlog items completed during a Sprint. Is this statement correct?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. No, the Sprint Review contains much more activities.

    A sprint review is much more than just a demo; it includes inspecting the increment and adapting the product backlog. Stakeholders collaborate on next steps. A demo is only a small part of this adaptive event.

  53. Question 53 of 554What is the most suitable structure for Scrum Teams to produce integrated increments?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Each Scrum Team develops functionality from beginning to end, across all technical layers.

    Cross-functional teams that develop features across all technical layers are best suited for Scrum. Avoid component teams, as working on isolated technical layers creates hand-offs and delays the creation of a valuable, usable Increment.

  54. Question 54 of 554How often should the Scrum Team membership change?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. As needed while taking into account a short-term reduction in productivity

    Scrum Team membership should change as needed, but the team must account for a short-term reduction in productivity. Frequent changes disrupt team dynamics, so the guide warns against changing compositions without recognizing this cost.

  55. Question 55 of 554How much of the Sprint Backlog must be defined during the Sprint Planning meeting?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Enough so the Developers can create its best forecast of what it can do, and to start the first several days of the Sprint

    The Developers need just enough Sprint Backlog detail to confidently forecast their work and begin the first few days. Avoid options demanding complete upfront task estimation, as the Sprint Backlog evolves throughout the Sprint.

  56. Question 56 of 554What enhances the transparency of an increment?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Doing all work needed to meet the Definition of Done

    Meeting the Definition of Done ensures transparency because everyone shares a clear understanding of what completed work entails. Tracking tools or estimating undone work does not inherently make the increment transparent, as only done work is truly inspectable.

  57. Question 57 of 554What is the recommended size for a Scrum Team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. 10 or fewer people

    A Scrum Team is small enough to remain nimble and large enough to complete significant work, which is typically ten or fewer people. Smaller teams communicate better and are more productive, while larger teams should reorganize into multiple cohesive teams.

  58. Question 58 of 554The Product Owner is accountable for effective Product Backlog management, which includes:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Developing and explicitly communicating the Product Goal

    Developing and explicitly communicating the Product Goal is a direct accountability of the Product Owner. Option D is a strong distractor because establishing empirical product planning is the responsibility of the Scrum Master, not the Product Owner.

  59. Question 59 of 554Who is responsible for ensuring that all Scrum events take place, are productive, and kept within the timebox?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Master

    The Scrum Master ensures all Scrum events take place, are positive, and stay within the timebox. While the whole team participates, the Scrum Master acts as the facilitator and process enforcer.

  60. Question 60 of 554Every Scrum Team should have:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The competencies and skills needed to deliver a Done Increment in a Sprint

    A Scrum Team must collectively possess all the skills needed to create a Done Increment each Sprint. Cross-functionality means the team works together without needing specific departmental roles.

  61. Question 61 of 554According to the Scrum theory, how should a group of 100 people be divided into several Scrum Teams?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Understanding the product, the product vision and the rules of the Scrum framework, the group divides itself into teams.

    Scrum Teams are self-managing, so the group should divide itself based on the product vision and rules. A key exam cue is that management never assigns people to teams. Self-organization is fundamental to agility.

  62. Question 62 of 554Who is the chief product visionary? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Product Owner

    The Product Owner is the primary product visionary, responsible for maximizing value and communicating the vision. While executives influence strategy, the Product Owner solely owns the product direction.

  63. Question 63 of 554Why does the Daily Scrum take place at the same time and place?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The consistency reduces complexity

    Holding the Daily Scrum at the same time and place reduces complexity and overhead. This consistency lets the team focus entirely on planning the next day. Logistics like room bookings are logistical distractors.

  64. Question 64 of 554When does the Sprint Retrospective occur?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. After the Sprint Review and prior to the next Sprint Planning

    The Sprint Retrospective occurs after the Sprint Review and right before the next Sprint Planning. For the exam, memorize the exact sequence of Scrum events to easily eliminate options that break the flow of the Sprint.

  65. Question 65 of 554How much work must the Developers of the Scrum Team do on a Product Backlog item they select for a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. As much as they have told the Product Owner will be done for every Product backlog item they select in conformance with the Definition of Done.

    Developers must complete work on a Product Backlog item so it meets the Definition of Done during the Sprint. Avoid options that suggest splitting phases like testing into separate intervals, as Scrum requires fully done increments.

  66. Question 66 of 554Who is allowed to tell the Developers what work needs to be done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner

    The Product Owner is the sole person accountable for managing the Product Backlog and directing what work is needed. Remember that while others might suggest ideas, only the Product Owner controls the backlog ordering and content.

  67. Question 67 of 554What two things can a Scrum Master do if the Developers do not have the tools and infrastructure to completely finish each selected Product Backlog Item?

    Select 2 answers.

    Show answer & explanation

    Correct answer: D. Have the Scrum Team establish a Definition of Done that is actually possible to achieve given current circumstances · F. Coach the Scrum Team members to improve their skills, tools and infrastructure over time and adjust the Definition of Done accordingly

    The Scrum Master should help the team create a realistic Definition of Done and coach them to improve over time. Never choose exam options that suggest accepting incomplete work or temporarily stopping feature delivery to focus solely on infrastructure.

  68. Question 68 of 554Which of the following is required by Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Sprint Retrospective

    The Sprint Retrospective is a mandatory Scrum event. Dismiss options like burndown charts or release planning, as the exam strictly tests the framework without prescribing specific charts or scaling practices.

  69. Question 69 of 554What are the two primary ways a Scrum Master keeps a Scrum Team working at its highest level of productivity?

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. By causing the removal of impediments to the Scrum Team's progress · C. By coaching the team members in self-management and cross-functionality

    The scrum master serves the team by removing impediments and coaching developers in self-management and cross-functionality. Options like ordering the product backlog belong specifically to the product owner, not the scrum master.

  70. Question 70 of 554A Sprint Review is held at:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The end of the Sprint

    The sprint review takes place at the end of the sprint to inspect the increment and adapt the product backlog. The scrum team and stakeholders collaborate on what was built and what should happen next.

  71. Question 71 of 554What is the outcome of the Sprint Review?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. A revised Product Backlog

    The primary outcome of a Sprint Review is a revised Product Backlog that reflects stakeholder feedback and current market conditions. The Increment already exists from the Sprint, while updating the Definition of Done happens during the Sprint Retrospective.

  72. Question 72 of 554What are the reasons it is important to have only one Product Owner per product? Choose the BEST three answers.

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. It is clear who is accountable for the ultimate value of the product. · C. The Scrum Team always knows who determines the order of the Product Backlog. · E. It helps avoid barriers to effective communication and rapid decision-making.

    A single Product Owner ensures clear accountability for product value, provides a sole decision-maker for backlog ordering, and removes communication barriers. Options about confusing stakeholders or backup roles are incorrect distractors that miss core accountabilities.

  73. Question 73 of 554During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. As soon as possible after they are identified

    New work or further decomposition is added to the Sprint Backlog as soon as it is identified. This maintains transparency, though the Sprint Goal remains fixed. Avoid options suggesting formal approvals are needed for backlog updates during the Sprint.

  74. Question 74 of 554When is the Scrum Team allowed to interact with the Key Stakeholders? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Any time where it's valuable to have the Stakeholder input

    A Scrum Team can interact with Key Stakeholders any time it is valuable to do so. While the Sprint Review is a formal opportunity, collaboration is encouraged throughout development. Do not restrict stakeholder communication to only official events.

  75. Question 75 of 554What are the artifacts in Scrum? (choose all that apply)

    Select 3 answers.

    Show answer & explanation

    Correct answer: B. Product Backlog · C. Increment · D. Sprint Backlog

    The three Scrum artifacts are the Product Backlog, the Sprint Backlog, and the Increment. For the exam, remember that the Sprint Goal and Definition of Done are commitments to these artifacts, not artifacts themselves.

  76. Question 76 of 554What does it mean for a Scrum Team to be cross-functional?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment of product

    A cross-functional Scrum Team has all the skills necessary to deliver a Done Increment without relying on external teams. Watch out for options suggesting sub-teams or handoffs to specialists outside the Scrum Team.

  77. Question 77 of 554A new Developer is in conflict with other members of the Scrum Team, creating a hostile working environment. If necessary, who is responsible for removing the Scrum Team member?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Scrum Team is responsible, and may need help from the Scrum Master

    The Scrum Team manages its own membership and dynamics, so it holds the responsibility. The Scrum Master might facilitate the resolution. Do not confuse team accountability with the Scrum Master removing impediments.

  78. Question 78 of 554Which three statements about Scrum are true?

    Select 3 answers.

    Show answer & explanation

    Correct answer: C. Scrum is based on empirical process control theory · D. Scrum is a framework for developing and sustaining complex products · F. Each component of Scrum serves a specific purpose, and is essential to Scrum's success and your usage of Scrum to develop complex products

    Scrum is firmly grounded in empirical process control theory and acts as a minimal framework for complex product development. Every element of Scrum is essential, meaning you cannot simply pick and choose parts without losing its benefits.

  79. Question 79 of 554The Product Backlog is ordered by:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Importance, where the most important items are at the top at all times

    The Product Owner orders the Product Backlog by priority, value, risk, and dependencies to maximize product value. While smaller items often rise to the top, the primary driver is overall importance, making high priority the best answer.

  80. Question 80 of 554Which topics should be discussed at the Sprint Review?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Sprint results

    The Sprint Review focuses on inspecting the Sprint results and collaborating on what to do next. Engineering practices are typically evaluated during the Sprint Retrospective, not the Review. Keep event purposes distinct.

  81. Question 81 of 554When should the Scrum Team release the increment into production?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. When it makes sense

    Multiple increments may be released during a Sprint, but releasing to production only happens when it makes sense to maximize value. A defect-free increment does not automatically dictate a production release without business approval.

  82. Question 82 of 554What is included in the Sprint Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Any of the these options (or others) which are a decomposition of the selected Product Backlog items

    The Sprint Backlog contains the selected Product Backlog items and a plan for delivering them. Format choices vary, so answers naming specific artifacts like user stories or tasks are distractors. The core requirement is decomposing work to meet the goal.

  83. Question 83 of 554What is the accountability of the Product Owner during Sprint 0?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. There is no such thing as Sprint 0

    Scrum does not recognize a Sprint Zero or any preparatory Sprints before development begins. Every Sprint must produce a Done, usable Increment. Avoid pseudo-Sprints used for planning; remember that regular Sprints handle upfront work immediately.

  84. Question 84 of 554The Daily Scrum is an event that takes place every day. What would be the three main concerns if the frequency were to be lowered to every two or three days?

    Select 3 answers.

    Show answer & explanation

    Correct answer: D. Opportunities to inspect and adapt the Sprint Backlog are lost · F. The Sprint plan becomes inaccurate · G. Impediments are raised and resolved more slowly

    Reducing Daily Scrum frequency causes the Sprint plan to become inaccurate and impediments to be resolved more slowly. The team loses critical opportunities to inspect progress and adapt the Sprint Backlog toward the Sprint Goal daily.

  85. Question 85 of 554If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Its productivity is likely to decrease

    Adding new teams temporarily decreases the original team's productivity due to integration and knowledge transfer overhead. While long-term capacity increases, expect initial delays when forming new teams and managing dependencies.

  86. Question 86 of 554Which two ways of creating a Scrum Team are consistent with Scrum's values?

    Select 2 answers.

    Show answer & explanation

    Correct answer: D. Bring all the Developers together and let them self-organize · E. Existing teams propose how they would like to go about organizing into the new structure

    Scrum teams are self-managing and organize themselves rather than having managers assign them. Options D and E reflect this empowerment. Avoid options where managers or chiefs dictate team structures, as Scrum discourages that.

  87. Question 87 of 554James wants to use a waterfall approach for a project, and Lucia would like to use her Scrum Team. What is a disadvantage of using a waterfall approach?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. It has rigid guidelines of how to do the work.

    A disadvantage of waterfall is its rigid guidelines dictating how work must be done. This inflexibility contrasts sharply with Scrum. Watch out for distractors highlighting flexibility, which is actually a Scrum advantage.

  88. Question 88 of 554The Daily Scrum is held at the same time and place.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    The Daily Scrum is indeed held at the same time and place each day to reduce complexity and improve communication. For the exam, remember that consistency in this event helps the team inspect progress toward the Sprint Goal.

  89. Question 89 of 554The Developers are managed by:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. None of the above

    Scrum Teams are self-managing, meaning Developers decide how to accomplish their work without a traditional manager directing them. Options like the Scrum Master or Product Owner represent accountabilities rather than command and control management roles.

  90. Question 90 of 554At what point should the Product Owner update the project plan? Choose the most appropriate answer.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The project plan in Scrum is represented by the Product Backlog, which should be continuously updated as new information and insights emerge.

    Scrum avoids traditional project plans, utilizing the Product Backlog for continuous planning instead. The Product Owner updates the backlog as new insights emerge. A static plan contradicts empirical adaptation.

  91. Question 91 of 554You are the Scrum Master of a newly formed Scrum Team. Select three of the following activities that would probably help the team get started.

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Have the Scrum Team members introduce themselves to each others and give a brief background of their skills and work history · B. Ask the Product Owner to discuss the product or project, its history, goals, and context as well as answer questions · C. Ensure the Scrum Team understands they need a Definition of Done

    A new scrum team benefits from understanding the product context, meeting each other, and establishing a definition of done. Options like individual bonuses or management introductions violate core agile principles.

  92. Question 92 of 554Which of the following are accountabilities within a Scrum Team?

    Select 3 answers.

    Show answer & explanation

    Correct answer: D. Scrum Master · E. Product Owner · F. Developers

    The 2020 Scrum Guide defines exactly three accountabilities within a Scrum Team: Developers, Product Owner, and Scrum Master. Users and customers are important stakeholders but are not internal Scrum Team members.

  93. Question 93 of 554Who must participate in every Sprint Planning?

    Select 3 answers.

    Show answer & explanation

    Correct answer: B. The Product Owner · C. The Developers · F. The Scrum Master

    The entire Scrum Team, which includes the Developers, Product Owner, and Scrum Master, participates in Sprint Planning to collaborate on the upcoming Sprint. External stakeholders like the CEO attend only if invited by the team to provide specific input.

  94. Question 94 of 554Once the Sprint begins, its duration can be:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. Never extended

    A Sprint has a maximum duration and its timebox can never be extended once it begins. Fixed durations create predictability. Options suggesting extensions undermine the empirical process control fundamental to the framework.

  95. Question 95 of 554Which two activities are part of the Product Owner's role according to Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Ensuring that the most valuable functionality is produced at all times

    The Product Owner is accountable for maximizing product value and actively interacting with stakeholders to gather their input. They do not provide detailed technical specifications, as defining how to build the work belongs to the Developers.

  96. Question 96 of 554John is looking to create an agile team. He knows that he will need to rely on each person to help others learn new skills. This type of team is known as:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. cross-functional

    A team where members rely on each other and share skills to deliver value is cross-functional. For the exam, always associate Scrum Teams with being cross-functional and self-managing to complete work without depending on outsiders.

  97. Question 97 of 554Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose 2)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The value of work currently represented in the Product Backlog

    The Retrospective focuses on inspecting the past Sprint and adapting team processes, relationships, and tools. Discussing future Sprint Backlog planning or overall Product Backlog value belongs in Sprint Planning, making those the correct out-of-scope topics.

  98. Question 98 of 554During the Sprint, the Scrum Master's accountability is to help the Scrum Team with which two of the following? (Choose 2)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Causing the removal of impediments to the Scrum Team's progress

    The Scrum Master serves the team by causing the removal of impediments and helping the team focus on creating high-value Increments that meet the Definition of Done. Remember that Scrum Masters facilitate self-management rather than assigning tasks.

  99. Question 99 of 554Which properties of the Daily Scrum are correct?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Its location and time should remain constant

    The Daily Scrum is a fifteen-minute event for Developers to synchronize activities. To reduce complexity, it should be held at the same time and place every day. Ignore options treating it as a formal status report.

  100. Question 100 of 554Who is accountable for the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Product Owner

    The Product Owner is solely accountable for effective Product Backlog management, including its ordering and availability. While Developers help add detail, the final accountability never shifts away from the Product Owner.

  101. Question 101 of 554When does a new Sprint begin?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Immediately after the end of the previous Sprint.

    A new Sprint begins immediately after the conclusion of the previous Sprint. This continuous cycle ensures no downtime, maintaining the cadence and flow of inspection and adaptation throughout the project.

  102. Question 102 of 554What provides guidance to the Scrum Team on why they are building the Increment?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Sprint Goal

    The Sprint Goal provides guidance to the Scrum Team on why they are building the Increment. It creates coherence and focus, allowing the team flexibility in the exact work performed to achieve that objective.

  103. Question 103 of 554Who is responsible for ensuring that the work done on a Product Backlog Item meets the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Developers.

    Developers are accountable for instilling quality by adhering to the Definition of Done for every Product Backlog Item. Watch out for distractors like the Scrum Team, as accountability for actually doing the work rests with Developers.

  104. Question 104 of 554What might be a valid reason for abnormally cancelling a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. When the Sprint Goal becomes obsolete.

    A Sprint is abnormally cancelled only when the Sprint Goal becomes obsolete. Avoid options about work being too difficult or new features appearing, as the Scrum Team should adapt the backlog instead.

  105. Question 105 of 554What should Developers do with non-functional requirements?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Ensure they are addressed in every Increment.

    Every Increment must meet non-functional requirements to be considered potentially releasable. Avoid options like separate lists or hardening phases, as Scrum demands quality be built in continuously.

  106. Question 106 of 554Who has the authority to cancel the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. The Product Owner

    Only the Product Owner has the authority to cancel a Sprint, usually because the Sprint Goal has become obsolete. A common trap is assuming the Scrum Master shares this authority, but their role is to facilitate the process.

  107. Question 107 of 554Who is responsible for managing Developers' tasks during the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers.

    The Developers are accountable for creating their Sprint plan and adapting it daily toward the Sprint Goal. Because they are self-managing, no one else assigns or manages their tasks during the Sprint, eliminating roles like Scrum Master or Project Manager.

  108. Question 108 of 554Why is it important to have only one Product Owner per product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. It is clear who is accountable for the Product Backlog, the Developers always know who determines priorities, and it helps avoid barriers to effective communication and rapid decision-making

    Having one Product Owner ensures clear accountability for the Product Backlog and priorities. This single source of decision-making prevents conflicting directions, reduces communication barriers, and allows rapid adaptation to changing market needs.

  109. Question 109 of 554Who should be present to review and adjust the selected Sprint work if the Developers determine that they will not be able to finish the complete forecast?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Owner and the Developers.

    The Developers collaborate with the Product Owner to review and adjust Sprint scope. If a forecast cannot be met, scope may be clarified and renegotiated with the Product Owner as more is learned during the Sprint.

  110. Question 110 of 554How much work must Developers of a Scrum Team do to a Product Backlog item they select for a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. As much as they have informed the Product Owner will be done for every Product Backlog item it selects in conformance with the Definition of Done.

    Developers must complete work on a Product Backlog item to meet the Definition of Done. Partially done work is never accepted, ensuring transparency and a potentially releasable Increment every Sprint.

  111. Question 111 of 554Which of the following describes an appropriate Sprint length?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. All of these answers are correct.

    Sprints must be one month or less to keep risk acceptable and synchronize with business events. The correct answer incorporates all these limits, as Scrum relies on a timebox that balances focus and predictability.

  112. Question 112 of 554Could the Product Owner and the Scrum Master also be Developers of the Scrum Team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Yes

    Yes, Scrum does not prohibit individuals from holding multiple roles within a Scrum Team. For the exam, remember that the Product Owner and Scrum Master can also be Developers.

  113. Question 113 of 554When does a Sprint end?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. When the time-box expires.

    A Sprint ends strictly when its fixed time-box expires. Do not choose an option about finishing work early; Sprints are never extended to complete remaining items.

  114. Question 114 of 554How frequently should product releases occur?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Frequently enough to eliminate the risk that the product's value will get out of line with the marketplace

    Releases should happen frequently enough to ensure the product's value stays aligned with the marketplace. Do not select rigid timeframes like every Sprint, as the release cadence is a business decision driven by risk.

  115. Question 115 of 554What are the three most applicable characteristics of the Product Owner?

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Lead Facilitator of Key Stakeholder Involvement · B. Product Marketplace Expert · E. Product Value Maximizer

    The Product Owner is accountable for maximizing product value, understanding the marketplace, and engaging key stakeholders. Avoid confusing these duties with the Scrum Master's responsibilities, such as facilitating Scrum events or evangelizing Scrum across the organization.

  116. Question 116 of 554It is a good practice to have at least two Product Owners on big projects.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The Product Owner is exactly one person, not a committee, regardless of project size. A practical exam cue is to remember that while multiple people can advise, only one person holds the final accountability for Product Backlog ordering and value maximization.

  117. Question 117 of 554How should multiple Scrum Teams, working from the same Product Backlog, select the Product Backlog items they plan to work on?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Owner will present the work and the Developers will select the items they will work on.

    Developers self-manage by selecting their own work from the single Product Backlog during Sprint Planning. A strong exam cue is remembering that the Product Owner orders items but never assigns work to the teams.

  118. Question 118 of 554Who decides the duration of the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Scrum Team

    The Scrum Team decides the Sprint length, balancing risk, complexity, and market dynamics. While the Scrum Master facilitates this discussion, accountability rests with the entire Scrum Team. Once set, the duration remains fixed.

  119. Question 119 of 554What is the essence of Scrum? Select the most appropriate option.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. A small team of people that is highly flexible and adaptive

    The essence of Scrum is a small, highly flexible, and adaptive team solving complex problems. Distractors like the Scrum Guide or specific accountabilities describe the framework or rules, not the fundamental team spirit driving empirical process control.

  120. Question 120 of 554Who determines how to do the work during the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers.

    The Developers determine exactly how to turn selected Product Backlog items into a working Increment. This reflects Scrum’s self-management principle. Watch out for options involving traditional roles like team leads or architects directing the work.

  121. Question 121 of 554How long should the Sprint be?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Not more than 1 month

    A Sprint is a fixed length event of one month or less. This timeboxing creates predictable cycles for inspection and adaptation. Anything longer than one month introduces too much risk regarding complexity and changing requirements.

  122. Question 122 of 554If three distinct Scrum Teams are working on a single product, how many Product Owners should there be?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. One

    A single product must have exactly one Product Owner to maintain a unified vision and a single Product Backlog. For the exam, remember that multiple teams can work on one product, but the product owner role remains singular to ensure clear accountability.

  123. Question 123 of 554Who is allowed to tell the Developers which requirements to work on?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. The Product Owner

    The Product Owner holds the exclusive authority to order Product Backlog items and direct what work maximizes value. While others may offer suggestions, only the Product Owner decides priorities. Use this as a primary cue for questions about backlog management authority.

  124. Question 124 of 554What should Developers do if they realize they have selected too much work after starting the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Work with the Product Owner to remove some work or Sprint Backlog items as soon as possible.

    Developers must collaborate with the Product Owner to negotiate and remove scope, ensuring the Sprint Goal remains achievable. Never choose options that suggest lowering quality standards or expanding the team mid-Sprint. Always maintain focus on the Sprint Goal.

  125. Question 125 of 554The Scrum Team consists of: Select three.

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. The Scrum Master · B. The Developers · D. The Product Owner

    A Scrum Team is a cohesive unit made up of one Scrum Master, one Product Owner, and Developers. Stakeholders are strictly external to the core team. Memorize this exact structure, as the framework emphasizes small teams without sub-teams or hierarchical titles.

  126. Question 126 of 554Who is responsible for monitoring progress towards high-level goals related to the product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Team

    The entire Scrum Team is collectively responsible for monitoring progress toward high-level product goals. Avoid picking individual roles like the Product Owner for this, as the 2020 Scrum Guide emphasizes shared accountability for achieving goals.

  127. Question 127 of 554What is the Increment? (Choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The sum of all the usable Product Backlog items completed during the Sprint. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together.

    An Increment is the sum of all usable Product Backlog items completed during a Sprint, added to prior Increments. The key distractor fails because simply summing completed items misses that the work must be thoroughly verified and integrated.

  128. Question 128 of 554What are the time-boxes for the Daily Scrum and the Sprint Review?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. 15 minutes and 4 hours respectively

    The Daily Scrum is timeboxed to 15 minutes, and the Sprint Review is capped at four hours for a one-month Sprint. A frequent mistake is assuming the Review and Retrospective share the same maximum timebox.

  129. Question 129 of 554As a product expands, should Product Owners consider delegating some of their accountabilities to Product Managers or other individuals knowledgeable about customer interactions and the product market?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. No

    A Product Owner may receive support from others, but they cannot delegate their core accountability for the Product Backlog. A practical exam cue is to remember that accountability remains entirely with the Product Owner, even when others help.

  130. Question 130 of 554Who is accountable for promoting and supporting Scrum? Select the best choice.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Master

    The Scrum Master is accountable for establishing Scrum and promoting its effective use across the organization. A practical exam cue is to remember that while the whole team lives by Scrum values, only the Scrum Master holds this specific leadership accountability.

  131. Question 131 of 554The Developers on the Scrum Team are waiting for a specific software component they need to integrate. The component will be ready in about a month, and the highest-priority Product Backlog Items depend on it. What should the Product Owner do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Ensure the dependency is clearly visible in the Product Backlog and that the Developers have enough independent Items to work on in the next Sprint.

    The Product Owner should make the dependency transparent and ensure Developers have independent items to work on. A practical exam cue is that Scrum discourages special wait lists, and Developers should never sit idle while waiting for dependencies.

  132. Question 132 of 554What Product Owner activities occur between the end of the current Sprint and the beginning of the next Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. There are no such activities. When the current Sprint ends, the new Sprint begins.

    When a Sprint ends, the next Sprint begins immediately, so there is no gap for special activities. A key exam cue is that Product Backlog refinement happens during the Sprint itself, not in a phantom break between Sprints.

  133. Question 133 of 554Who is responsible for all product-related activities?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Team

    The Scrum Team is responsible for all product-related activities, including maintenance, operation, and experimentation. A practical exam cue is that the entire team shares these responsibilities, rather than assigning them to isolated roles or departments.

  134. Question 134 of 554A cross-functional Scrum Team is defined as:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Cross-functional, meaning the members have all the skills necessary to create value each Sprint. They are also self-managing, meaning they internally decide who does what, when, and how.

    A cross-functional Scrum Team possesses all the skills necessary to create value each Sprint and is self-managing. A practical exam cue is that traditional titles and functional managers do not exist within a self-managing Scrum Team.

  135. Question 135 of 554Who is responsible for tracking the total work remaining in the Sprint Backlog to project the likelihood of achieving the Sprint Goal?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Developers

    The Developers are responsible for tracking the total work remaining in the Sprint Backlog to project the likelihood of achieving the Sprint Goal. A practical exam cue is that the Developers own the Sprint Backlog completely.

  136. Question 136 of 554Who participates in the Sprint Planning? (Select three)

    Select 3 answers.

    Show answer & explanation

    Correct answer: C. The Developers · D. The Product Owner · E. The Scrum Master

    The entire Scrum Team, which includes the Developers, the Product Owner, and the Scrum Master, collaborates during Sprint Planning. Outside managers or stakeholders do not participate in this core planning event unless explicitly invited by the team.

  137. Question 137 of 554Kevin is a senior developer who has recently joined an existing Scrum Team. The existing team members cannot get along with Kevin and conclude that he does not fit their culture. If necessary, who is responsible for removing the new team member, and why?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Scrum Team as a whole is responsible as the Scrum Team is self-managed.

    Scrum Teams are self-managing, meaning they internally decide who does what, when, and how. While the Scrum Master removes impediments, resolving team composition and membership issues rests entirely with the Scrum Team itself, not management or the Product Owner.

  138. Question 138 of 554What should Developers do if they don't understand a functional requirement?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Work with the Product Owner to determine what is possible and acceptable.

    Developers collaborate with the Product Owner to clarify functional requirements and determine what is acceptable. The Product Owner is responsible for maximizing value and clearly explaining backlog items so the team can build the right feature.

  139. Question 139 of 554How frequently should the Product Owner communicate and reiterate his product vision to the Scrum Team and the Key Stakeholders?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Early and often

    The Product Owner should communicate and reiterate the product vision early and often. Doing so ensures the Scrum Team and stakeholders maintain shared understanding and alignment, rather than limiting communication to a single event.

  140. Question 140 of 554What are the responsibilities of the Developers of the Scrum Team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Select the Product Backlog items for the Sprint and do the work planned in the Sprint Backlog.

    Developers select items from the Product Backlog during Sprint Planning and do the work to create a usable increment. They do not decide product value or reorder the backlog, as those are Product Owner accountabilities.

  141. Question 141 of 554Who has the vision of the product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Product Owner

    The Product Owner is responsible for managing the Product Backlog to best achieve the overarching product vision. While others may have input, the Product Owner ultimately owns and communicates this strategic direction.

  142. Question 142 of 554Which stakeholder is the most important for the Product Owner to satisfy?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product's users

    The product's users are the most important stakeholders because the primary goal is delivering value to them. While internal stakeholders matter, focusing on user satisfaction ultimately drives the true business value.

  143. Question 143 of 554What does the Cone of Uncertainty show?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. How much is known about the Product over time

    The Cone of Uncertainty illustrates how uncertainty decreases and knowledge increases over time as a product is developed. For the exam, remember that early estimates have high variance, which shrinks as details emerge.

  144. Question 144 of 554During a Sprint Review, the stakeholders notice that the product development progress is not very visible and lacks transparency. Moreover, they don't understand the next steps. Who is responsible for this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Scrum Team

    The Scrum Team shares this accountability because the Sprint Review is a collaborative working session. Avoid blaming the Product Owner; current Scrum emphasizes that the entire team is responsible for stakeholder collaboration.

  145. Question 145 of 554Who are the typical key stakeholders (select the 3 best options)?

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. The human people who actually use the product under development · B. The people responsible for paying to use the product · E. The people responsible for making the funding decisions for the product development effort

    Key stakeholders typically include the end users, the people paying to use the product, and those making funding decisions. Avoid selecting the Scrum Team or marketing, since stakeholders are external to the development team.

  146. Question 146 of 554An important executive wants the Developers to take in a highly critical feature in the current Sprint. The Developers:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Will ask the executive to work with the Product Owner

    The correct answer works because the Product Owner is the sole person accountable for managing the Product Backlog. A practical exam cue is to always route priority changes through the Product Owner. Developers cannot be forced by outsiders to change their Sprint Backlog.

  147. Question 147 of 554Which of the following statements is true? Select all that apply.

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. After the Sprint Planning, a sprint cannot proceed without a Sprint Goal · B. After the Sprint Planning, a sprint can proceed without a complete Sprint Backlog

    A valid Sprint requires a Sprint Goal for focus, but it does not need a fully detailed Sprint Backlog. The Sprint Backlog emerges as the Developers learn. Avoid options demanding complete upfront architecture or specifications, as Scrum embraces emerging requirements.

  148. Question 148 of 554A new Product Owner is hired to work on an existing product that has been ongoing for five Sprints. He/she is unsure about all of the responsibilities of a Product Owner. Which of these Product Owner activities are defined in Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Interacting with stakeholders and ensuring that the most valuable functionality is is always produced first.

    Scrum mandates that the Product Owner interact with stakeholders and optimize value, leaving format choices to the team. Watch out for specific formatting traps like writing User Stories or Use Cases, which are not prescribed formalities in the official Scrum Guide.

  149. Question 149 of 554Which factor(s) should be considered when defining the Sprint length?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The level of expertise over the technology to be used, ability to release an Increment to the end users, and the risk of being disconnected from the stakeholders.

    Sprint length balances risk, technology uncertainty, and stakeholder feedback frequency. Shorter Sprints limit risk by allowing more inspection. Distractors focusing on team size or membership changes miss the core inspection and adaptation rhythm.

  150. Question 150 of 554The Developers should have all the skills and competencies needed to:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Turn the Product Backlog items it selects into a potentially releasable product increment of functionality.

    The Developers must possess all the skills needed to create a potentially releasable Increment each Sprint. Options involving handoffs or fixed estimates contradict empiricism and cross-functionality. Remember that creating a Done Increment is the primary development goal.

  151. Question 151 of 554When is a Product Backlog retired?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. When the Product retires

    A Product Backlog exists as long as the product exists. Because Scrum has no final project sign-offs, the backlog is only retired when the product itself is retired. As long as the product provides value, its backlog continues evolving.

  152. Question 152 of 554Who is responsible for estimating the work effort in the Product Backlog? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Developers

    The Developers performing the work are solely responsible for estimating Product Backlog items. The Product Owner might influence them by clarifying trade-offs, but those doing the actual work create the estimates to ensure accountability.

  153. Question 153 of 554In addition to product requirements, Scrum Teams also impose some technical conditions that the product must meet. These conditions must be added to the:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Definition of Done

    Technical conditions and quality standards that apply universally to the product belong in the Definition of Done. This ensures every Increment meets required quality measures for release. Individual requirements belong in the Product Backlog.

  154. Question 154 of 554What does not happen when a Sprint is cancelled? Select two.

    Select 2 answers.

    Show answer & explanation

    Correct answer: C. Several top Product Backlog Items are taken into the Sprint Backlog to replace the obsolete items · E. At the Sprint Retrospective the Scrum Master determines who from the Developers are responsible for cancelling the Sprint

    When a Sprint is cancelled, completed work is reviewed and incomplete items return to the Product Backlog. The team does not swap in new items, and no one is blamed during the Retrospective. Use process of elimination on negative questions to find the false statements.

  155. Question 155 of 554Who works on building an increment without Technical Debt?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Developers

    Developers are specifically accountable for creating a usable increment and managing technical quality. They must negotiate a robust Definition of Done to prevent accumulating defects. On the exam, always associate hands-on creation and quality control directly with the developers.

  156. Question 156 of 554How does the Product Owner communicate marketplace knowledge to the Scrum Team? Select three.

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Sprint Reviews · B. Product Backlog Refinement · C. Informal daily interactions

    The Product Owner shares market insights through backlog refinement, Sprint Reviews, and ongoing daily interactions. Remember that Daily Scrums are exclusively for Developers, so exclude that option. Prioritize continuous collaboration over formal events for communicating market knowledge.

  157. Question 157 of 554Scrum's artifacts are designed to maximize the Developers' velocity.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Scrum artifacts exist to maximize transparency of key work information, not to optimize speed or velocity. Increased transparency enables effective inspection and adaptation. When you see velocity mentioned in relation to artifacts on the exam, assume it is a distractor.

  158. Question 158 of 554A key concern when multiple Scrum Teams are working for the same Product Backlog is minimizing dependencies between teams.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    Minimizing cross-team dependencies reduces complexity and boosts agility when multiple teams share a Product Backlog. Remember that while dependencies cannot always be eliminated completely, the goal during refinement is to make them transparent and minimize them.

  159. Question 159 of 554How can the Product Owner bring his Product vision to life? (choose the best three answers)

    Select 3 answers.

    Show answer & explanation

    Correct answer: B. Articulating the product vision to the Scrum Team and the Key Stakeholders early and often. · D. Via the Product Backlog and iterating towards that vision every Sprint. · E. Utilizing the underlying empirical product planning features of Scrum.

    The Product Owner brings the vision to life by articulating it often, using empirical planning, and iterating via the Product Backlog. Avoid options that involve management approval or delegating communication to the Scrum Master.

  160. Question 160 of 554Within just a few Sprints, Scrum increases the transparency of the following:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Both

    Scrum quickly increases transparency around both real progress and the team's technical ability to create Increments. Remember that Scrum ruthlessly exposes reality, making both project status and technical constraints visible.

  161. Question 161 of 554How long does the Product Backlog exist?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. As long as the Product exists

    The Product Backlog exists as long as the product itself exists, continuously evolving to remain competitive. Do not assume the backlog disappears when a team disbands or a specific release is shipped.

  162. Question 162 of 554What activities should a Product Owner do during an active Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Engage with the stakeholders and answer questions from the Developers.

    During an active Sprint, a Product Owner engages with stakeholders and answers questions from the Developers to clarify requirements. A practical exam cue is that Product Owners never prioritize the Sprint Backlog, as only the Developers manage the Sprint Backlog.

  163. Question 163 of 554What must the Developers do during the first Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Create a potentially shippable product Increment that includes at least one piece of functionality.

    During the first Sprint, Developers must create a potentially shippable product Increment that includes at least one piece of functionality. A practical exam cue is that every Sprint without exception must result in a usable Increment.

  164. Question 164 of 554Developers are self-managed and empowered. They are also the authority in deciding which business needs are required to be developed.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The Product Owner is the sole authority responsible for managing and ordering the Product Backlog to maximize value. Developers decide how to build the work, but they never dictate which business needs or features take priority.

  165. Question 165 of 554Who is responsible for ensuring the Product Backlog items are understood to the needed level?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner.

    The Product Owner is accountable for ensuring that Product Backlog items are transparent and understood to the level needed by the Developers. The Product Owner may do this directly or delegate the actual writing, but they remain accountable for the clarity.

  166. Question 166 of 554The Product Owner should be expertly aware of the marketplace for the product.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. True

    The Product Owner is accountable for maximizing the value of the product resulting from the Developers' work. To make effective ordering decisions, the Product Owner must deeply understand the marketplace, competition, and evolving customer needs.

  167. Question 167 of 554Which of these tools is mandatory for the Product Owner to use?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. None of the answers is correct.

    The Scrum framework does not mandate any specific project management tools, charts, or software for the Product Owner. The Product Owner may use whatever techniques and tools they find most effective for managing the Product Backlog.

  168. Question 168 of 554Who must adhere to the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Developers

    The Developers conform to the Definition of Done to ensure every increment meets quality standards. However, the entire Scrum Team is accountable for creating a clear definition, which can make strictly choosing only Developers slightly ambiguous contextually.

  169. Question 169 of 554Your organization is new to Scrum. Management would like to understand what metrics are useful in determining if value is being delivered. As a Product Owner, which two metrics would be appropriate? (choose the two best answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: D. Customer satisfaction · E. Time-to-Market

    Customer satisfaction and time-to-market directly measure value delivery, unlike internal metrics like velocity. For the exam, associate value with external user outcomes and business viability rather than internal team output.

  170. Question 170 of 554When more Scrum Teams are added to a project that works on one single product, the productivity of the original Scrum Teams is more likely to increase.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    False. Adding multiple teams to a single product initially increases complexity and communication overhead, which often decreases productivity. Watch out for assuming that more teams immediately equals more output.

  171. Question 171 of 554The product development project is to deliver internal functionality for an organization. The Scrum Team has a good mix of skills and has worked on similar projects. The duration of the Sprint can be:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. up to one month

    A Sprint can be up to one month long, regardless of whether the project is internal or external. The length is fixed and decided in advance to establish a consistent cadence for the Scrum Team.

  172. Question 172 of 554Who is not accountable for changes in the Product Backlog? (Select all that apply)

    Select 4 answers.

    Show answer & explanation

    Correct answer: A. The Key Stakeholders · B. The Scrum Master · D. The Developers · E. The CEO

    Only the Product Owner is accountable for changing the Product Backlog. However, a Developer or CEO can suggest changes. Because suggest and change are often conflated, this question is slightly ambiguous, so be careful to distinguish final accountability from mere input.

  173. Question 173 of 554What does the word 'development' mean in the context of Scrum? Select the best option.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Complex work that can include all the suggested options and even more

    In Scrum, development refers to any complex work required to create a product. This intentionally broad definition includes research, software, hardware, and sustaining operations. For the exam, always choose the most inclusive option when defining development work.

  174. Question 174 of 554The Definition of Done is:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Initially defined per product by the Scrum Team, but may change throughout the product development duration

    The Definition of Done is created by the Scrum Team and evolves over time as the environment changes. It is not deferred until after the first Sprint. If organizational standards exist, the team’s Definition of Done must minimally reflect them.

  175. Question 175 of 554The success of a product is mainly measured by customer satisfaction. Customer satisfaction should be measured:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Frequently

    Customer satisfaction should be measured frequently to ensure the team is building the right thing at the right time. Be careful not to choose rigid schedules like quarterly or daily, as empirical inspection happens continuously.

  176. Question 176 of 554In the Sprint Retrospective, the Scrum Master participates as a:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Peer Team Member

    The Scrum Master participates in the Sprint Retrospective as a peer team member to help inspect and adapt the process. A strong exam cue is that the Scrum Master is never a silent observer or an auditor within Scrum events.

  177. Question 177 of 554As the Scrum Team is in the process of defining Product Backlog items, the Scrum Master notices that the team is not using the User Story format to capture the Product Backlog items. The Scrum Master should:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. let the team decides the format of the Product Backlog items

    Scrum Teams are self-managing and decide their own format for Product Backlog items. User stories are a popular technique but are completely optional, so the Scrum Master should simply let the team choose their preferred format.

  178. Question 178 of 554A Product Owner is not available for Scrum events and is not supportive enough for Developers. The next immediate accountability lies with:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Scrum Master, who needs to educate the Product Owner on his role

    The Scrum Master is accountable for coaching the Product Owner and helping everyone understand and enact their responsibilities. If a Product Owner is unavailable, the Scrum Master steps in to resolve this impediment.

  179. Question 179 of 554An organization decides to have very small Scrum Teams of fewer than three persons. The likely result could be:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. All the answers are correct

    Scrum Teams must be small enough to remain nimble but large enough to complete significant work. Teams with fewer than three members often lack the necessary skill diversity, experience lower productivity, and suffer from decreased interaction, making all listed outcomes likely. Watch for this specific size rule.

  180. Question 180 of 554In the middle of a Sprint, a team member was required by another department manager to support an important task outside the Sprint work. What is recommended for the team member to do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The team member should inform the other Scrum Team members so the whole Scrum Team can decide what to do with the inquiry

    The team member should immediately bring the conflict to the entire Scrum Team so they can navigate the impediment together. Avoid picking distractors where individuals act alone or blindly follow outside management, because Scrum teams manage their own work.

  181. Question 181 of 554A Scrum Team crafts the following Sprint Goal: "All the Sprint code should have passed 100% automated unit tests". It is incorrect, since Product Owner formulates the goal and not the Scrum Team.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Not an appropriate goal, since Sprint Goal should be about expected business value

    A Sprint Goal should focus on delivering expected business value rather than just meeting technical metrics. For the exam, remember that while code quality matters, goals must guide the team toward a coherent product objective.

  182. Question 182 of 554Which of the following can the Product Owner delegate to others, while remaining accountable for the work? (Select 2 answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: C. Developing and communicating the Product Goal. · D. Ordering the Product Backlog.

    A Product Owner can delegate actual work like ordering the Product Backlog or communicating the Product Goal to others. However, the Product Owner remains strictly accountable for these outcomes and cannot delegate their overall accountability.

  183. Question 183 of 554Select the five Scrum Values.

    Select 5 answers.

    Show answer & explanation

    Correct answer: A. Courage · B. Focus · C. Commitment · D. Openness · F. Respect

    The five Scrum Values are commitment, focus, openness, respect, and courage. Remember that effectiveness, self-organization, and agility are core principles but are not official values.

  184. Question 184 of 554What are the two best responses when a project manager working with your Scrum Team raises concerns about progress and money spent?

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. Share the Earned Value Analysis (EVA) report. · B. Engage in a discussion with the project manager, sharing the current impediments and forecasting for the Sprint.

    The best responses focus on transparency and collaboration. Sharing the Product Backlog provides project visibility, while discussing current impediments and Sprint forecasts addresses immediate concerns. Avoid traditional metrics like earned value analysis, which conflict with empiricism.

  185. Question 185 of 554The Scrum Master serves the organization in several ways, including:

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Planning and advising Scrum implementations within the organization · D. Leading, training, and coaching the organization in its Scrum adoption · E. Removing barriers between stakeholders and Scrum Teams

    Serving the organization involves leading its Scrum adoption, planning implementations, and removing stakeaker barriers. Options about managing the Product Backlog or defining the Product Goal belong exclusively to the Product Owner.

  186. Question 186 of 554How does the Scrum Master serve the Scrum Team? Select the three most appropriate answers.

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Ensuring that all Scrum events take place and are positive, productive, and kept within the timebox · C. Helping the Scrum Team focus on creating high-value Increments that meet the Definition of Done · E. Coaching the team members in self-management and cross-functionality

    The Scrum Master serves the team by ensuring events are productive and timeboxed, helping focus on high-value increments, and coaching self-management. Remember that finding techniques for Product Backlog management is how the Scrum Master serves the Product Owner, not the entire Scrum Team.

  187. Question 187 of 554What is the maximum length of the Sprint Planning in a project with three-week Sprints?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. 8 hours

    Sprint Planning has an absolute maximum timebox of eight hours regardless of the Sprint length. For shorter Sprints, the event is usually shorter, but the official maximum cap does not scale down proportionally with a three-week duration.

  188. Question 188 of 554The Developers are always accountable for:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Adapting their plan each day toward the Sprint Goal

    Developers are accountable for adapting their daily plan toward the Sprint Goal. The Product Owner manages the Product Backlog and communicates the Product Goal, while the Scrum Master ensures the events themselves take place and remain productive.

  189. Question 189 of 554What is the result of the Sprint Review?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. A revised Product Backlog that defines the probable Product Backlog items for the next Sprint

    The Sprint Review yields a revised Product Backlog defining probable items for the next Sprint. Do not confuse this with the Retrospective, which outputs actionable improvements, or Sprint Planning, which produces the Sprint Goal and Sprint Backlog.

  190. Question 190 of 554Who defines the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Scrum Team

    If the organization does not provide one, the Scrum Team must create a Definition of Done appropriate for the product. Watch out for Developers, because while they must conform to it, the entire team owns its creation.

  191. Question 191 of 554What happens during the Sprint? Select three answers.

    Select 3 answers.

    Show answer & explanation

    Correct answer: B. No changes are made that would endanger the Sprint Goal · C. Quality goals do not decrease · E. Scope may be clarified and renegotiated with the Product Owner as more is learned

    During a Sprint, quality goals remain constant while scope can be clarified as teams learn more. Avoid options claiming the Sprint Goal changes frequently or scope is permanently locked, as those violate empirical process rules.

  192. Question 192 of 554What are the three pillars that uphold Scrum?

    Select 3 answers.

    Show answer & explanation

    Correct answer: B. Transparency · E. Adaptation · F. Inspection

    Scrum is founded on the empirical pillars of transparency, inspection, and adaptation. The other choices, like cross-functionality and agility, are valuable traits but are not the required pillars.

  193. Question 193 of 554The Scrum Team consists of:

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. The Developers · C. The Scrum Master · D. The Product Owner

    The Scrum Team consists of one Product Owner, the Developers, and a Scrum Master. Stakeholders are vital for providing input during the Sprint Review, but they remain outside the actual Scrum Team structure because they do not hold core accountabilities.

  194. Question 194 of 554How is the Product Backlog ordered?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. Whatever seems the best to the Product Owner.

    The Product Owner is accountable for the Product Backlog and may order it using whatever method seems best to maximize value. Story points, risk levels, or functional categories might be considered, but the final ordering strictly remains the Product Owner's call.

  195. Question 195 of 554Who assigns tasks to the Developers?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Developers themselves

    Developers are self-managing, meaning they decide among themselves how to turn Product Backlog items into a Done Increment. Scrum explicitly removes the project manager role, so no external authority is allowed to assign daily tasks to the Developers.

  196. Question 196 of 554Scrum is best described as a:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Framework for developing and sustaining complex products

    Scrum is a framework for developing and sustaining complex products. A practical exam cue is to avoid choosing options that narrowly label Scrum as a software methodology or a rigid process.

  197. Question 197 of 554Which of the following is a valid service from the Scrum Master to the Product Owner?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Helping the Product Owner find techniques for managing the Product Backlog.

    The Scrum Master serves the Product Owner by helping find techniques for effective Product Backlog management. Avoid options where the Scrum Master orders the backlog or acts as a proxy or middleman, which violates Scrum accountabilities.

  198. Question 198 of 554In which event are key stakeholders allowed to participate?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Sprint Review

    Key stakeholders participate in the Sprint Review to inspect the Increment and collaborate on future adaptations. For other events, remember the core Scrum Team generally attends privately to maintain focus.

  199. Question 199 of 554What is the purpose of the Sprint Retrospective? (Choose three)

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Inspect how the last Sprint went with regards to people, relationships, process, and tools · B. Identify and order the major items that went well and potential improvements · C. Create a plan for implementing improvements to the way the Scrum Team does its work

    The Retrospective inspects the past Sprint, identifies improvements, and creates an action plan. Avoid options involving stakeholders or outside specialists, because this event is strictly for internal Scrum Team reflection.

  200. Question 200 of 554Product Backlog Refinement… Select the two most applicable sentence endings.

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. Is the act of adding detail, estimates, and order to Product Backlog items · E. Is an ongoing process

    Product Backlog refinement is an ongoing activity where the team adds detail, estimates, and order to upcoming items. Avoid options that assign rigid frequencies or timeboxes to refinement, as Scrum intentionally leaves the duration and frequency open to the team's needs.

  201. Question 201 of 554As a Product Owner, which of the following would be a valid focus? (choose the two best answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. Ensuring the project and release status is transparent to customers and stakeholders. · B. Frequently work with customers and stakeholders in identifying potential work that could deliver the most value.

    A Product Owner focuses on stakeholder collaboration to identify valuable work and ensuring project status remains highly transparent. Avoid options enforcing mandatory formats like User Stories, as Scrum explicitly allows any format for Product Backlog items.

  202. Question 202 of 554What are the desired benefits of a Product Owner having a clear Product Vision? (choose the best three answers)

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. A Product vision provides the Sprint Review a way of inspecting the incremental progress. · D. A Product vision provides an overarching direction so that Sprints deliver high added-value. · E. It helps the Scrum Team stay focused and provides them something to check their decisions against.

    A clear Product Vision provides overarching direction for high-value Sprints, offers a checkpoint for incremental progress, and helps the team stay focused. It does not dictate exact remaining work, as the vision represents the strategic goal rather than a fixed tactical checklist.

  203. Question 203 of 554How can an organization know the results of a product under development? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. By releasing often, and updating KPIs (key performance indicators) on value after every release and feeding this information back into work on the Product Backlog.

    Frequent releases allow empirical inspection of value, letting the organization update performance indicators and adapt the Product Backlog accordingly. Be wary of distractors relying on velocity, as velocity only measures output and does not validate actual customer value.

  204. Question 204 of 554Which is not a Product Backlog management activity?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Using formal change control to manage Product Backlog when market provides feedback from Product usage

    Formal change control directly opposes Agile and Scrum principles. For the exam, remember that the Product Owner manages the backlog dynamically without bureaucratic gates. Effective backlog management relies on transparency and ordering, not rigid approval processes.

  205. Question 205 of 554How does the Scrum Master help the Product Owner? Select the three most appropriate answers.

    Select 3 answers.

    Show answer & explanation

    Correct answer: C. Helping the Scrum Team understand the need for clear and concise Product Backlog items · D. Helping find techniques for effective Product Goal definition and Product Backlog management · E. Facilitating stakeholder collaboration as requested or needed

    The Scrum Master serves the Product Owner by facilitating stakeholder collaboration and finding effective backlog management techniques. Avoid options suggesting the Scrum Master introduces technical development practices, as this belongs to the Developers.

  206. Question 206 of 554Who is responsible for addressing a lack of transparency in Scrum artifacts?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Team

    The entire Scrum Team shares the responsibility to address any lack of transparency in Scrum artifacts. The Scrum Master is specifically accountable for detecting issues, but fixing them requires the collaborative effort of the whole team.

  207. Question 207 of 554In which event must the Key Stakeholders participate?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Sprint Review

    Key Stakeholders are invited to participate in the Sprint Review to inspect the Increment and collaborate on what to do next. They are not required to attend other formal events like Sprint Planning or the Daily Scrum.

  208. Question 208 of 554How does the Scrum Master serve the organization? Select the three most appropriate answers.

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Working with other Scrum Masters to increase the effectiveness of the application of Scrum in the organization · B. Leading and coaching the organization in its Scrum adoption · D. Planning Scrum implementations within the organization

    The Scrum Master serves the organization by leading Scrum adoption, planning implementations, and collaborating with other Scrum Masters. Avoid options involving arbitrary team mixing or micromanaging stakeholder invitations, as these violate empiricism.

  209. Question 209 of 554What is a key inspect and adapt meeting for the Developers?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Daily Scrum

    The Daily Scrum is the key inspect and adapt event specifically for the Developers. It focuses on progress toward the Sprint Goal and adapting the plan for the next twenty-four hours. Watch out for non-Scrum meetings like project status sessions acting as distractors.

  210. Question 210 of 554The Sprint Backlog is owned by the:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Developers.

    The Developers own the Sprint Backlog because they are solely responsible for creating the actionable plan and doing the work. Remember that while the Product Owner suggests the goal, the Developers decide how much work to take on.

  211. Question 211 of 554Within the Scrum Team, who is most likely to identify the Key Stakeholders for the Product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Product Owner

    The Product Owner is the best person to identify stakeholders because they are accountable for maximizing product value and managing the Product Backlog. They actively engage with stakeholders to understand their needs and gather valuable input.

  212. Question 212 of 554The Increment is the sum of all the Product Backlog items completed only during the current Sprint.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    This statement is false because an Increment includes the sum of all prior completed work plus the new items. Exam cue: always think of the Increment as cumulative value that grows each Sprint, never as a standalone batch of work.

  213. Question 213 of 554Which two statements describe the Definition of Done? (choose 2 answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. Increases transparency · C. Helps ensure the Increment is releasable

    The Definition of Done creates transparency and ensures the Increment is releasable by setting a shared quality standard. Options like increasing velocity or ensuring documentation are classic traps because Scrum strictly avoids equating velocity with value.

  214. Question 214 of 554Who has the "final say" on the order of the Product Backlog Items?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner

    The Product Owner has the final say on Product Backlog ordering to maximize value. Remember that while the Developers provide effort estimates, the Product Owner alone decides what ranks highest and gets prioritized.

  215. Question 215 of 554A product is a vehicle for delivering value. It has no boundaries, no known stakeholders and no defined users or customers.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    A product actually has clear boundaries, known stakeholders, and defined users or customers. If a statement describes a product as having no boundaries or users, you should immediately recognize it as false.

  216. Question 216 of 554What are the best ways for a Product Owner to manage value for the Product? (choose the best two answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: C. Frequently releasing increments to validate assumptions built into the product. · D. Ordering of the Product Backlog.

    A Product Owner manages value primarily through the strategic ordering of the Product Backlog and by frequently releasing increments to validate assumptions. Avoid value points or cost ratios, because empirical validation and ordering are key.

  217. Question 217 of 554When is ownership of individual items in the Sprint Backlog assigned to Developers?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Never. Even if individuals work on specific Sprint Backlog items, the Developers as a whole remains accountable for the Sprint Backlog in its entirety.

    Ownership is never assigned to individual Developers; the entire group of Developers remains accountable for the Sprint Backlog. Watch for options mentioning the Scrum Master assigning work, because self-management prevents this.

  218. Question 218 of 554At the Sprint Retrospective meeting the Scrum Team identified some improvements related to the product that can be done. What may the Scrum Team do? Select the best option.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Add the improvements to the Sprint Backlog for the next Sprint.

    The most impactful improvements identified during a Sprint Retrospective are often added directly to the Sprint Backlog for the next Sprint. Assigning individual owners contradicts Scrum's emphasis on shared team accountability and self-management.

  219. Question 219 of 554What is the commitment for the Sprint Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Sprint Goal.

    The Sprint Goal serves as the specific commitment for the Sprint Backlog. It provides focus and flexibility, allowing the Developers to negotiate scope if needed. Remember the three commitments map to specific artifacts: Product Goal, Sprint Goal, and Definition of Done.

  220. Question 220 of 554Who is allowed to participate in the Daily Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Developers

    The Daily Scrum is an internal meeting exclusively for the Developers to inspect progress toward the Sprint Goal. Be very careful here, the Scrum Master or Product Owner may attend as observers, but only the Developers actively participate.

  221. Question 221 of 554If it is not an organizational standard, who is responsible for creation of the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Team

    If there is no existing organizational standard, the entire Scrum Team is responsible for creating a Definition of Done appropriate for the product. Do not fall for the common distractor that assigns this accountability solely to the Developers.

  222. Question 222 of 554Why do the Developers need a Sprint Goal?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Developers are more focused with a common and specific goal

    A Sprint Goal provides the Developers with a shared, specific focus and purpose, guiding them on why they are building the Increment. It does not guarantee that every single selected Product Backlog item will be fully implemented.

  223. Question 223 of 554What technique should be used for representing Product Backlog Items?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Any technique, even a mix of several techniques

    Scrum is highly flexible, meaning any technique or even a mix of techniques can be used to represent Product Backlog items. Do not fall for distractors like User Stories, because Scrum does not prescribe a specific format.

  224. Question 224 of 554When something about Scrum frustrates the Product Owner, he can delegate some accountabilities to the Scrum Master.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    A Product Owner may delegate specific tasks, but they remain completely accountable for the outcome. Remember the exam rule: accountabilities cannot be transferred or shared, even if others assist.

  225. Question 225 of 554What are the prerequisites for starting a Sprint Planning? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. There are no such prerequisites.

    A new Sprint starts immediately following the conclusion of the previous one without formal prerequisites. Ignore distractors about fully refined backlogs or steering committee approvals, as Scrum operates continuously without enforced readiness gates.

  226. Question 226 of 554Who can change the Sprint Backlog in the middle of the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Only the Developers

    Only the Developers own and modify the Sprint Backlog during a Sprint to reflect emerging work. While the Product Owner negotiates scope, they do not directly update the Sprint Backlog.

  227. Question 227 of 554The Product Owner wants to apply some non-functional requirements to the Product. What is the best way to proceed?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Add the non-functional requirements to the DoD and check every Increment against these criteria

    Adding recurring non-functional requirements to the Definition of Done ensures every Increment meets essential quality standards. Placing them as separate backlog items is sometimes valid, but the Definition of Done is typically preferred.

  228. Question 228 of 554All increments to be created by Developers must come from the Product Backlog.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    All work performed by Developers must originate from the Product Backlog. This single source of truth ensures the Scrum Team consistently maximizes value and aligns with business goals.

  229. Question 229 of 554Who participates in the Sprint Review? Select all applicable variants.

    Select 4 answers.

    Show answer & explanation

    Correct answer: A. The Scrum Master · B. The Developers · C. The Product Owner · E. The Key Stakeholders

    The Sprint Review includes the entire Scrum Team and key stakeholders to inspect the outcome of the Sprint and figure out what to do next. Remember that the CEO can technically attend as a stakeholder, but option E is the definitive answer for outside attendees.

  230. Question 230 of 554What are the areas of focus that can help a Product Owner ensure that the product delivers value? (choose the three best answers)

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. How much of the functionality of his product is being utilized. · B. Direct customer feedback. · E. How much can the customer absorb and use the product.

    Product Owners measure value by looking at direct customer feedback, feature utilization, and how much customers can actually absorb. Avoid distractors focused on output metrics like story points or matching original requirements, because Agile prioritizes adapting to deliver outcome value.

  231. Question 231 of 554What is the impact of technical debt on the Product Owner? (choose the two best answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. More time and money is spent maintaining the product when you have technical debt. · D. Technical debt can reduce the velocity in which new functionality can be created.

    Technical debt directly impacts the Product Owner because it drains time and money on maintenance, while simultaneously slowing down the creation of new features. Never assume technical debt is solely a Developer issue, as it ultimately destroys the product's potential value.

  232. Question 232 of 554If multiple stakeholders have varied interests in the product and different viewpoints, what is the best strategy for the Product Owner?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Do an intelligent balancing of interests and try to maximize the value of the Product as a whole

    The Product Owner must balance varied stakeholder interests to maximize the overall product value. Avoid options that prioritize only funding or speed, because the Product Owner optimizes value rather than pleasing a single group.

  233. Question 233 of 554An organization that has just adopted Scrum wants to know how the interactions between the Product Owner and the Developers should take place. Which two statements best describe this relationship?

    Select 2 answers.

    Show answer & explanation

    Correct answer: D. They collaborate frequently in order for the Developers to deliver Increments that address user and stakeholder needs. · E. They collaborate frequently in order for the Product Owner to make sound decisions in managing the Product Backlog.

    The Product Owner and Developers collaborate frequently so the Developers deliver valuable Increments and the Product Owner makes sound backlog decisions. Avoid options where the Product Owner micromanages work or limits interaction to event boundaries.

  234. Question 234 of 554The structure of the Daily Scrum is well-defined and constant. Every Developer should answer the three main questions.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. False

    This statement is false because the Developers choose the Daily Scrum structure. The three standard questions are an option, but remember the event only mandates focus on progress toward the Sprint Goal.

  235. Question 235 of 554What should a Product Owner take into consideration when ordering the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. What is most appropriate to achieve the objectives of the product and optimise the value delivered to users while taking into account the dependencies.

    The Product Owner orders items to achieve product objectives and optimize value while managing dependencies. Exam cue: reject absolute words like always, because ROI alone ignores context and sequencing.

  236. Question 236 of 554Select all that apply. The Scrum Team participates in:

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Sprint Retrospective · C. Sprint Planning · D. Sprint Review

    The entire Scrum Team participates in Sprint Planning, the Sprint Review, and the Sprint Retrospective. The Daily Scrum is excluded because only Developers participate to inspect and adapt their progress.

  237. Question 237 of 554Which statement regarding the Product Backlog is FALSE?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. It is a finalized list of requirements to be done for the Product.

    The Product Backlog is never finalized; it is a dynamic, living artifact that constantly evolves as the product and market change. The strongest distractor calls it an inventory of work, which is acceptable because it technically lists all desired features and requirements.

  238. Question 238 of 554What are the time-boxes for the Sprint Review and the Sprint Retrospective?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. 4 and 3 hours respectively

    For a one-month Sprint, the Sprint Review is capped at four hours, and the Retrospective is capped at three hours. A helpful exam cue is to remember that reviewing with stakeholders takes longer than internal team reflection.

  239. Question 239 of 554Who should do the legwork of gathering the marketplace data for the Product Owner?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. It does not matter who does the legwork

    Scrum does not dictate who gathers marketplace data, meaning anyone can assist with this legwork. The critical point for the exam is that the Product Owner remains accountable for the final decision and product value.

  240. Question 240 of 554If only the work scheduled for the Sprint's first few days is decomposed to units of one day or fewer, might the Sprint Planning be completed?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Yes, if the remaining work is also estimated, maybe in bigger units

    Sprint Planning can be completed if only the near-term work is finely decomposed, as long as the Developers understand the remaining scope. Detailed decomposition of the entire Sprint backlog is not required during planning.

  241. Question 241 of 554At the end of Sprint Planning, the Developers could not decompose all of the work into units of one day or less. They could decompose the work for only the first few days of the Sprint. Since the team is self-organized, they should continue Sprint Planning in the following days before they start the work.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers should close the Sprint Planning and start the work

    Sprint Planning is strictly time-boxed, so the Developers must close the event and start working on the decomposed items. Exam cue: you do not need the entire Sprint planned day-by-day upfront, as the Sprint Backlog emerges during the Sprint.

  242. Question 242 of 554Who monitors the remaining work of the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Product Owner

    The Product Owner tracks total product progress by monitoring the remaining work in the Product Backlog. A strong distractor is the Developers, but they only track work remaining inside the current Sprint Backlog, not the overall Product Backlog.

  243. Question 243 of 554What are the Scrum Artifacts? Select all applicable answers.

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Increment · C. Sprint Backlog · D. Product Backlog

    The three official artifacts in Scrum are the Product Backlog, the Sprint Backlog, and the Increment. Be careful not to select the Sprint Goal here, as it functions as a crucial commitment attached to the Sprint Backlog.

  244. Question 244 of 554What are Product Backlog characteristics? (choose the best three answers)

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. As long as a product exists, its Product Backlog also exists · D. It is dynamic · E. It is never complete

    A Product Backlog is dynamic and never complete as long as the product exists. Remember that Scrum events or artifacts do not get closed or dismissed; they continuously evolve to maximize value.

  245. Question 245 of 554What measures can help determine the success of the product? (choose the best three answers)

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. The product's impact on customer satisfaction. · B. The product's impact on cost. · D. The product's impact on revenue.

    Product success is measured by its impact on customer satisfaction, cost, and revenue. Avoid metrics like velocity, which only measures team speed, or delivered scope, which does not guarantee actual value.

  246. Question 246 of 554What is the duration of the Daily Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. 15 minutes

    The Daily Scrum is strictly timeboxed at 15 minutes to inspect progress toward the Sprint Goal. Ignore options mentioning the three questions, because the 2020 guide removed those as mandatory requirements.

  247. Question 247 of 554In the Scrum context, the word "development" only refers to software.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    In Scrum, the terms develop and development refer to any complex product work, not just software. This broad definition ensures the framework applies to hardware, marketing, or any complex domain. Never limit Scrum concepts to software development.

  248. Question 248 of 554If 6 Scrum Teams work on the same product, how many Product Owners are needed?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. One Product Owner

    A product has exactly one Product Owner, regardless of how many Scrum Teams work on it. The Product Owner is one person, not a committee, ensuring a clear and unified product vision. Multiple teams may share this single Product Owner.

  249. Question 249 of 554What should be taken into account for the Definition of Done? Select the two most appropriate items.

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. The Definition of Done of other Scrum Teams working on the same Product · C. Conventions, standards and guidelines of the Organization

    The Definition of Done must account for organizational standards and guidelines, as well as the definitions used by other teams working on the same product. If multiple teams share a product, they must mutually create and follow a unified Definition of Done.

  250. Question 250 of 554What type of process control is Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Empirical

    Scrum is founded on empirical process control theory. This means decisions are made based on observation, experience, and experimentation. Empiricism relies on the three pillars of transparency, inspection, and adaptation to manage complex work effectively.

  251. Question 251 of 554Successful use of Scrum depends on people becoming more proficient in living five values including: Select two.

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. Commitment · E. Respect

    Commitment and Respect are two of the five official Scrum values. The complete list includes Focus, Openness, and Courage. Hierarchy, velocity, and multitasking are management concepts or metrics that are not part of the core Scrum values.

  252. Question 252 of 554What action should a Scrum Master take if the Developers have decided that Retrospectives are no longer necessary?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Start facilitating more productive and useful Retrospectives.

    The Scrum Master must ensure all Scrum events occur and remain productive, meaning they should coach the team to hold useful Retrospectives. Canceling mandatory events or extending the timebox violates Scrum rules and removes critical inspection opportunities.

  253. Question 253 of 554Who is responsible for collaborating with the stakeholders?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Team

    The entire Scrum Team shares responsibility for collaborating with stakeholders to align the product with user needs. However, this is somewhat ambiguous because the Product Owner also has a primary duty to engage stakeholders for managing the Product Backlog.

  254. Question 254 of 554How long should the Sprint Planning be?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Not more than 8 hours

    Sprint Planning is timeboxed to a maximum of eight hours for a standard one-month Sprint, usually proportionally shorter for shorter Sprints. Avoid the trap of thinking planning continues until every single task is fully decomposed.

  255. Question 255 of 554What is the impact of a changing environment on the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Backlog is a living artifact that evolves as the product and the environment in which it will be used evolves.

    The Product Backlog is a living artifact that constantly evolves as the product, environment, and stakeholder needs change over time. It is never static or locked in, because Scrum embraces changing requirements to maximize value.

  256. Question 256 of 554The Scrum Master does the following regarding the Daily Scrum (select all that apply):

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. If others are present at the Daily Scrum, ensures that they do not disrupt the meeting · B. Ensures that the Developers have the meeting · C. Teaches the Developers to keep the Daily Scrum within the 15-minute time-box

    The Scrum Master ensures the Developers hold the event, teaches them to respect the timebox, and prevents disruptions from others. Remember that the Scrum Master is never responsible for running the Daily Scrum, as it belongs strictly to the Developers.

  257. Question 257 of 554For the first Sprint, the inputs are the Product Backlog and the Projected Capacity of the Developers. What are the additional inputs to the subsequent Sprints?

    Select 2 answers.

    Show answer & explanation

    Correct answer: C. Past performance of the Developers · D. Latest Product Increment

    For subsequent Sprints, Sprint Planning also considers the past performance of the Developers and the latest product Increment. This is because prior velocity and the current state of the product help guide realistic planning.

  258. Question 258 of 554What does Product Backlog management include? Select the three most applicable answers.

    Select 3 answers.

    Show answer & explanation

    Correct answer: B. Optimizing the value of the work the Developers perform · C. Ordering the items in the Product Backlog to best achieve goals and missions · D. Ensuring that the Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next

    The selected answers are correct because Product Backlog management includes optimizing value, ordering items, and ensuring transparency. A key exam cue is that Developers pull items into the Sprint Backlog themselves during Sprint Planning, so moving items is not a Product Backlog management activity.

  259. Question 259 of 554Who must present the new increment to the stakeholders during the Sprint Review? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Team

    The entire Scrum Team collaborates with stakeholders during the Sprint Review to inspect the increment. Do not pick the Product Owner or Developers alone, because inspecting the outcome is a shared team responsibility.

  260. Question 260 of 554The Scrum Master should not allow the Product Owner to attend Sprint Planning if the Product Owner is not ready with a Sprint Goal. Is this true or false?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    This is false because the Product Owner must attend Sprint Planning to collaborate on creating the Sprint Goal. Remember that Scrum events rely on teamwork rather than exclusion based on readiness.

  261. Question 261 of 554What are the true statements? (choose the best two answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. Only the Developers should be responsible for estimating the Product Backlog Items · D. Only the Product Owner can cancel the Sprint. Others can only influence the decision to cancel

    Only Developers are responsible for sizing or estimating Product Backlog items, and only the Product Owner can cancel a Sprint. Remember that a Product Owner can delegate backlog updates, making that distractor false.

  262. Question 262 of 554What is the order of items in the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Less valuable and most unclear items at the bottom

    The Product Backlog is ordered to maximize value, with the most valuable and clear items typically placed at the top. For the exam, remember that the Product Owner orders items based on priority, not simply by when they were added or alphabetically.

  263. Question 263 of 554When is the Scrum Team allowed to interact with the Key Stakeholders (select the most applicable option)?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Any time where it's valuable to have the Stakeholder input

    A Scrum Team can interact with stakeholders at any time if it provides valuable input for the product. While Sprint Reviews are formal feedback events, Scrum does not restrict necessary stakeholder collaboration to official meetings.

  264. Question 264 of 554What does the Sprint Burndown Chart show?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. How much work remains till the end of the Sprint

    A Sprint Burndown chart visually tracks how much total work remains until the end of the Sprint. While not a mandatory official artifact, it is a highly common progress tracking tool you will see tested on the exam.

  265. Question 265 of 554It is a good practice to have from time to time a special technical Sprint that consists only of tasks removing the technical debt without implementing any new functionality.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The correct answer is false because Scrum prohibits dedicated technical Sprints; every Sprint must produce a usable Increment. For the exam, remember that fixing technical debt must occur continuously alongside new feature development rather than in separate phases.

  266. Question 266 of 554When multiple Scrum Teams are working on the same product, should they integrate all their work into a single functional increment every Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Yes, so that the whole Scrum Team and the Stakeholders can inspect a full piece of functionality at the Sprint Review.

    Multiple teams working on one product must integrate their work into a single functional increment every Sprint. This enables proper inspection at the Sprint Review. Dismiss options suggesting integration sprints or independent deliveries.

  267. Question 267 of 554When does inspection occur?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Frequently, but not so often that gets in the way of work.

    Inspection happens frequently throughout Scrum events, but it must not get in the way of actual work. While the Sprint Review is a formal opportunity for inspection, adapting and inspecting continually throughout the Sprint is critical for empirical process control.

  268. Question 268 of 554Why does the Scrum framework recommend small Scrum Teams of 10 or fewer people?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Because they communicate better

    The Scrum Guide notes that smaller teams generally communicate better. However, the official guide primarily highlights that small teams remain nimble while being large enough to complete significant work, making the provided correct option slightly narrow but ultimately accurate.

  269. Question 269 of 554What doesn't happen when a Sprint is cancelled? Select two.

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. Several top Product Backlog Items are taken into the Sprint Backlog to replace the obsolete items · E. At the Sprint Retrospective the Scrum Master determines who from the Developers are responsible for cancelling the Sprint

    When a Sprint is cancelled, work does not get swapped in, and blame is never assessed. Any completed work is reviewed, while incomplete items return to the Product Backlog. Remember that only the Product Owner can cancel a Sprint early.

  270. Question 270 of 554Select the two events in which people outside the Scrum Team are NOT allowed to participate.

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. The Sprint Retrospective · C. The Daily Scrum

    Only the Scrum Team participates in the Sprint Retrospective, and only the Developers participate in the Daily Scrum. Others may attend Sprint Planning or the Sprint Review, so those two events are not completely closed.

  271. Question 271 of 554Although burn-down charts are optional, they can be a useful tool for tracking which measure (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. How much work is remaining across time.

    A burn-down chart tracks the amount of work remaining over a given period of time. It is a progress tracking tool for the Developers, not a mechanism for reporting individual performance, accumulated costs, or realized business value to the organization.

  272. Question 272 of 554Select all the formal opportunities to inspect and adapt.

    Select 4 answers.

    Show answer & explanation

    Correct answer: A. The Sprint Planning · B. The Sprint Review · C. The Daily Scrum · D. The Sprint Retrospective

    All four official Scrum events are formal opportunities to inspect and adapt. The Sprint itself wraps these events, enabling the transparency required for empirical process control.

  273. Question 273 of 554Who is responsible for managing the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Owner

    The Product Owner is solely accountable for effective Product Backlog management, which includes ordering items and ensuring transparency. While others may help, final accountability always rests here, so avoid choosing options that shift this core duty to Developers or the Scrum Master.

  274. Question 274 of 554At the Sprint Retrospective, the Scrum Team identified some improvements that could be made. What should the Scrum Team do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. They address the most impactful improvements as soon as possible. They may even add those to the Sprint Backlog for the next Sprint.

    The team should address its most impactful improvements as soon as possible, often adding them directly to the next Sprint Backlog. Avoid options that mandate assigning specific individuals or require tackling every item simultaneously, as Scrum favors self-management.

  275. Question 275 of 554How does the Scrum Master help the Product Owner? (choose the best three answers)

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Facilitating stakeholder collaboration as requested or needed · D. Helping find techniques for effective Product Goal definition and Product Backlog management · E. Helping establish empirical product planning for a complex environment

    The Scrum Master serves the Product Owner by facilitating collaboration, finding effective management techniques, and establishing empirical planning. Be careful not to select coaching the organization, which is a valid duty but serves the organization rather than the Product Owner directly.

  276. Question 276 of 554When do the Developers create the Sprint Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. During the Sprint Planning

    Developers create the Sprint Backlog during Sprint Planning to map out the work needed for the upcoming Sprint. It is not created after the Sprint starts or during the review, making Sprint Planning the only correct phase.

  277. Question 277 of 554What is the Sprint Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Product Backlog items selected for this Sprint plus the plan for delivering them

    The Sprint Backlog comprises the selected Product Backlog items for the Sprint plus the Developers' plan for delivering them. Options listing only the items or only the plan are incomplete, so always choose the comprehensive definition.

  278. Question 278 of 554What provides guidance to the Developers on why they are building the Increment?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Sprint Goal

    The correct answer is the Sprint Goal because it provides the overarching purpose for the Sprint. For the exam, remember that the Sprint Goal acts as the guiding objective for why the team is building the Increment.

  279. Question 279 of 554Scrum has a role called "Project Manager."

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The answer is false because Scrum only defines three accountabilities: Developer, Product Owner, and Scrum Master. A practical exam cue is to instantly dismiss any mention of project managers.

  280. Question 280 of 554What are the characteristics of a Scrum Team? Select three most appropriate choices.

    Select 3 answers.

    Show answer & explanation

    Correct answer: B. The entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint · C. Scrum recognizes no sub-teams in the Scrum Team · D. Developers hold each other accountable as professionals

    The correct answers work because Scrum Teams are cross-functional, self-managing, and lack internal sub-teams. A practical exam cue is to eliminate any option implying specialized roles or hierarchies.

  281. Question 281 of 554At the Sprint Planning, who is responsible for ensuring that attendees are prepared to discuss the most important Product Backlog items and how they map to the Product Goal?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. The Product Owner

    The Product Owner works because they are accountable for managing the Product Backlog. A practical exam cue is to remember that the Product Owner ensures attendees are ready to discuss key items.

  282. Question 282 of 554Which of the following is not an Agile principle?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Following a plan over responding to change.

    The correct answer works because the Agile Manifesto values responding to change over following a plan. A practical exam cue is to always favor flexibility and adaptability over rigid adherence.

  283. Question 283 of 554The main duty of the Product Owner is:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Maximizing the value of the product resulting from the work of the Scrum Team

    The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. Guarding developers is a common myth; the entire team is self-managing and resilient to interruptions.

  284. Question 284 of 554Which of the following is not a pillar of Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Empiricism

    Empiricism is the foundation of Scrum, but its three pillars are transparency, inspection, and adaptation. Remember the distinction between the overarching theory and the specific pillars supporting it.

  285. Question 285 of 554Scrum is best described as a

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Framework for generating value through adaptive solutions for complex problems

    Scrum is defined as a lightweight framework that helps people generate value through adaptive solutions for complex problems. Avoid calling it a methodology or a collection of best practices, as those terms violate the guide.

  286. Question 286 of 554Which of the following does NOT apply to Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Static requirements

    Scrum requires adaptation, meaning requirements cannot be static or fully predicted upfront. The framework relies on empirical process control to manage complex work rather than rigid predictive planning.

  287. Question 287 of 554Which statement best describes Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. A framework to address complex products in complex environments.

    Scrum is specifically a lightweight framework designed to address complex problems in unpredictable environments. Dismiss any options calling it a defined methodology, a predictable process, or a collection of best practices. It is grounded in empiricism, not rigid computer science principles.

  288. Question 288 of 554Which are considered Scrum Values? (Choose all that apply)

    Select 5 answers.

    Show answer & explanation

    Correct answer: A. Focus · B. Commitment · D. Respect · E. Courage · F. Openness

    The five official Scrum Values are Focus, Commitment, Respect, Courage, and Openness. Self-organization is a core characteristic of successful teams, but it is categorized as a structural pillar rather than an official value. Memorize these five to easily spot tricky distractors.

  289. Question 289 of 554Who is accountable for maximizing the value of the product resulting from the work of the Scrum Team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Product Owner

    The Product Owner is accountable for maximizing product value. For the exam, watch for questions trying to shift this specific accountability to the Developers or Scrum Master. The Product Owner manages the Product Backlog to optimize value.

  290. Question 290 of 554If the Sprint Goal becomes obsolete, the Sprint should be cancelled.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    A Sprint is cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel a Sprint, though others can provide input. Remember that incomplete work does not justify cancelling a Sprint.

  291. Question 291 of 554Could the Product Owner and the Scrum Master also be a Developer?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Yes

    A Product Owner or Scrum Master can also be a Developer if they actively execute Sprint Backlog work. However, Scrum explicitly prohibits anyone having the title of lead or manager within the Scrum Team.

  292. Question 292 of 554Who is responsible for promoting and supporting Scrum? Select the best choice.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Master

    The Scrum Master is responsible for promoting and supporting Scrum as defined in the Scrum Guide. They serve the organization by leading and coaching its adoption. Remember this specific accountability applies to the Scrum Master role.

  293. Question 293 of 554When multiple teams are working on the same product, who should make sure that their outputs can be integrated into one Increment?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers of the Scrum Teams

    The Developers of all Scrum Teams working on the same product are responsible for creating a usable integrated Increment. Multiple teams must coordinate to ensure their combined work is successfully integrated at least by the Sprint end.

  294. Question 294 of 554Who must get feedback from the Key Stakeholders in the Sprint Review? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Team

    The entire Scrum Team must get feedback from key stakeholders during the Sprint Review. This collaborative event goes beyond a simple status report, focusing on gathering stakeholder input to adapt the Product Backlog and optimize future value.

  295. Question 295 of 554What is used by the Scrum Team to identify unfinished work at the end of the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Definition of Done

    The Definition of Done creates transparency by providing a strict set of criteria to evaluate incomplete work at the end of a Sprint. If an item fails to meet this shared standard, it cannot be part of the finished Increment.

  296. Question 296 of 554The Product Owner can invite stakeholders to the Product Backlog Refinement sessions.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Yes

    The Product Owner can indeed invite stakeholders to Product Backlog refinement sessions to gather insights and clarify expectations. This collaboration ensures the team understands market needs without disrupting the Developers' accountability over their work.

  297. Question 297 of 554Doing your best and helping other Scrum Team members demonstrates which of the following?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Value of Commitment

    Doing your best and helping others demonstrates the Scrum value of commitment. While high performance is a goal, the specific behavior of personal dedication directly aligns with this foundational value, making it the best choice.

  298. Question 298 of 554Scrum is an iterative and incremental Agile framework.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    Scrum is founded on empiricism, making it inherently iterative and incremental. It repeats cycles to inspect progress and adds usable functionality step by step, so any definition missing these concepts is incorrect.

  299. Question 299 of 554All Scrum Teams working on the same Product should use the same Product Backlog.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    All Scrum Teams working on the same product must use a single Product Backlog. This rule ensures transparency, proper prioritization, and alignment under one Product Owner, even when multiple teams execute the work.

  300. Question 300 of 554When multiple Scrum Teams work on the same product (and therefore same Product Backlog), how should the Product Backlog items be picked by each team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Developers (or appropriate representatives) of each Scrum Team pull work from the Product Backlog in agreement with the Product Owner.

    The correct answer works because developers pull work rather than having it pushed or assigned by a manager. For the exam, remember that self-management means teams select their own items in coordination with the Product Owner.

  301. Question 301 of 554Which of the following statements is not correct?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Product Owner only orders the Product Backlog Items on their value

    The correct answer works because ordering goes beyond just value. A practical exam cue is to remember that the Product Owner also considers dependencies, risk, and market conditions when ordering items.

  302. Question 302 of 554Who is allowed to make changes in the Product Backlog? Select two options.

    Select 2 answers.

    Show answer & explanation

    Correct answer: C. The Developers, but with permission of the Product Owner · E. The Product Owner

    The correct answers work because the Product Owner manages the backlog and can delegate work to Developers. A practical exam cue is that anyone can add items, but final authority rests with the Product Owner.

  303. Question 303 of 554The Scrum Framework recommends:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Early and frequent releases of usable increments

    The correct answer works because Scrum emphasizes frequent delivery to maximize feedback. A practical exam cue is to recall that multiple Increments can even be released within a single Sprint.

  304. Question 304 of 554What is a good way for a Scrum Team to ensure that security concerns are addressed and made transparent?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Have the Scrum Team create Product Backlog items for each concern and/or add security concerns to the Definition of Done.

    Addressing non-functional requirements like security means integrating them directly into the Definition of Done or adding them to the Product Backlog. Avoid isolated sprints or separate backlogs, because these create hidden dependencies and break cross-functional team flow.

  305. Question 305 of 554From the organization's perspective, who is accountable for creating the Increment every Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Team

    The entire Scrum Team shares accountability for creating a valuable Increment each Sprint. While Developers actually build it, the Product Owner and Scrum Master are also accountable for overall success, making options listing only Developers incorrect.

  306. Question 306 of 554Where can Scrum be used? Select all the applicable answers.

    Select 6 answers.

    Show answer & explanation

    Correct answer: A. Development of products and enhancements · B. Development of software and hardware · C. Development of almost everything we use in our daily lives as individuals and societies · D. Development and sustaining of Cloud and other operational environments · E. Managing the operation of an organization · F. Research and identifying of viable markets, technologies, and product capabilities

    Scrum is highly versatile and applies to software, hardware, research, and organizational management. Whenever a question asks where it can be used, default to selecting all positive domains, as the framework applies to complex product development broadly.

  307. Question 307 of 554What could be a source of requirements for any changes to be made to the product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Product Backlog

    The Product Backlog is the single source of requirements for any changes made to the product. For the exam, remember that stakeholders can request features, but those features only become actionable requirements once they are added to the Product Backlog by the Product Owner.

  308. Question 308 of 554A Scrum Team is at the end of a Sprint. The next Sprint starts:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Immediately after the Sprint Retrospective

    A new Sprint starts immediately following the conclusion of the previous Sprint Retrospective. This continuous cycle ensures no downtime between Sprints. Do not assume a release to production is required before starting the next Sprint.

  309. Question 309 of 554The Scrum Master serves the Scrum Team in several ways, including:

    Select 3 answers.

    Show answer & explanation

    Correct answer: A. Causing the removal of impediments to the Scrum Team's progress · B. Coaching the team members in self-management and cross-functionality · D. Helping the Scrum Team focus on creating high-value Increments that meet the Definition of Done

    The Scrum Master serves the team by coaching self-management, focusing on value, and removing impediments. Eliminate any option suggesting the Scrum Master acts as a direct manager or unilaterally changes team composition based solely on velocity.

  310. Question 310 of 554How much time is required after a Sprint to prepare the next Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. None. A new Sprint starts immediately after the end of the previous Sprint

    A new Sprint starts immediately after the previous Sprint concludes, requiring no preparation time in between. For the exam, strictly reject any options suggesting downtime for testing, documentation, or breaks between Sprints.

  311. Question 311 of 554Which of the following statements is true?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Sprint Retrospective focuses on Scrum Team's process and people aspects while the Sprint Review focuses on the product

    The Sprint Retrospective focuses on processes and people, while the Sprint Review focuses on the product. A key exam cue is that the Review inspects the Increment, whereas the Retrospective inspects team processes.

  312. Question 312 of 554It is normal to have a "hardening" Sprint to remove all technical debt and prepare the Product for the upcoming release.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    It is false because a hardening Sprint to clear technical debt violates the Definition of Done rule for every Increment. For the exam, always insist that each Sprint must result in a potentially releasable product.

  313. Question 313 of 554What are the accountabilities in a Scrum Team? Select all that apply.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: F. None of the above

    The only specific accountabilities in Scrum are Developers, Product Owner, and Scrum Master. Job titles like architect or tester do not exist as separate roles within the official rules.

  314. Question 314 of 554At the eighth Sprint Review, the stakeholders are upset that the product being built is not what they expected and will incur additional costs that were not planned for. What may have led to this?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Master has not ensured that the project is transparent. The Product Owner has not made the stakeholders aware of the progress of the project. The stakeholders have not been attending the Sprint Reviews.

    This scenario indicates a lack of transparency and missed stakeholder feedback at the Sprint Review. The empirical process requires regular inspection by stakeholders to avoid costly late-stage surprises.

  315. Question 315 of 554The frequency of updating the product backlog is:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Anytime, as needed

    The Product Backlog is a living artifact that can be updated anytime as needed to reflect changing priorities. Expect exam questions linking continuous backlog refinement to empirical process control. It never freezes or waits strictly for Sprint boundaries.

  316. Question 316 of 554What would be the main benefits of self-management?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Increased creativity, self-accountability, commitment.

    Self-management directly fosters increased creativity, self-accountability, and commitment within the team. Rule compliance and sheer output contradict the agile mindset. Recognize that empowering developers to solve complex problems drives true ownership and successful deliveries.

  317. Question 317 of 554What are the inputs to Sprint Planning? (Choose four)

    Select 4 answers.

    Show answer & explanation

    Correct answer: A. The latest product Increment · B. Projected capacity of the Scrum Team during the Sprint · C. The Product Backlog · D. Past performance of the Scrum Team

    Sprint Planning requires the Product Backlog, the latest product Increment, past team performance, and projected capacity. While stakeholder feedback is valuable, it typically influences the backlog earlier. Focus strictly on these four inputs when tackling planning questions.

  318. Question 318 of 554It is the responsibility of the Scrum Master to engage the stakeholders to maximize the value of the product

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    This statement is false because maximizing product value is the accountability of the Product Owner. The Scrum Master focuses on ensuring Scrum is understood and enacted, acting as a facilitator and coach rather than managing product value.

  319. Question 319 of 554For the Product Backlog Refinement, the Scrum Team needs to define a recurring preset time every week outside the current working hours of the Developers.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Product Backlog refinement is an ongoing activity consuming no more than ten percent of Developers' capacity. Scrum does not prescribe a specific weekly time outside working hours. The Developers size items during this continuous refinement process.

  320. Question 320 of 554The Developers of the Scrum Team are waiting for a specific software component that they need to integrate and use. The component should be ready in two months. The Product Backlog items with highest priorities depend on this specific component. What should the Product Owner do? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Re-order the Product Backlog to maximize utilization of the Developers and deliver at least some Increment of product functionality in the next Sprint.

    The Product Owner should re-order the Product Backlog to ensure the Developers can deliver a valuable Increment without being blocked by dependencies. A practical exam cue is that Product Owners must always maximize value by sequencing work to deliver functional increments every Sprint.

  321. Question 321 of 554Who is responsible for crafting the Sprint Goal at the Sprint Planning?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Team

    The entire Scrum Team collaborates to craft the Sprint Goal during Sprint Planning. While the Product Owner proposes objectives, the Developers must figure out how to deliver the goal, ensuring everyone shares a clear focus for the Sprint.

  322. Question 322 of 554Is it allowed to skip the Daily Scrum if there is nothing interesting to talk about?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. No

    The Daily Scrum cannot be skipped because it provides critical daily inspection of progress toward the Sprint Goal. As an mandatory event, it ensures the Developers continuously adapt their plan to avoid falling behind.

  323. Question 323 of 554The Scrum Team is self-managing which means:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. It manages how to perform the development work

    A self-managing Scrum Team decides internally how to perform its development work, assigning tasks and choosing methods independently. Remember that management or external roles do not dictate how the Developers accomplish their Sprint Backlog work.

  324. Question 324 of 554When technical debt occurs, the system might become more unstable as development progresses and code is added, resulting in future work being slowed down.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    Accumulated technical debt reduces transparency, increases complexity, and slows down future development as the system becomes harder to maintain. On the exam, always associate unchecked technical debt with decreased velocity, lower quality, and hidden risks.

  325. Question 325 of 554The practice of Product Backlog refinement focuses on items for upcoming Sprints, not the current Sprint in progress.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    The correct answer works because refinement targets future work rather than the active Sprint Backlog. A practical exam cue is to remember that the Product Owner can still clarify current Sprint items as needed.

  326. Question 326 of 554Select the true statements. Before starting the first Sprint, what are the prerequisites?

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. Just enough Product Backlog Items with business ideas for the first Sprint · B. A staffed Scrum Team

    A Sprint can start once a complete Scrum Team exists and enough Product Backlog items are ready to define the work. You do not need a complete Product Backlog or architecture, because Scrum embraces emergent requirements over rigid upfront planning.

  327. Question 327 of 554What is the optimal length of a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Short enough to minimize risk

    The optimal Sprint length is short enough to minimize risk and allow for quick feedback without excessive overhead. Exam cue: never pick a rigid timebox like two weeks, because the optimal length varies based on the specific context and environment.

  328. Question 328 of 554Which of the following is a way to reduce technical debt?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Improving the Definition of Done

    Strengthening the Definition of Done forces the team to resolve quality issues immediately, which directly limits new technical debt. Be wary of external auditors, because quality must be internally owned by the Developers doing the actual work.

  329. Question 329 of 554Who advises what to work on for the next Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner

    The Product Owner is responsible for managing the Product Backlog, which ultimately dictates what the Scrum Team works on next. Watch out for a Product Manager option, as that generic role does not inherently hold Scrum responsibilities.

  330. Question 330 of 554Which of the following refers to the average amount of work done per Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Velocity

    Velocity measures the average amount of work completed per Sprint. A practical exam cue is to distinguish velocity from capacity, which estimates available hours or effort, rather than historical completion rates.

  331. Question 331 of 554Which activity or event takes place between the current Sprint and the next Sprint beginning?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. None

    No activity takes place between Sprints because a new Sprint starts immediately after the previous one concludes. For the exam, remember Scrum emphasizes continuous flow without any gaps or downtime between Sprints.

  332. Question 332 of 554As a Scrum Master, what would you strive for if five new Scrum Teams were to work on one product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The product has one Product Backlog and one Product Owner.

    A single product must have exactly one Product Backlog and one Product Owner, regardless of the number of teams. Avoid the common trap of scaling by adding Product Owners or backlogs for each new team.

  333. Question 333 of 554If an inspector determines that one or more aspects of a process deviate from acceptable limits, when must an adjustment be made?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. As soon as possible to minimize further deviation

    An adjustment must be made as soon as possible to minimize further deviation. Avoid options that add unnecessary approval steps or delay fixing the issue until another event like the Daily Scrum.

  334. Question 334 of 554How often should Scrum practitioners review Scrum artifacts and monitor progress towards achieving a Sprint Goal?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Frequently, but it should not get in the way of the work

    Artifacts and progress must be inspected frequently, but not so often that it gets in the way. Avoid the trap of picking extreme answers like inspecting as frequently as possible, which disrupts actual work.

  335. Question 335 of 554Which statements about the Sprint Retrospective meeting are correct? (Choose 2 answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: C. It's three hours in a one-month Sprint · D. It's an opportunity for inspection and adaptation

    The Retrospective is a three-hour event for a one-month Sprint and serves as an opportunity for inspection and adaptation. Do not fall for distractors stating it happens before the Review or excludes the Product Owner.

  336. Question 336 of 554Who is responsible for the development quality in Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Everyone who performs the development work

    The entire Scrum Team is responsible for the quality of the development work. A good exam tip is that Scrum avoids traditional titles like lead developer or tester to enforce shared team accountability for quality.

  337. Question 337 of 554What does the Burn-down Chart show?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. How much work remains till the end of the Sprint

    A burn-down chart visually tracks the remaining work against the Sprint timebox. While not an official artifact, it remains a widely accepted tracking tool on the exam for measuring progress.

  338. Question 338 of 554What is the Sprint Retrospective?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. It is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint

    The Sprint Retrospective is specifically designed for the Scrum Team to inspect its own interactions and processes, creating an actionable improvement plan. Avoid broad labels like inspect and adapt; the Sprint Review adapts the Product Backlog, not team processes.

  339. Question 339 of 554Each Increment must be released to production to maximize value.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    An Increment only needs to be potentially releasable to meet the Definition of Done, meaning it must be in a usable state regardless of whether the Product Owner actually releases it. The Product Owner decides the optimal release timing to maximize return on investment.

  340. Question 340 of 554Which Scrum Value is impacted by trust?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: F. All the answers are correct

    Trust is the foundation that enables every single Scrum Value, making the all of the above option correct. Without trust, teams lack the courage to take risks or the openness to share challenges. Expect trust and empiricism to remain heavily emphasized on the exam.

  341. Question 341 of 554Developers of a Scrum Team decide to divide the Sprint Backlog and assign ownership of every Sprint Backlog item to each member of the team. The Scrum Master should:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Coach the team to collectively take ownership of the Sprint Backlog items

    The Scrum Master should coach the team to collectively own the Sprint Backlog. Developers are self-managing and share accountability. Assigning items destroys collaboration and limits learning across the team.

  342. Question 342 of 554A Developer's behavior causes issues to the whole Scrum Team and affects the progress of the development work. Who is responsible for resolving the issue?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Scrum Master

    The Scrum Master is specifically responsible for resolving team conflicts and removing impediments that affect progress. While the Scrum Team is self-managing, the Scrum Master serves as the facilitator for addressing behavioral issues when the team cannot resolve them independently.

  343. Question 343 of 554Technical Debt can lead to false assumptions about the current state of the system and the Increment reviewed at the end of the Sprint.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    Accumulated technical debt obscures the true quality of the Increment, leading stakeholders to falsely assume the product is stable. Watch for velocity spikes on the exam, as taking shortcuts to inflate speed is a classic trap indicating hidden debt.

  344. Question 344 of 554What belongs solely to the Developers?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Sprint Backlog

    The Sprint Backlog is managed solely by the Developers throughout the iteration. Note that option B is a known distractor; while the team owns the Definition of Done, the Developers are specifically accountable for adapting it, which can make this phrasing slightly ambiguous.

  345. Question 345 of 554Who takes the ownership of Scrum Events?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Scrum Team

    The entire Scrum Team owns the Scrum events. The Scrum Master merely facilitates these events and ensures they stay within timeboxes, so avoid choosing the Master whenever the question specifically asks about ownership.

  346. Question 346 of 554It is good practice to maintain separate Product Backlogs for multiple Scrum Teams working on one product.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Scrum requires exactly one Product Backlog for a product, regardless of how many Scrum Teams are working on it. A single backlog ensures transparency, unified prioritization, and prevents overlapping work across multiple teams.

  347. Question 347 of 554A Developer is requested by an important stakeholder to help them with some external tasks. The Developer referred him to the Product Owner. In this case, the Scrum Master should:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Do nothing since the Developer's action is correct

    The Developer correctly redirected the stakeholder to the Product Owner, who solely manages the Product Backlog. Because the Developers acted appropriately by protecting their Sprint focus, the Scrum Master does not need to intervene.

  348. Question 348 of 554When a product grows, it is quite possible that the Product Owner will get help from other Product Managers and others in the organization who interact regarding the customer facing activities and knowledge of the product marketplace. Is it a good idea for the Product Owner to proxy or outsource some of their duties to these people (for example, Scrum Team facing duties)?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. No

    A Product Owner can get help from others, but they cannot proxy or outsource their final accountability, especially regarding team-facing duties. They remain responsible for making the decisions and managing the Product Backlog effectively.

  349. Question 349 of 554What are not Product Backlog characteristics? Select two.

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. A Product Backlog could be closed when it contains no items to include into the next Sprint · C. When the final version of a product is rolled out, its Product Backlog is dismissed

    A Product Backlog is never closed or dismissed, and it exists as long as the product does. A strong exam cue is that a product always evolves, meaning there is never a final version in Scrum.

  350. Question 350 of 554What would likely happen if management only changed the organization's current terminology to fit Scrum without the proper understanding and support of Scrum as defined in the Scrum Guide?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. All answers apply.

    Simply renaming roles without adopting the Scrum framework prevents realizing its true benefits. Changing vocabulary alone does not change behavior. If management wants less stress, real structural change is required.

  351. Question 351 of 554During the Sprint, the Developers track the remaining work and the trend at least:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Everyday

    The Developers track remaining work and progress trends every day during the Daily Scrum. This daily inspection allows the team to adapt their plan immediately and ensure they are trending toward achieving the Sprint Goal.

  352. Question 352 of 554The Scrum Team adapts the Definition of Done during:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Sprint Retrospective

    The Scrum Team adapts the Definition of Done during the Sprint Retrospective. This event is designed for inspecting processes and planning ways to increase quality, making it the correct place to strengthen what it means for work to be complete.

  353. Question 353 of 554Scrum is founded on what?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Empiricism

    Scrum is firmly rooted in empiricism, which means making decisions based on observed reality and experience. The provided question text incorrectly mentions Kanban, so ignore that prompt error and memorize the three empirical pillars for your exam.

  354. Question 354 of 554In a Nexus context, all the Scrum Teams' Sprints must be aligned.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True

    In a Nexus context, all Scrum Teams must align their Sprints to integrate work effectively and minimize dependencies. While Nexus is a scaling extension, the underlying principle of synchronized Sprints is universally tested in Scrum concepts.

  355. Question 355 of 554Select the correct statement regarding the Definition of Done. Before the Sprint Planning, the Developers must have a Definition of Done formally approved by the Product Owner.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. None of the answers is correct

    The Definition of Done is created by the Scrum Team and does not require formal Product Owner approval. The other options mention user stories and Scrum Boards, which are optional complementary practices not mandated by Scrum.

  356. Question 356 of 554How can a Product Owner validate the results of his/her assumptions made for the Product? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Releasing Increments to the market, early and often, to learn about the business assumptions built into the product.

    A Product Owner validates assumptions by releasing increments early and often to measure actual market feedback. End-of-Sprint testing only verifies build quality, while a Sprint Goal simply provides focus. Real validation requires empirical user data.

  357. Question 357 of 554How long should the Sprint Retrospective be?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. A time-boxed meeting of 3 hours for a 1-month sprint, for shorter sprints this can be a shorter event

    The Sprint Retrospective is timeboxed to a maximum of three hours for a one-month Sprint, and is usually shorter for shorter Sprints. Memorize the official maximum timeboxes. The eight-hour limit applies to Sprint Planning, not the Retrospective.

  358. Question 358 of 554The Scrum Master helps the Product Owner do what with regard to the product backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Scrum Master helps find techniques for effective Product Goal definition and Product Backlog management

    The Scrum Master serves the Product Owner by facilitating effective Product Goal definition and backlog management techniques. Watch out for distractors suggesting the Scrum Master either takes over backlog responsibility or remains completely uninvolved.

  359. Question 359 of 554A Sprint Retrospective can last up to 8 hours for a one-month Sprint.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The Sprint Retrospective is timeboxed to a maximum of three hours for a one-month Sprint. For the exam, remember that the Sprint Planning event is the only event with an eight-hour maximum for a one-month Sprint.

  360. Question 360 of 554When can the Product Backlog be revised? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Backlog can be updated at any time by the Product Owner or at the Product Owner's discretion.

    The Product Backlog is dynamic and can be updated at any time by the Product Owner. For the exam, dismiss options that restrict changes to specific Scrum events or require formal change requests, as Scrum favors continuous adaptation.

  361. Question 361 of 554The Sprint Retrospective marks the beginning of a new Sprint.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    A new Sprint starts immediately after the conclusion of the previous Sprint. The Sprint Retrospective is the final event of a Sprint, marking its end rather than the beginning of the next one. Sprint Planning is always the first event.

  362. Question 362 of 554The Scrum Master serves the Scrum Team but not the larger organization.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The Scrum Master serves both the Scrum Team and the larger organization as a true leader. A common exam trap is assuming the Scrum Master only focuses inward on the team, completely ignoring their broader organizational coaching and leadership responsibilities.

  363. Question 363 of 554The Product Owner is accountable for:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Ensuring that the Product Backlog is transparent, visible and understood

    The Product Owner is accountable for effective Product Backlog management, which includes ensuring the backlog is transparent, visible, and understood. Creating the Sprint Backlog is the Developers' accountability, while coaching the team belongs to the Scrum Master.

  364. Question 364 of 554What variables should a Product Owner consider when ordering the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Whatever is most appropriate for the Product Owner to achieve the product's goals and to optimize the value received

    The Product Owner orders the Product Backlog in any way that best achieves the product's goals and optimizes overall value. Avoid rigid formulas like prioritizing effort or lowest cost first, because true value optimization depends entirely on context.

  365. Question 365 of 554You are in a Scrum Team that is in the middle of the Sprint. Your team gets some additional team members. The likely result is:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The team may suffer in its productivity

    Adding members mid-Sprint typically reduces short-term productivity due to the overhead of onboarding and communication. Remember Brook's Law; adding people disrupts the existing team dynamics. A Sprint is rarely extended or re-planned just for new members.

  366. Question 366 of 554What are the five Scrum events?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The sprint, sprint planning, daily scrum, sprint review, sprint retrospective

    The five Scrum events are the Sprint, Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. The Sprint itself acts as a container for the other four events. Remember that backlog refinement and releases are not official Scrum events.

  367. Question 367 of 554What are the pillars of the empirical process in Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Transparency, inspection, adaptation

    Scrum is founded on empiricism, which relies on the three pillars of transparency, inspection, and adaptation. Watch out for options listing Scrum values or mixing up the pillars, as those are common distractors.

  368. Question 368 of 554How long should the Daily Scrum be?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. 15 minutes

    The Daily Scrum is strictly timeboxed at fifteen minutes to optimize inspecting progress. Remember that timeboxes are fixed maximums, so options suggesting the duration varies based on Sprint length are incorrect.

  369. Question 369 of 554What is empirical process control in relation to Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Knowledge comes from experience and making decisions based on what is known – this can be achieved by using the 3 pillars of transparency, inspection, adaptation

    Empiricism asserts that knowledge comes from experience, requiring decisions based on known information via transparency, inspection, and adaptation. Strong distractors often reference unrelated Agile techniques to confuse you.

  370. Question 370 of 554The Product Owner's authority to change and update the Product Backlog is unlimited, except for:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: F. Nothing. The entire organization must respect a Product Owner's decisions.

    The entire organization must respect the Product Owner's decisions regarding the Product Backlog, meaning their authority is absolute. Exam cues often include traditional titles like CEO to trick you into thinking hierarchy overrides the role.

  371. Question 371 of 554The structure of the Daily Scrum is set by the Scrum Master.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The Developers are responsible for selecting and structuring the Daily Scrum to best meet their inspection needs. A key exam cue is that Scrum Masters act as facilitators and coaches rather than dictating internal team processes or meeting formats.

  372. Question 372 of 554A Developer has notified the Scrum Master of a potential data security risk. What action should the Scrum Master take?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Ask the Developer to share the issue with the team as soon as possible.

    The Scrum Master should coach the Developer to bring the issue to the team immediately so they can collaborate on a solution. Do not wait for a retrospective to address a serious impediment or risk that threatens the current Sprint.

  373. Question 373 of 554How can the Product Owner benefit from having time-boxed Sprints?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. By having shippable increments every Sprint, he/she can have work released in order to obtain feedback from users and the market in order to feed back into the Product Backlog.

    Timeboxed Sprints allow the Product Owner to receive a usable Increment frequently, enabling early market feedback. This empirical feedback loop is essential for updating the Product Backlog. Scrum never guarantees fully delivered projects by a fixed deadline.

  374. Question 374 of 554What is the Product Owner accountable for in Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Creating and sustaining a Product Backlog that maximizes value and represents the needs of the stakeholders

    The Product Owner is accountable for creating and managing a transparent Product Backlog that maximizes value. They do not hand off refined items or dictate daily technical work. Writing user stories is just one possible technique, not a formal accountability.

  375. Question 375 of 554Which two statements explain why the Definition of Done is important to the Scrum Team? (Choose the two best answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. It assures the Increment reviewed at the Sprint review is usable so the Scrum Team may choose to release it. · C. It creates transparency regarding progress within the Scrum Team.

    The Definition of Done creates transparency by providing a shared understanding of what work was completed, ensuring the Increment is usable. Options A and D fail because tracking open work or identifying undone work is a byproduct of artifact transparency, not the primary purpose of the Definition of Done.

  376. Question 376 of 554Which two of the following are mandatory in Scrum?

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. Sprint Retrospectives · D. Sprint Backlog

    Scrum mandates specific events and artifacts, making the Sprint Retrospective and Sprint Backlog required elements. Remember that Scrum does not dictate specific development techniques like pair-programming or formatting rules like user stories.

  377. Question 377 of 554A group of stakeholders wants to come to the Daily Scrum. How should the Scrum Master handle that situation?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Instruct the stakeholders to remain quiet and refrain from asking questions or making comments; they are allowed to listen in for the sake of transparency but the meeting is for the developers

    The Daily Scrum is exclusively for the Developers to inspect progress and adapt their plan. If stakeholders attend, the Scrum Master must ensure they only observe and do not disrupt the event.

  378. Question 378 of 554What three questions must be answered during Sprint Planning in order to create an effective Sprint Goal?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Why, What, How

    Sprint Planning addresses why the Sprint is valuable, what can be done, and how the work will get done. A solid exam cue is to remember these three distinct topics that guide the creation of the Sprint Goal and Sprint Backlog.

  379. Question 379 of 554The Developers find out during the Sprint that they aren't likely to build everything they forecasted. What would you expect a Product Owner to do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Re-work the selected Product Backlog items with the Developers to meet the Sprint Goal.

    The Product Owner and Developers can renegotiate the scope of the Sprint Backlog as more is learned without changing the Sprint Goal. Canceling the Sprint is an extreme measure and only the Product Owner can take it.

  380. Question 380 of 554As a Scrum Master, you observe that the Product Owner is not collaborating with the Developers effectively. What actions would you take?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Coach the Product Owner.

    The Scrum Master serves the Product Owner by coaching them on effective collaboration with the Developers. Avoid acting as a proxy or go-between, as direct communication between the Product Owner and Developers is essential.

  381. Question 381 of 554Why is it crucial for the Scrum Team to be familiar with the Definition of Done? (choose the best two answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. It guarantees that the Increment presented at the Sprint Review is ready for deployment, allowing the Scrum Team to determine its release. · C. It creates transparency regarding progress within the Scrum Team.

    Familiarity with the Definition of Done ensures the Increment is usable and creates transparency regarding progress. Options B and D fail because the Definition of Done is a quality measure, not a tracking tool or bottleneck identifier.

  382. Question 382 of 554At the end of the Sprint, all items are done except for one that is almost done. What should be done with this item?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Do not include it in the Increment.

    Only items that meet the Definition of Done can be included in the Increment, meaning partially finished work must remain out. Options involving customer acceptance or user testing fail because they violate the core rule that done means done without exceptions.

  383. Question 383 of 554When is the proper time for a Business Analyst on a Scrum Team to discuss the proper workflow of the application?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. There is no Business Analyst role recognized by Scrum

    Scrum only recognizes three accountabilities: Product Owner, Scrum Master, and Developers. There is no Business Analyst role. Any team member performing analysis is considered a Developer and handles these discussions as needed during the Sprint.

  384. Question 384 of 554Selena, a Product Owner for a Scrum Team, has refined the Product Backlog based on risk and value. John, a program manager with the PMO overseeing the group of projects Selena is working on, has ordered Selena to place a different item at the top of the Product Backlog. What should Selena do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Selena may consider the opinions of others as to how she organizes the product backlog, but the final say as to the order is hers and hers alone

    The Product Owner is solely accountable for the final ordering of the Product Backlog. While stakeholders like John can offer input, Selena has the ultimate authority. The organization must respect her decisions to maintain clear accountability.

  385. Question 385 of 554In what ways does the Scrum Master keep a Scrum Team working at its highest level of productivity?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. By causing the removal of impediments to the Scrum Team's progress

    Causing the removal of impediments directly supports Scrum Team productivity. Avoid options that assign administrative tracking tasks to the Scrum Master, since self-managing Developers should handle their own artifacts.

  386. Question 386 of 554What must the Developers do for each Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Develop an increment of potentially releasable product meeting the definition of "Done"

    Developers must create a potentially releasable Increment that meets the Definition of Done during every Sprint. For the exam, ignore specific estimation techniques like planning poker as mandatory rules, and focus on the core accountability of delivering value.

  387. Question 387 of 554To deliver a single product, three different Scrum Teams are formed. How many Product Owners are needed?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. One

    A single product must have exactly one Product Backlog and one Product Owner to ensure a clear vision and maximize value. Multiple teams can work from this single backlog, even if the Product Owner delegates specific backlog management tasks to others.

  388. Question 388 of 554The Developers have suggested moving the Daily Scrum to every two days instead of every day. What is the most appropriate action for the Scrum Master to take?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Learn why the Developers want this, coach the team on why the Daily Scrum is important and work with them to improve the outcome of the Daily Scrum.

    The Scrum Master should coach the Developers on why a daily inspection is critical for adapting the plan. While the team self-manages, supporting an arbitrary reduction misses the core value of daily progress inspection.

  389. Question 389 of 554Which statement best describes the Sprint Backlog in an active Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The scope may be re-negotiated as more is learned.

    The Sprint Backlog is a living artifact, and its scope can be clarified and renegotiated between the Product Owner and Developers. Remember that swapping items purely for priority changes distracts from the Sprint Goal.

  390. Question 390 of 554A Product Owner is applying value estimations to Product Backlog items. Is this acceptable? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Yes. It's OK as it can help the Product Owner order the Product Backlog and validate the expected value against the actual delivered value.

    Applying value estimations is perfectly acceptable because it helps the Product Owner order the Product Backlog effectively. Avoid distractors claiming certain estimation practices are strictly mandated by Scrum.

  391. Question 391 of 554A discussion of what to do next is part of the Sprint Review.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. True, and it may capture probable Backlog Items for the next Sprint, but the scope of the next Sprint is deferred until Sprint Planning

    A discussion of what to do next is a core feature of the Sprint Review to help guide the next Sprint. Remember that final scope decisions are strictly deferred until Sprint Planning.

  392. Question 392 of 554There can be a maximum of one release per Sprint.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    You can release multiple Increments within a single Sprint, as long as each meets the Definition of Done. The exam expects you to know that a Sprint does not strictly limit the number of releases.

  393. Question 393 of 554In some cases, work can be considered part of an Increment even if it doesn't meet the Definition of Done.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The correct answer is false because an Increment must meet the Definition of Done to be considered complete. Watch for options suggesting partially done work can be included; it violates core transparency.

  394. Question 394 of 554An organization that is new to Scrum wants to know how the interactions should be between the Product Owner and the Stakeholders. Which statement best describes the relationship? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Owner proactively seeks feedback and expectations from stakeholders in order to make changes to the Product Backlog.

    The Product Owner actively collaborates with stakeholders to gather feedback and refine the Product Backlog. Avoid options positioning stakeholders as approvers or requiring handoffs of documentation.

  395. Question 395 of 554The items in the Product Backlog are ordered by value only.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Ordering considers more than just value, including dependencies, risk, and effort. While value is important, dependencies often force lower-value items to be completed first.

  396. Question 396 of 554What are two typical activities for a Product Owner in a Sprint?

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. Work with the Developers on Product Backlog refinement. · E. Collaborate with stakeholders, user communities and product managers.

    The Product Owner refines the backlog with Developers and collaborates with stakeholders. Distractors involving daily task management or mandatory attendance exceed the role's defined boundaries.

  397. Question 397 of 554Which two alternatives are viable when the Product Owner is unavailable? (choose the best two answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. If the Product Owner is consistently absent, a replacement must be designated. The Scrum framework requires the presence of a Product Owner role. · D. During the Sprint, Developers make optimal decisions to progress toward the Sprint Goal and reconnect with the Product Owner once he/she is available again.

    If a Product Owner is permanently absent, a replacement is mandatory. For temporary absences, self-managing Developers make optimal decisions to achieve the Sprint Goal.

  398. Question 398 of 554A Scrum Master may cancel a sprint at any time.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The Product Owner is the only role with the authority to cancel a Sprint. Remember that while the Scrum Master, Developers, or stakeholders can influence this decision, the final say rests exclusively with the Product Owner.

  399. Question 399 of 554Which three statements are correct about non-functional requirements?

    Select 3 answers.

    Show answer & explanation

    Correct answer: C. Some of them can be added to the Product Backlog. · D. Some of them can be added to the Definition of Done. · E. They should be incorporated into every increment.

    Non-functional requirements guide how the product functions and can reside in the Product Backlog, the Definition of Done, or apply globally. Discard distractors mentioning integration sprints or separate backlogs, as these are outdated concepts.

  400. Question 400 of 554Paul is a Scrum Master and leads a team of eight people. He wants to add a ninth person (a Developer) to help strengthen some areas where current skills are lacking. He has recently received approval from his managers to hire an additional Developer. How should Paul go about choosing the right Developer for the Scrum Team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Paul should include the current Developers in the hiring decision. They should know what skills they need for their team and have a chance to evaluate potential additions to the Scrum Team

    Scrum Teams are self-managing and should make their own decisions about team composition and hiring. The Developers know exactly what skills they lack. For the exam, remember that Scrum Masters and HR should act as facilitators rather than dictating team structure.

  401. Question 401 of 554Which statement is true about projects with one product and multiple Scrum Teams?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. It should have one Product Backlog and one Product Owner

    A single product must always have exactly one Product Backlog and one Product Owner to maintain clear accountability. Having multiple backlogs fragments the vision. This one-to-one-to-one ratio is a core Scrum concept for the exam.

  402. Question 402 of 554What action can the Scrum Master take to ensure communication between the Developers and Product Owner is effective?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Observe the communications between them and facilitate discussions if needed or by request.

    The Scrum Master serves as a facilitator and servant leader, observing interactions and guiding effective communication. Acting as a gatekeeper or forcing technical language fails because the Product Owner should focus on business value.

  403. Question 403 of 554What are the five values of Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Commitment, respect, focus, openness, courage

    The five Scrum values are commitment, focus, openness, respect, and courage. These values bring the pillars of transparency, inspection, and adaptation to life. Watch out for options that incorrectly mix the three empirical pillars into the values list.

  404. Question 404 of 554If Developers cannot complete all of the required elements of a Sprint, what should they do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Developers should meet with the Product Owner and adjust the Sprint Backlog if needed

    If the Developers realize they cannot complete the planned work, they must collaborate with the Product Owner to negotiate and adjust the Sprint Backlog scope. Extending the Sprint is never allowed, and the Developers manage their own scope.

  405. Question 405 of 554When multiple Scrum Teams are working on the same project, what best describes the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. All the Scrum Teams must mutually define and comply with the same Definition of Done

    When multiple Scrum Teams work on the same product, they must mutually define and comply with a single integrated Definition of Done. This ensures the combined work results in a cohesive, potentially releasable Increment at the end of every Sprint.

  406. Question 406 of 554Which two of the following may change during the Sprint? (choose the BEST two answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: C. Product Backlog · D. Sprint Backlog

    Both the Product Backlog and the Sprint Backlog are emergent and can change as the team learns more during the Sprint. The Sprint Goal remains fixed, and changing team composition mid-Sprint is highly discouraged.

  407. Question 407 of 554Which practice must be used by a Product Owner to manage the Product Backlog and share the Product Backlog progress? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Any projective practice based on trends of work completed and upcoming work to be done.

    The Product Owner may use any projective practice based on past work trends to forecast progress, such as burn-downs or burn-ups. Scrum does not mandate a specific charting tool, so any highly specific option is incorrect.

  408. Question 408 of 554Which description best fits the accountability of the Product Owner?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Value Maximizer

    The Product Owner is accountable for maximizing the value of the product resulting from the work of the Developers. Remember that the Product Owner focuses on business value, not on traditional project management roles or simply gathering requirements.

  409. Question 409 of 554Learning turns into 'validated learning' when assumptions and goals can be assessed through results. What is a key way for a Product Owner to apply validated learning?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Release an Increment to the market to learn about the business assumptions built into the product.

    Validated learning occurs when assumptions are tested against real market results, typically by releasing an Increment to users. Internal planning or acceptance activities alone do not validate value because they lack external, empirical market feedback.

  410. Question 410 of 554What are the Scrum artifacts?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The product backlog, the sprint backlog, the increment

    The three official Scrum artifacts are the Product Backlog, the Sprint Backlog, and the Increment. Remember that the Definition of Done is a crucial commitment, not an artifact, and do not mistake the official events for artifacts.

  411. Question 411 of 554For a Scrum Team, the Sprint Planning meetings are always going beyond the timebox. What could the likely causes be? (choose all that apply)

    Select 2 answers.

    Show answer & explanation

    Correct answer: C. The Developers are trying to get a perfect and detailed Sprint plan. · D. The Team didn't invest enough in Product Backlog refinement

    Sprint Planning often exceeds its timebox when Developers attempt to create a perfectly detailed plan rather than just enough. Another major cause is failing to invest enough in Product Backlog refinement, leaving items unclear and unestimated before planning.

  412. Question 412 of 554You are a Product Owner of a Scrum Team. In the middle of the Sprint, you find out that the Developers will not be able to finish the Sprint Backlog by the end of the Sprint. What is the most appropriate response? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Work with the Developers to re-work selected Product Backlog items in the Sprint Backlog in order to meet the Sprint Goal.

    The Product Owner should collaborate with the Developers to rework the Sprint Backlog so they can still meet the Sprint Goal. The scope can be renegotiated, but extending a Sprint is never allowed, and forcing overtime violates Scrum's commitment to sustainable pace.

  413. Question 413 of 554What would a Product Owner typically do during a Sprint? (choose all that apply)

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. Work with the Developers on refining the Product Backlog. · F. Collaborate with stakeholders, users, customers, and people in your organization.

    During a Sprint, the Product Owner collaborates with stakeholders and works with Developers on Product Backlog refinement. They do not manage daily tasks, estimate items for committees, or enforce rigid scope locks; they ensure Product Backlog items are clearly understood.

  414. Question 414 of 554Only the Developers may cancel a sprint.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Only the Product Owner has the authority to cancel a Sprint, typically when the Sprint Goal becomes obsolete. Developers cannot cancel a Sprint, but they can consult with the Product Owner if they realize the goal cannot be achieved.

  415. Question 415 of 554What is the responsibility of the Product Owner during the Sprint Retrospective?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Participating as a member of the Scrum Team

    The Product Owner actively participates as a Scrum Team member during the Sprint Retrospective to inspect and adapt processes. The goal is team improvement, not managing the team or merely describing backlog items, ensuring shared accountability for Scrum implementation.

  416. Question 416 of 554What best describes the Product Backlog? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. A living artifact of product requirements evolves and exists as long as the product exists.

    The Product Backlog is a living artifact that evolves as long as the product exists. It is never a finalized or approved list of requirements. Avoid traditional project management terms; the backlog constantly adapts to incorporate newly discovered information.

  417. Question 417 of 554What pre-conditions must be fulfilled in order to allow Sprint Planning to begin?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. There are no such pre-conditions

    There are no formal pre-conditions required to begin Sprint Planning, as it is simply the start of the Sprint. While having refined backlog items is helpful, Scrum explicitly avoids mandatory readiness gates. The team collaborates during the event.

  418. Question 418 of 554Which of the following is a 'FALSE' statement? Select an answer:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Scrum values low visibility and high customer involvement.

    It is false to claim Scrum values low visibility. The framework relies entirely on high visibility and transparency to enable proper inspection and adaptation. Watch for absolute or contradictory statements regarding core pillars when eliminating distractors.

  419. Question 419 of 554Only the Developers may attend the Daily Scrum.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Anyone may attend the Daily Scrum, but only the Developers actively participate. Distinguish between merely attending as an observer and actively contributing. The Scrum Master ensures outsiders do not disrupt the Developers during this daily event.

  420. Question 420 of 554Who is responsible for removing impediments during a project?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. Scrum Master

    The Scrum Master is accountable for removing impediments and serving the team to ensure smooth progress. A key exam cue is to avoid traditional roles like Project Lead, as Scrum recognizes no such title.

  421. Question 421 of 554Which of the following statements are true about the Scrum Master's accountability?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Master helps those outside the Scrum Team understand which interactions are helpful and teaches the Developers to keep the Scrum meetings to within the timebox.

    The Scrum Master serves the organization by facilitating interactions and coaching timeboxes. A key distractor has the Scrum Master assigning tasks, which violates self-management.

  422. Question 422 of 554Several Sprints into a project, a client is complaining to the Product Owner about the poor performance of the product. As a Scrum Master, how can you help the Product Owner?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Coach the Product Owner on effective ways to communicate this concern to the Developers and encourage the Product Owner to add the performance issue to the Product Backlog.

    The Scrum Master serves the Product Owner by coaching them on managing the Product Backlog and facilitating collaboration. Avoid taking over the problem, and instead encourage direct communication to add concerns to the backlog.

  423. Question 423 of 554James and Bob are Developers on a Scrum Team. They have a disagreement about how to implement a package tracking feature they are working on in the current sprint. The end result of each method is the same; It is only the process to implement that is different. What is the best way for them to handle their disagreement?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Discuss each option with the other members of the Scrum Team and gain their input; if necessary each team member can vote on what they believe to be the best course of action

    Developers are self-managing and must resolve their own technical disagreements internally. A practical cue is to reject options asking external roles like the Product Owner or Scrum Master to dictate technical solutions.

  424. Question 424 of 554The duration (length) of Sprint is decided by:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Scrum Team

    The entire Scrum Team collaboratively decides the maximum duration of a Sprint, ensuring it balances risk and complexity while remaining consistent. Avoid assuming the Scrum Master dictates timeboxes, as self-management governs structural decisions.

  425. Question 425 of 554How important is it for a Product Owner to order Product Backlog items by value points?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. It is a good practice, keeping in mind that market reception is the best measure of value.

    Assigning value points is a useful practice for ordering work, but actual value is only confirmed by real market reception. Remember that empirical process control means you must validate predicted value through actual product increments.

  426. Question 426 of 554Burn-down charts are the only recognized way in Scrum to track progress.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Scrum does not mandate any specific tracking tool, leaving the choice to the Developers based on what works best for them. Do not confuse common agile practices with mandatory Scrum rules, as burn-downs are merely optional.

  427. Question 427 of 554Which of the following is NOT correct about the Product Owner's accountability?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Participates in the Daily Scrum meeting

    Only the Developers actively participate in the Daily Scrum, making the third option the incorrect statement about Product Owner accountabilities. While the Product Owner manages the backlog and maximizes value, they do not attend this specific daily inspection.

  428. Question 428 of 554The Product Backlog and the Sprint Backlog are two names for the exact same backlog.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The Product Backlog and Sprint Backlog are distinct artifacts with different purposes. The Product Backlog outlines all desired product features, while the Sprint Backlog contains only the work selected for the current Sprint.

  429. Question 429 of 554Which accountability would know the most about the progress toward a business objective and be able to explain clearly the alternatives?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Owner

    The Product Owner is accountable for maximizing product value and managing the Product Backlog. Therefore, they track business objectives and clearly communicate trade-offs. Developers focus on technical progress, while the Scrum Master focuses on team effectiveness.

  430. Question 430 of 554As a Product Owner, John is encountering challenges with Developers not completing the selected items for the Sprint. What steps should John take to support the Developers in meeting the Sprint Goal?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. John should work more closely with the Scrum Team; items should not be added to the Sprint Backlog by the Product Owner. Developers must choose the items and commit to completing them within the Sprint

    The Developers self-manage and select their own work for the Sprint Backlog to foster commitment. John should collaborate closely to clarify items rather than forcing scope or pushing for overtime. The Scrum Master can help resolve underlying impediments.

  431. Question 431 of 554Developers maintain a Sprint burndown to track estimated remaining work. In the middle of the Sprint, the burndown graph shows an upward spike. This indicates:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers added new work

    An upward spike on a burndown chart means the total estimated remaining work has increased. This happens when Developers discover new tasks or realize work is more complex than initially thought. The Product Owner cannot unilaterally add items mid-Sprint.

  432. Question 432 of 554What can you take into consideration when ordering items in the Product Backlog? (choose the best answers)

    Select 3 answers.

    Show answer & explanation

    Correct answer: D. The dependencies between Product Backlog items. · E. The value of Product Backlog items. · F. The dependencies to other products.

    The Product Owner orders the Product Backlog to maximize value, which requires considering dependencies and value. Tooling or the Scrum Master's availability does not directly dictate the priority order of the Product Backlog items.

  433. Question 433 of 554On average, items on the Sprint Backlog tend to be:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Smaller than those on the Product Backlog

    Sprint Backlog items are smaller because they must be small enough to be completed within a single Sprint. A practical exam cue is that Product Backlog refinement breaks down large items so they fit into the upcoming Sprint.

  434. Question 434 of 554When is user acceptance testing done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. During the Sprint

    All work, including user acceptance testing, must be completed during the Sprint to create a Done Increment. Remember that hardening Sprints and release phases are not Scrum concepts and violate the rule of a potentially releasable Increment.

  435. Question 435 of 554What is the accountability of the Scrum Master in the Daily Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Scrum Master does not need to attend the Daily Scrum, they only need to make sure the Daily Scrum is occurring

    The Daily Scrum is strictly for the Developers to inspect progress and adapt their plan. The Scrum Master ensures the event happens but does not need to attend or lead it. Status updates fail because the meeting is about alignment, not reporting.

  436. Question 436 of 554The three questions must always be answered during the Daily Scrum.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The three specific questions are no longer mandated in the current Scrum Guide. Developers simply need to inspect progress toward the Sprint Goal and adapt their plan. Choosing true fails because the team can structure the meeting however they see fit.

  437. Question 437 of 554What should happen to the "Done" Product Backlog items when the Sprint is cancelled?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. They will be reviewed, and if they are potentially releasable, the Product Owner typically accepts them.

    When a Sprint is cancelled, completed work is reviewed for potential release. Because these items meet the Definition of Done, the Product Owner typically accepts them. Moving them back to the Product Backlog fails because done work is usable.

  438. Question 438 of 554In the middle of a Sprint, Developers identify a defect. Initially, they were not sure about the cause of the defect, and hence they involved the P.O. to discuss. After discussing, both the Product Owner and the Developers agreed that the defect is indeed a clear gap in the feature being developed in their Sprint and not a new requirement. The defect should be:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Fixed in the current Sprint

    Since the Developers and Product Owner agree this is a clear gap in the current feature, fixing it aligns with meeting the Sprint Goal. Deferring it fails because leaving a known defect violates the Definition of Done and compromises Increment quality.

  439. Question 439 of 554The way the Developers of a Scrum Team approach the Sprint Goal during the Daily Scrum changes if they are using Kanban.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Using Kanban with Scrum does not change how the Daily Scrum operates or how the Sprint Goal is approached. Kanban simply enhances flow and transparency. Choosing true fails because Kanban does not alter core Scrum events or accountabilities.

  440. Question 440 of 554Stakeholders should hold their feedback until the Sprint Review occurs.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    Feedback can be provided at any time, fostering continuous inspection and rapid adaptation. Do not assume stakeholders must wait for the Sprint Review, as ongoing dialogue helps the Scrum Team quickly adapt to new market needs.

  441. Question 441 of 554Must the Product Owner be present at the Sprint Retrospective?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. It is mandatory. The Sprint Retrospective is an opportunity for the Scrum Team to assess its performance and improve itself.

    The entire Scrum Team, including the Product Owner, must attend the Sprint Retrospective to inspect and adapt their processes. Avoid choosing options that restrict this event to only the Developers, as continuous improvement involves the whole team.

  442. Question 442 of 554The Product Owner manages the Product Backlog. Who is accountable for estimating the effort to complete the Product Backlog items?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Developers. As a collective, they have a complete view of the work needed to transform Product Backlog items into Increments of product.

    The Developers are accountable for estimating the effort because they are the ones doing the actual work to create the Increment. The Product Owner might influence ordering, but they do not assign or dictate estimates to the team.

  443. Question 443 of 554How should a Scrum Master coordinate the work when more than one Scrum Team is working on one product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Teach them that it's their responsibility to coordinate with the other teams to integrate and create a shippable product Increment at the end of every Sprint.

    The Scrum Master should teach the teams to self-manage and coordinate their own integration efforts to create a unified Increment. Avoid options where the Scrum Master directly manages dependencies or merges teams, as this violates Scrum's principles of empowerment.

  444. Question 444 of 554A manager from accounting has an urgent task for one of the Developers on a Scrum Team. He says the VP of product development has ordered the Developers to complete this task for him. What should the Developers do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Developers member should notify the Product Owner so that he or she can work with the manager

    Developers should notify the Product Owner, who has final say over what is worked on to maximize value. No one outside the Scrum Team can force changes to the Sprint Backlog without Product Owner collaboration.

  445. Question 445 of 554During the Sprint, you receive a request from an influential stakeholder to add two new features needed for the product. As a Product Owner, what actions would be appropriate? (choose the best two answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. You can add them to the Product Backlog. · C. If the items are urgent and important, you can ask the Developers if they can consider whether or not to add the features to the current Sprint.

    The Product Owner can add new requirements to the Product Backlog at any time. If urgent, they may also ask the Developers if they can accommodate the work in the current Sprint.

  446. Question 446 of 554What are the limitations on the decisions of the Product Owner for the Product Backlog? (choose the best answer)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. There are no limitations. The Product Backlog is fully owned by the Product Owner and the entire organization must respect a Product Owner's decisions.

    The Product Owner owns the Product Backlog and the organization must respect their decisions. Distractors about definitions of ready or approvals conflict with the Product Owner's ultimate authority.

  447. Question 447 of 554Rebecca, a scrum master, has recognized that Ricky, a developer, is having issues getting along with the other members of the team. The other developers of the Scrum Team have complained about Ricky frequently and often cite him as one reason they struggle to complete some work on time. After evaluating the situation, it is clear to Rebecca that Ricky has the skill needed to do the work but not the emotional intelligence required to work well with others. What should Rebecca do about the situation?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Rebecca should make every effort to help coach Ricky and the rest of the team to work more cohesively; if problems still persist it may be time for the Scrum Team to consider replacing Ricky with someone who is a better fit

    The Scrum Master coaches the team but the self-managing Developers ultimately decide their membership. Remember the Scrum Master leads and coaches rather than unilaterally firing team members.

  448. Question 448 of 554What is the most appropriate action for the Scrum Master to take if the Product Owner is having difficulties managing the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize the flow of value.

    The Scrum Master serves the Product Owner by helping them maximize value through effective Product Backlog ordering. Avoid options that suggest delaying Sprints or shifting ordering responsibilities to Developers, as these violate core principles.

  449. Question 449 of 554How should items in the Product Backlog be ordered?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Prioritized by business importance first. The items that result in biggest ROI, must be prioritized first

    The Product Owner orders the Product Backlog by maximizing value and ROI. Distractors that suggest chronological or alphabetical ordering fail to understand that backlog ordering is strictly about optimizing the flow of value.

  450. Question 450 of 554Who is responsible for creating functional documentation when it's included in the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Developers

    The Developers are responsible for creating any work required to meet the Definition of Done, including functional documentation. The entire Scrum Team collaborates to define the standard, but only the Developers execute the actual work to create a Done Increment.

  451. Question 451 of 554What is the cone of uncertainty?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. In the early stages of a project, very little is known about the product; as time goes knowledge of the product should increase – creating a cone shape over time

    The cone of uncertainty describes how project uncertainty is highest at the beginning and decreases as more knowledge is gained over time. Do not confuse this concept with a specific tracking chart like a burn-down, which only measures remaining work.

  452. Question 452 of 554Which two of the following are required by Scrum? (choose the best two answers)

    Select 2 answers.

    Show answer & explanation

    Correct answer: D. Sprint Retrospectives · E. Having timeboxed events

    Scrum requires its events to be timeboxed to create predictability and focus, and Sprint Retrospectives are mandatory events. Concepts like Test-Driven Development or a Definition of Ready are complementary practices, not mandatory parts of the Scrum framework.

  453. Question 453 of 554In a Product Backlog, which items are at the top?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The highest priority items as decided by the product owner are at the top

    The Product Owner orders the Product Backlog to optimize value, placing the highest priority items at the top. Developers do not set the priority. The guide uses the term ordering rather than prioritization to encompass value, risk, and dependencies.

  454. Question 454 of 554Scrum is an Agile framework for developing complex products.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. True

    This is true because Scrum is specifically designed as a framework to manage complex product development. Remember that while Scrum is Agile, it explicitly targets complexity.

  455. Question 455 of 554Agility is enhanced by:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Continuous attention to technical excellence and design

    Continuous attention to technical excellence and good design directly enhances agility according to Agile principles. Be careful of options promoting rigid planning or fast paces without quality.

  456. Question 456 of 554The Product Owner wants to get some additional product backlog items added to the current Sprint Backlog. Sprint planning has already happened, what should the Product Owner do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Owner should hold a separate meeting with the developers and discuss the options of adding some additional items; the developers can consider the possibility and may be able to accommodate the additional work

    The Product Owner and Developers should negotiate any changes to the Sprint Backlog scope outside of the Daily Scrum. Remember that only the Developers can pull new work into a Sprint, and hijacking the Daily Scrum violates its strict timebox.

  457. Question 457 of 554In a two-week-long Sprint, how long should the Sprint Planning meeting be?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Never longer than 8 hours. Usually about 4 hours for a two-week sprint.

    Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint, so a two-week Sprint is usually around four hours. While meetings should be as short as effective, saying they can take unlimited time ignores Scrum timeboxes.

  458. Question 458 of 554Besides user stories, what helps a product team understand requirements?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. all of these choices

    Acceptance criteria, story maps, and process models all help a team fully grasp requirements. While these complementary practices are common, remember that the Scrum Guide formally requires only Product Backlog items and their descriptions.

  459. Question 459 of 554Which of the following statements are false? (choose all that apply)

    Select 2 answers.

    Show answer & explanation

    Correct answer: B. after the Sprint Planning, a Sprint cannot proceed without a complete architecture · C. after the Sprint Planning, a Sprint cannot proceed without complete requirement specifications

    Scrum uses an empirical approach, meaning Sprints do not require complete upfront architecture or detailed requirement specifications. A Sprint can proceed without a complete Sprint Backlog, but it absolutely requires a Sprint Goal to provide direction.

  460. Question 460 of 554During the Sprint…

    Select 2 answers.

    Show answer & explanation

    Correct answer: A. Any adjustments that could compromise the Sprint Goal are avoided · C. The standard of quality is maintained

    During the Sprint, quality must not decrease and changes that endanger the Sprint Goal are avoided. Clarifying scope is done with the Product Owner, not the Scrum Master, so be careful with distractors involving the wrong accountabilities.

  461. Question 461 of 554In the middle of the Sprint, a team member was required by another Department Manager to support an important task outside the Sprint work. What is recommended for the team member to do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The team member should politely decline and explain to the manager about his ownership and accountability for the Scrum Team

    Developers self-manage their work and must protect the Sprint Goal from external disruptions. For the exam, always prioritize self-organization and defer external new work additions to the Product Owner.

  462. Question 462 of 554All of the following are examples of valid SCRUM rules EXCEPT:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Scrum Master can add/remove items from a Sprint.

    A Scrum Master cannot add or remove items from the Sprint Backlog because Developers own it. Watch for options that incorrectly assign Sprint Backlog modification authority to the Scrum Master or Product Owner.

  463. Question 463 of 554The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an estimated date of release to production (when).

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. False

    The answer is false because the Sprint Backlog includes an actionable plan for delivering the Increment, not a release date. Remember the three parts of the Sprint Backlog for the exam: the why, the what, and the how.

  464. Question 464 of 554Antonio is a Product Owner for a Scrum Team. A three-week-long Sprint began four days ago and the Scrum Team is well on their way towards meeting the Sprint Goal they set. Antonio has just learned that four of the five features chosen for the current Sprint are features the customer no longer wishes to implement. What should Antonio do in this situation?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Antonio should consider cancelling the current Sprint and begin a new Sprint immediately; the one item that is not obsolete can be placed back in the Product Backlog and reevaluated for another Sprint

    Only a Product Owner can cancel a Sprint early, and only if the Sprint Goal becomes obsolete. Since four of five features are cancelled, the original goal is likely invalid; however, Antonio must collaborate with the team before making this drastic decision.

  465. Question 465 of 554During the Daily Scrum, a team member says he does not know when his task will be complete.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Developers should collaborate to plan alternative steps such as pairing with someone else, etc. to eliminate the risk of not meeting the Sprint Goal

    Developers must collaborate to adjust their plan and protect the Sprint Goal. The Daily Scrum is for inspection and adaptation, not status reporting or management intervention.

  466. Question 466 of 554You are the lead for a project ABC and you receive communication from the client that the work units delivered by the team are not satisfactory. What is the BEST method to address this issue?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Setup a meeting with the team to gain an understanding of the exact situation and devise a strategy to meet the acceptance criteria.

    Collaborating with the team to understand the exact situation and meet acceptance criteria aligns with agile principles of transparency. Options suggesting formal notices or defending the team without investigation fail to support continuous improvement.

  467. Question 467 of 554Which topic should NOT be discussed at the Sprint Review?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Coding best practices

    The Sprint Review focuses on inspecting the Increment and collaboratively adapting future plans, not internal coding practices. While quality is vital, discussing technical best practices is appropriate for the Sprint Retrospective or internal Development discussions, not the Review.

  468. Question 468 of 554In an Agile environment, which accountability BEST describes the 'Voice of the Customer'?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Product Owner

    The Product Owner represents the stakeholders and acts as the voice of the customer to maximize product value. Other roles like the Business Analyst are not formal accountabilities in Scrum and do not hold this decision authority.

  469. Question 469 of 554In addition to leadership, communication, analysis, and decision-making skills, a Product Owner needs to be skilled at:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. relationship building

    A Product Owner must excel at relationship building to effectively collaborate with stakeholders and the Scrum Team. Technical skills like programming or database management are not required, as the Product Owner focuses on maximizing product value.

  470. Question 470 of 554A group of stakeholders wants to attend the Daily Scrum. How should the Scrum Master handle the situation?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Instruct the stakeholders to remain quiet and refrain from asking questions or making comments. They are allowed to listen in for the sake of transparency, but the meeting is intended for the developers.

    The Daily Scrum is specifically for Developers, but bystanders may observe silently. Complete exclusion is too extreme an option, so ensure you pick the choice that protects the event without entirely banning observation.

  471. Question 471 of 554All of the following are key ingredients of defining a Scrum method EXCEPT:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. Responsibilities

    Scrum is defined by accountabilities, events, and artifacts rather than generic responsibilities. The 2020 update specifically replaced traditional roles with specific accountabilities, making that the clear exception here.

  472. Question 472 of 554Ideally, the Daily Scrum should be a:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Short, focused 15-minute event

    The Daily Scrum is intentionally designed to be a focused 15-minute event for synchronization. The physical location or posture of participants is entirely irrelevant, so focus strictly on the timebox.

  473. Question 473 of 554You are the Scrum Master for a product development project and one of your goals is to ensure that the team performs at its highest level of productivity. What is the BEST way to realize this objective?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. By facilitating daily scrum meetings and removing impediments

    Facilitating the Daily Scrum and removing impediments is a core Scrum Master duty. Ensure you filter out distractors proposing weekly Scrum events or ignoring obstacles, as these violate foundational Scrum rules.

  474. Question 474 of 554Who creates the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The development organization (or the Scrum Team if none is available from the development organization)

    If it exists, the development organization sets the minimum standard for the Definition of Done. Otherwise, the Scrum Team must create it. Remember that the Product Owner or Scrum Master alone cannot dictate this standard; it requires broader organizational or team consensus.

  475. Question 475 of 554If a Developer becomes an impediment, can the project manager remove them from the team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. There is no project manager within the Scrum Team. If a project manager works with a Scrum Team, he does not have the authority to remove a Developer as the Scrum Team is self-managed.

    There is no project manager role in Scrum, and Scrum Teams are self-managing. While external managers handle personnel, the team decides how to accomplish work without outside interference.

  476. Question 476 of 554Transparency and trust in an Agile project is built by:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. Maintaining highly visible information radiators about the progress and performance of the teams

    Using highly visible information radiators ensures project progress and performance are open to all stakeholders, building trust through transparency. Options focusing on socializing or exposing all individual work misrepresent agile principles.

  477. Question 477 of 554You are assigned to conduct a feasibility study on a complicated product development project to see if it can be delivered in an Agile environment. Which approach would you adopt to maximize the business value?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. Empirical

    An empirical approach relies on transparency, inspection, and adaptation, making it ideal for complex Agile projects. Theoretical or hypothetical approaches lack real-world validation, which is required to navigate complex project uncertainty properly.

  478. Question 478 of 554In an Agile project, the customer is kept satisfied by:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Continuous delivery of a valuable product

    Agile principles prioritize customer satisfaction through the continuous delivery of valuable software. Options suggesting heavy documentation or late delivery fail because empirical approaches rely heavily on early and frequent increments.

  479. Question 479 of 554During the Daily Scrum, the Scrum Master goes around the room pointing to each Developer and asks them for their work done the day before. Each team member gives their update and the Scrum Master goes to the next person. The Daily Scrum goes smoothly and everyone is happy with this way of working. What is the Scrum Master doing wrong?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Scrum Master should not be directly involved in the Daily Scrum – his only duty regarding the Daily Scrum is to ensure the Developers are having the Daily Scrum and that they keep it within a timebox of 15 minutes

    The Scrum Master should not run the Daily Scrum as a status report, because Developers fully own and conduct this event. Remember that facilitating Scrum events does not mean the Scrum Master actively participates in them.

  480. Question 480 of 554Sprint Retrospectives focus on:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. What is working well and what is not working well

    The Sprint Retrospective focuses on inspecting how the last Sprint went regarding individuals, interactions, processes, tools, and the Definition of Done. Exam cue: if an option discusses what was delivered or creating backlogs, it describes the Sprint Review or Planning, not the Retrospective.

  481. Question 481 of 554What does a Product Owner focus on?A. The product as a whole B. The next release C. The next sprint D. All of these choices

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. all of these choices

    A Product Owner must focus on the product as a whole, the next release, and the next Sprint to effectively maximize value. For the exam, remember that the Product Owner balances both the overarching product strategy and immediate delivery goals.

  482. Question 482 of 554Without product ownership, the team may build products that are _____.

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. all of these answers

    The Product Owner is accountable for maximizing the value of the product resulting from the work of the Developers. Without clear product ownership, teams risk delivering products that are not valuable, useful, or what customers actually need.

  483. Question 483 of 554John is working on a product development project in an Agile environment and discusses with his team ways to improve and manage stakeholder expectations. Which of the following best describes his efforts in achieving this objective?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Creating an environment of trust so as to decrease the impediments among stakeholders.

    Agile principles emphasize collaboration and building trust to manage stakeholder expectations effectively. For the exam, dismiss distractors that suggest excluding less influential stakeholders or micromanaging team members, as these violate Agile values.

  484. Question 484 of 554You are entrusted with the responsibility of forming an Agile team to add business value to the project. What key competencies would you look for in creating the team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. A blend of interpersonal and technical skills

    Agile teams require a blend of interpersonal and technical skills to collaborate and deliver successfully. The placeholder option is a clear formatting error that should be ignored during practice.

  485. Question 485 of 554What is one way the Scrum Master serves the organization?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. By planning and advising Scrum implementations within the organization

    Planning and advising Scrum implementations within the organization is a direct responsibility of the Scrum Master serving the organization. The other three options describe how the Scrum Master serves the Developers or the Product Owner, so watch those boundaries.

  486. Question 486 of 554What happens when the Product Backlog is not clear enough at Sprint Planning?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Nothing; the Sprint would be planned anyway.

    Sprint Planning proceeds as scheduled, because timeboxes are fixed events in Scrum. The team simply collaborates to clarify uncertainties during refinement and implementation, avoiding any artificial delays.

  487. Question 487 of 554What should happen when a Sprint is cancelled?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Incomplete items should be placed back into the Product Backlog; completed items should be reviewed and considered for possible release

    When a Sprint is canceled, any incomplete items return to the Product Backlog for future ordering. Completed work meeting the Definition of Done is reviewed and may be released to avoid wasting delivered value.

  488. Question 488 of 554What type of test should be done during the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Every type of test

    Developers must perform every type of test during the Sprint to ensure the Increment is usable and meets the Definition of Done. Excluding any testing phase risks delivering an unstable product at the end of the Sprint.

  489. Question 489 of 554When a product grows, it is quite possible that the Product Owner will get help from other Product Managers and others in the organization who interact regarding the customer facing activities and knowledge of the product marketplace. Is it a good idea for the Product Owner to proxy or outsource some of their duties to these people?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. No

    The Product Owner may delegate actual work but remains accountable and should never become a proxy or outsource final decisions. For the exam, remember that accountability for maximizing value cannot be transferred to a proxy role.

  490. Question 490 of 554Who is responsible for all estimates in the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. The Developers after clarifying requirements with the Product Owner.

    The people who will perform the work finalize all estimates. A strong practical cue is that the Product Owner may clarify requirements and discuss trade offs, but they never dictate the actual effort numbers.

  491. Question 491 of 554What is an increment?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. It is the moment a Product Backlog item meets the Definition of Done

    An increment is born the moment a Product Backlog item meets the Definition of Done. Avoid options claiming prior work counts even if it fails to meet this definition, because undone work never creates a usable increment.

  492. Question 492 of 554What should Developers be able to explain at the end of Sprint Planning?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. How they intend to complete the items selected for the sprint

    By the end of Sprint Planning, Developers must be able to explain how they intend to deliver the selected items. The event focuses on creating a actionable plan for the upcoming Sprint rather than addressing future improvements.

  493. Question 493 of 554When is it time to integrate the code?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Frequently, during the Sprint

    Code should be integrated frequently during the Sprint to ensure stability and early conflict resolution. Waiting until the end of a Sprint or release creates dangerous bottlenecks that contradict the empirical nature of Scrum.

  494. Question 494 of 554What is one way that the Scrum Master serves the Product Owner?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. By helping the Scrum Team understand the need for clear and concise Product Backlog items

    The Scrum Master serves the Product Owner by helping the team understand the need for clear Product Backlog items. The other options describe serving the broader organization or Developers rather than directly serving the owner.

  495. Question 495 of 554Who identifies the Key Stakeholders for the Product? (choose the best option)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. The Product Owner

    The Product Owner is responsible for maximizing value and identifying key stakeholders to engage throughout the development effort. While others may assist, remember that the Product Owner holds the final accountability for stakeholder mapping and product value decisions on the exam.

  496. Question 496 of 554The purpose of the Sprint Review is…

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. To inspect the Increment and adapt the Product Backlog

    The primary purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. Avoid options that frame it as a simple status update or just a showcase of completed work, because adapting the Product Backlog is essential.

  497. Question 497 of 554Who creates the Sprint Goal?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Team

    The entire Scrum Team collaboratively crafts the Sprint Goal during Sprint Planning to provide a shared objective. Beware of distractors assigning this accountability solely to the Product Owner or Developers, as the whole team must agree on the direction.

  498. Question 498 of 554Which statement is TRUE about the Daily Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. It is time boxed to 15 minutes.

    The Daily Scrum is strictly time-boxed to 15 minutes to inspect progress toward the Sprint Goal. While resolving impediments is crucial, it generally happens after the time box ends, making the strict 15-minute limit the only definitively true statement here.

  499. Question 499 of 554How long should a Sprint last?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. A time-box of one month or less

    A Sprint is a fixed-length event of one month or less, establishing a consistent cadence for inspection and adaptation. Sprints are strictly time-boxed rather than left open-ended, ensuring predictability and regular opportunities to deliver value.

  500. Question 500 of 554During which Scrum event should the Sprint Goal be crafted?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. The Sprint Planning

    The Sprint Goal is crafted during Sprint Planning to align the Scrum Team on exactly why the upcoming Sprint is valuable. Waiting until the Daily Scrum or defining it during the Sprint Review would defeat its purpose of guiding daily work.

  501. Question 501 of 554In the middle of the Sprint, the customer decides that there are two new features she wants. The Product Owner could: (choose the best option)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Add these features to the Product Backlog and evaluate their business value.

    The Product Owner should add new customer requests to the Product Backlog to properly evaluate and prioritize their business value. Adding work mid-Sprint without the Developers' approval disrupts the current Sprint Goal and scope.

  502. Question 502 of 554What is Product Backlog refinement?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. An ongoing process to add estimates, details, and order to the items in the product backlog

    Product Backlog refinement is the ongoing act of adding detail, estimates, and size to items. For the exam, remember this is not a formal Scrum event tied to a specific timebox but rather a continuous activity that ensures upcoming work is clearly understood.

  503. Question 503 of 554What should be considered when ordering the Product Backlog items?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. The Product Owner should consider whatever is needed to help the product achieve its goals and maximum value

    The Product Owner orders Product Backlog items by whatever factors are necessary to maximize value and achieve product goals. A common exam trap is limiting this decision to only risk and value, but dependencies, stakeholder needs, and market changes also apply.

  504. Question 504 of 554What is the minimum plan necessary to start a Scrum project? (choose the best option)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. A Product Goal and a Product Backlog.

    A Product Goal and a Product Backlog are the essential minimum requirements to begin Scrum. Beware of options mentioning release plans; the current Scrum Guide focuses entirely on product goals and backlog items rather than traditional project release planning.

  505. Question 505 of 554Why should a Scrum Team member be cross-functional?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The Scrum Team collectively should have all the skills needed to complete an increment; this can include cross-functional team members and sometimes specialists

    The entire Scrum Team must possess all the skills necessary to create a valuable increment each Sprint. While specialists are welcome, the collective team needs cross-functionality. The framework emphasizes team capability over individual specialization.

  506. Question 506 of 554What is the Product Owner accountable for in Scrum? (choose the best option)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Creating and sustaining a Product Backlog that maximizes value and represents the needs of the stakeholders.

    The Product Owner is accountable for creating and sustaining a Product Backlog that maximizes value and represents stakeholder needs. The Product Owner is not solely responsible for writing User Stories or handing refined items to Developers.

  507. Question 507 of 554The Sprint Backlog must be detailed enough so that…

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Changes in progress can be understood in the Daily Scrum

    The Sprint Backlog must be detailed enough so that changes in progress can be understood in the Daily Scrum. Avoid options claiming every task must be identified upfront or that stakeholders monitor daily tasks.

  508. Question 508 of 554Who is accountable for communicating the Product Vision to the Scrum Team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner

    The Product Owner is accountable for defining and communicating the Product Vision to the Scrum Team. The Product Manager is a distractor because that is not an official Scrum accountability on the Scrum Team.

  509. Question 509 of 554Which of the following may change during the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Product Backlog

    The Product Backlog is dynamic and can change at any time as new requirements emerge or priorities shift. Quality levels and the Sprint Goal must remain fixed during a Sprint to maintain focus and avoid scope creep.

  510. Question 510 of 554Which statement is correct when multiple Scrum Teams are working on the same product?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. There's only one Product Backlog for all of them

    Scrum requires exactly one Product Backlog for a product, even when multiple teams do the work, ensuring absolute transparency and clear prioritization. Multiple backlogs would fragment focus and make ordering difficult.

  511. Question 511 of 554The result of the Sprint Review is…

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. A revised Product Backlog that defines the probable Product Backlog items for the next Sprint

    A revised Product Backlog is a key outcome of the Sprint Review, serving as the basis for the next Sprint Planning. The event is a collaborative discussion rather than a formal presentation or acceptance meeting.

  512. Question 512 of 554What should the Sprint Backlog contain?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. It should contain a Sprint Goal, items from the Product Backlog chosen for the Sprint and an actionable plan on how the Developers intend to deliver them

    The Sprint Backlog explicitly contains the Sprint Goal, selected Product Backlog items, and an actionable plan for delivery. The actionable plan is created by the Developers to provide focus without locking in all details upfront.

  513. Question 513 of 554What is the logic behind which parameter is chosen to order the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Whatever is deemed appropriate by the Product Owner

    The Product Owner has full authority to order the Product Backlog however they deem appropriate to maximize value. Watch out for options that force a single factor like individual value, as the owner weighs multiple priorities.

  514. Question 514 of 554After a Sprint Review, the Product Owner deems the Product has come to the end of its life and the Product Backlog can be closed. The next immediate step is:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Communicate the Scrum Team's availability to stakeholders

    When a product ends, the immediate step is communicating team availability to stakeholders. A Retrospective is technically ambiguous here because if a Sprint is still active, standard Scrum dictates finishing its events before disbanding.

  515. Question 515 of 554The Sprint Review is just a demo of the Product Backlog items completed during a Sprint. Do you agree? (choose the best option)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. No, the Sprint Review contains many more activities.

    A Sprint Review is a collaborative working session, not just a demo. Expect exam questions to test the distinction between a status presentation and the actual purpose of the event, which is to inspect the Increment and adapt the Product Backlog together with stakeholders.

  516. Question 516 of 554How complete should the Sprint Backlog be at the end of the Sprint Planning meeting?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Complete enough to show the work for the next few days.

    The Sprint Backlog only needs enough detail and planning to show what the Developers will work on for the next few days. Avoid picking options suggesting the work is fully mapped out at the start, because the Sprint Backlog emerges as the Developers learn more.

  517. Question 517 of 554Who has final say over changes to the Sprint Backlog during a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Developers

    Developers have the final say over changes to the Sprint Backlog because they self-manage their work. A strong exam cue is remembering that the Product Owner negotiates scope, but the Developers ultimately own the Sprint Backlog mechanics during the Sprint.

  518. Question 518 of 554Every Developer must answer the three questions during the Daily Scrum:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: E. False

    The Daily Scrum focuses on inspecting progress toward the Sprint Goal, not on rigidly answering three specific questions. The three questions were removed as a mandatory format, so look out for exam options implying they are strictly required.

  519. Question 519 of 554Which of the following statements best describes a Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. A Sprint is a pre-specified amount of time in which the developers work at sustain pace to complete a chosen set of work.

    A Sprint is a fixed time-box where Developers work at a sustainable pace to complete a chosen set of work. The best answer rejects the idea of pulling random items continuously and emphasizes a cohesive Sprint Goal instead of just a list of tasks.

  520. Question 520 of 554When several Scrum Teams collaborate on a single product, how many Product Backlogs should there be?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. One

    A core rule of Scrum is that one product has exactly one Product Backlog to ensure a unified priority and vision. Having multiple backlogs for a single product would create conflicting priorities and duplicate work across the collaborating teams.

  521. Question 521 of 554Which of the following is the most important opportunity for capturing lessons learned?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Sprint Retrospective

    The Sprint Retrospective is the dedicated event at the end of each Sprint for the Scrum Team to inspect itself and create a plan for improvements. Other events focus on the product or the immediate daily plan rather than process improvement.

  522. Question 522 of 554How should the Product Backlog be ordered?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The most valuable and most refined items should be at the top

    The Product Owner orders the Product Backlog to maximize value, typically placing the most valuable and refined items at the top. Doing so provides clear direction to the Developers and ensures the highest priority work is tackled first.

  523. Question 523 of 554In the first few Sprints, the Scrum Team is expected to focus on:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Delivering a usable and potentially releasable product increment

    In every Sprint, including the first few, the primary focus must be delivering a usable, potentially releasable product Increment. Upfront infrastructure setup or baselining a traditional project plan contradicts Scrum's emphasis on empirical progress.

  524. Question 524 of 554A Scrum Team uses 2-week Sprints and timeboxes their Sprint Planning to 6 hours. Does this break the rules of Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. No

    Shortening the maximum timebox does not break Scrum rules, because the guide sets upper limits rather than mandatory durations. For the exam, remember that Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint and is usually shorter for shorter Sprints.

  525. Question 525 of 554The Product Owner doesn't spend enough time on the project. Which of the following options is the best response from the Scrum Master?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Train the Product Owner why it's important for her/him to spend enough time on the project

    The Scrum Master should coach the Product Owner on why their active engagement is critical for project success and value delivery. Avoiding proxy Product Owners is key; the Scrum Master acts as a servant leader and facilitator rather than escalating personnel issues to management.

  526. Question 526 of 554The Product Owner manages… (choose 1)

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Backlog

    The Product Owner is accountable for managing the Product Backlog to maximize product value. For the exam, remember that the Product Owner does not manage the Developers or the overall project but ensures backlog transparency and clear ordering.

  527. Question 527 of 554Select the true answer. During the Sprint:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. No changes are made that would endanger the Sprint Goal.

    During the Sprint, no changes are made that would endanger the Sprint Goal. Remember that while the overall scope might be negotiated with the Product Owner as learning occurs, the core Sprint Goal remains fixed to maintain focus and deliver a valuable Increment.

  528. Question 528 of 554Does Scrum have Project Managers?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. No

    Scrum does not define a project manager role. Accountability is distributed among the Developers, Product Owner, and Scrum Master. If a question mentions a project manager, treat it as a traditional management role outside the framework.

  529. Question 529 of 554Which of the following limits work in progress?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Using timeboxes

    Timeboxes limit work in progress by restricting how long a task can take, forcing the team to focus on a realistic scope. Sprint Reviews and Retrospectives are events for inspection and adaptation, not explicit work-in-progress limits.

  530. Question 530 of 554What does "Done" signify within the Definition of Done framework?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The increment built in a Sprint should be in a functional state and align with the Scrum Team's criteria for being "Done" (as per their Definition of Done)

    The Definition of Done ensures an increment is functional and meets the quality criteria set by the Scrum Team. Neither a program manager nor the Scrum Master defines it. The team owns it to guarantee transparency.

  531. Question 531 of 554The Scrum Master is accountable for…

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Ensuring Scrum is understood and enacted

    The Scrum Master is accountable for ensuring Scrum is understood and enacted. They coach the team rather than managing budgets, directing daily work, or solving every problem. Watch for traditional project manager duties as distractors.

  532. Question 532 of 554True or False: All work to be done by the Developers must ultimately originate from the Product Backlog?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. True

    Scrum dictates that all work done by Developers must originate from the Product Backlog to maintain transparency. This ensures the single source of requirements is respected. Any technical tasks needed must serve a Product Backlog item.

  533. Question 533 of 554In which situation might a Sprint be cancelled?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. When the Sprint Goal becomes obsolete

    A Sprint can only be cancelled if the Sprint Goal becomes obsolete. This decision can be made by the Product Owner, who might also consult others. An unachievable workload is managed by negotiation, not cancellation.

  534. Question 534 of 554Who should know the most about the overall Product roadmap and milestones?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. The Product Owner

    The Product Owner is responsible for maximizing product value and managing the Product Backlog, giving them the clearest view of the roadmap. Remember that Scrum replaces the traditional Project Manager with distinct accountabilities.

  535. Question 535 of 554How should multiple Scrum Teams, working on the same product, manage their Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. All Scrum Teams must share a common Definition of Done that allows all of their completed work to be integrated into a single product.

    Multiple teams building a single product must share a common Definition of Done so their combined work integrates into a cohesive increment. If they used different definitions, the integrated product would lack a consistent quality standard.

  536. Question 536 of 554Scrum is a newer way of doing things to address complex problems. It is a new way because

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. It increases the opportunity to control risk and optimize the predictability of progress

    Scrum increases the opportunity to control risk and optimize the predictability of progress through empiricism. While it offers new terminology, that is just a side effect rather than the core reason it effectively addresses complex problems.

  537. Question 537 of 554What factors might determine the optimal Sprint duration, given the importance of maintaining consistency throughout the development process?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. All of these answers are correct.

    All the listed factors correctly determine Sprint duration because Sprints must be short enough to manage risk while producing a usable Increment. Remember that a Sprint is strictly limited to a maximum of one month to effectively control risk.

  538. Question 538 of 554James is a Product Owner for a Scrum Team. The customer has expressed concerns about releasing new software after every Sprint. How should James address this situation?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. An increment only needs to be potentially releasable, James may hold back several increments and work with the customer on a release schedule that fits their needs

    An Increment must be potentially releasable, but multiple Increments can be combined and released later based on user needs. The strongest distractor incorrectly states that an actual release is strictly mandatory at the end of every single Sprint.

  539. Question 539 of 554Claire is a Scrum Master for a Scrum Team. She has received new information that may cause issues during the next Sprint. What should Claire do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. Claire should work with the Scrum Team to figure out the issues and their impact, but move forward with the next sprint using the best available information; if needed, the Developers should refrain from working on items most at risk and work on other items in the Product Backlog

    Claire should collaborate with the team to assess the issue and proceed using the best available information for the Sprint. Sprints start immediately after the previous one concludes, so avoid options that suggest delaying the next Sprint.

  540. Question 540 of 554What is the best approach for Scrum teams to produce valuable increments?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Each Scrum Team is accountable for building complete and functional increments from beginning to end.

    Scrum Teams are accountable for building complete, functional Increments from beginning to end rather than working on isolated components. The strongest distractors fail because independent layers or components disrupt integration and limit accountability.

  541. Question 541 of 554A Scrum Team is under pressure to get certain features of their product "Done" three Sprints earlier than their initial plan. In order to meet that goal, the Developers choose quicker and easier development solutions. What should the Product Owner explain to the stakeholders about the quicker and easier development solutions over the longer solutions originally planned?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. He should explain to the stakeholders that the quicker development solutions could create a technical debt that could cost more in time, effort and money in the future than the longer development solutions would

    The Product Owner must explain that choosing quicker development solutions can create technical debt that costs more time and money later. Developers are accountable for quality and should never simply ignore the long term consequences of technical compromises.

  542. Question 542 of 554Which of the following is not allowed in Scrum?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Hardening Sprints

    Hardening Sprints are not allowed because Scrum requires every Increment to be potentially shippable and meet the Definition of Done continuously. Allocating special Sprints for bug fixing or testing indicates a lack of continuous quality focus and violates core iterative delivery rules.

  543. Question 543 of 554What does the Product Owner do during the Sprint Review?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Product Owner explains to the present stakeholders what items from the product backlog were "Done" and what was not "Done" along with the entire Scrum Team

    The Product Owner explains which Product Backlog items were Done and which were not alongside the entire Scrum Team. The Sprint Review is a collaborative dialogue rather than a formal presentation, so the team works together to discuss outcomes with stakeholders.

  544. Question 544 of 554Which statement is correct when the Developers are working in the middle of the Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The scope may be clarified as more is learned.

    Scope may be clarified and renegotiated with the Product Owner as the Developers learn more during the Sprint. A Sprint Backlog is never frozen; it naturally emerges and evolves as the team uncovers new information while working toward the Sprint Goal.

  545. Question 545 of 554The Scrum Master serves the Scrum Team by:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: B. Causing the removal of impediments to the Scrum Team's progress

    The Scrum Master serves the team by causing the removal of impediments that hinder progress. The Product Owner is accountable for managing the Product Backlog and developing the Product Goal, whereas the Scrum Master focuses on team effectiveness and efficiency.

  546. Question 546 of 554Which event is the most appropriate for discussing or updating the Definition of Done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. During the Sprint Retrospective

    The Sprint Retrospective is the designated event for inspecting how the team works and adapting their processes, making it ideal for updating the Definition of Done. Modifying quality standards during planning or daily events distracts from the primary focus of those events.

  547. Question 547 of 554What should happen if an item in the Sprint Backlog cannot be completed in the current Sprint?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. The item is evaluated based on the team's rules for estimates and prioritization and then placed back into the Product Backlog.

    Unfinished Sprint Backlog items are returned to the Product Backlog so the Product Owner can re-evaluate and reorder them. This maintains transparency and ensures work meets the Definition of Done before release.

  548. Question 548 of 554In the Sprint Review, the purpose of presenting the product Increment to stakeholders is to:

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. To elicit feedback

    Presenting the Increment is primarily intended to elicit feedback from stakeholders and foster collaboration. A common exam trap is confusing this event with a status meeting or a formal sign-off, which goes directly against the empiricism Scrum relies on.

  549. Question 549 of 554The Developers' Daily Scrum is consistently taking longer than 15 minutes. Which statement best describes what should be done?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. The Scrum Master should facilitate the event in a way that keeps it to the time box

    The Scrum Master is responsible for ensuring that Scrum events occur and are kept within their time boxes. The Scrum Master should help the Developers understand the purpose of the Daily Scrum so they can keep it under 15 minutes without ending abruptly.

  550. Question 550 of 554Which factor(s) should be considered when deciding to release an increment?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: D. All answers are some possible things that should be considered when deciding to release an increment

    Releasing an Increment involves multiple business considerations like risk, cost, benefits, and customer readiness. Remember that releasing can happen multiple times within a Sprint, and the decision is driven by maximizing value rather than waiting strictly for the Sprint Review.

  551. Question 551 of 554What activities occur during the Sprint Review?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. 1) The Scrum Team explains what has been "Done" and what has not been "Done"; 2) The Developers demonstrate the "Done" work; 3) The Product Owner discusses the current state of the product backlog; 4) They all review any changes to the marketplace or business that may impact the potential of the product;

    The Sprint Review involves inspecting the increment and collaborating with stakeholders on the next steps. Option A incorrectly describes the Retrospective. Option B incorrectly focuses on pre-planning the next Sprint rather than reviewing the current outcome.

  552. Question 552 of 554When several Scrum Teams are working on the same product, what is the most important concern from the list below?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Reducing / eliminating dependencies between the different Scrum Teams.

    Minimizing dependencies between teams is crucial because it reduces bottlenecks and allows each team to deliver value independently. Synchronizing Sprint cadence is often helpful, but managing dependencies is the primary structural concern for multiple teams building a single product.

  553. Question 553 of 554The Developers cannot deliver the Increment because they don't understand a functional requirement. What should they do?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: C. Collaborate with the Product Owner to solve the problem

    Developers should collaborate directly with the Product Owner to clarify functional requirements and determine the next best step. Unilaterally moving work to a future Sprint without this conversation breaks transparency and bypasses the accountability of managing the backlog.

  554. Question 554 of 554What measure will you most likely use for calculating the velocity of the Team?

    Tap an answer — you get instant feedback and the reasoning.

    Show answer & explanation

    Correct answer: A. Story Points

    Story points are the most common relative measure used for velocity in agile practices, though the 2020 Scrum Guide moved away from standardized estimates. Remember that Scrum does not mandate specific estimation techniques, making this a complementary agile question.